Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 12 months from the original
7 of 11Construction stages donefurthest along: Internal walls, 50%
20 of 54Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

TIRUPATI APARTMENTS CHSL is a Residential / Group Housing project by TIRUPATI APARMTNETS CO OPERATIVE HOUSING SOCIETY LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800048581 on 10 Jan 2023. Possession is promised by 31 Oct 2026. The completion date has moved by 12 months from the original filing. 34 of the 54 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameTIRUPATI APARTMENTS CHSL
  • TypeResidential / Group Housing
  • Location
    • LALA DEVIDAYAL CROSS ROAD
    • MULUND WEST
    • Mulund
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • RERA no.P51800048581
  • ReraGenie IDRG-MH-35927

Builder

  • NameTIRUPATI APARMTNETS CO OPERATIVE HOUSING SOCIETY LIMITED
  • Entity typeSociety
  • ChairpersonDILIP VELJI SHAH
  • SecretoryAJITKUMAR LAXMIDAS LAKHANI

Key dates

this monthRegisteredJan 2023First promiseOct 2025Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Jan 2023
  • Promised completion31 Oct 2026
  • Revised completionRevised to 31 Oct 2026 (originally 31 Oct 2025)
  • Buildings1 building record
  • Documents filed67 files

Current status

63%34 of 54 units booked
82.0%Work done, per cost certificate

Figures as on 23 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TIRUPATI APARTMENTSNA211754054

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 50%.

TIRUPATI APARTMENTS: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,672 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on31 Oct 2025

Approvals and building plan

Sanctioning authorityBrihanmumbai Municipal Corporation
Permissible FSI3609.62
Proposed, not sanctioned3,610 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMULUND WEST
Estimated costRs 19.60 cr
Cost incurredRs 16.08 cr
Work done82.02%
BuildingWingEstimatedIncurred
TIRUPATI APARTMENTSNARs 13.85 crRs 13.78 cr
-NARs 5.75 crRs 2.30 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKUNJ RAMBHIA ARCHITECTS
ArchitectTiwaskar & Associates
EngineerJ W CONSULTANTS
EngineerJayant Prakash Joshi
Chartered AccountantCHIRG SAIYA AND ASSOCIATES
Chartered AccountantSachin Dutikrishna Mahanty
Chartered AccountantS V Paresh & Co
PartnerRole in project
TIRUPATI APARMTNETS CO OPERATIVE HOUSING SOCIETY LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA07112518272Oct 2025 → Oct 2026

Reason as filed by the promoterThis is due to the uncertain supply of construction materials, Shortage of skilled labour and Delay in society approval, therefore we are applying for Extension of the project till 31/10/2026

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2026

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: For Tirupati CHS - Form 1.pdf23 Jul 2026
Withdrawal Update Form 2File: For Tirupati CHS - Engineers Certificate -Q1.pdf23 Jul 2026
Withdrawal Update Form 3File: Tirupati_Form 3 Q1_compressed.pdf23 Jul 2026
Withdrawal Update Form 1File: FORM - 1 (1).pdf17 Jun 2026
Withdrawal Update Form 2File: FORM 2 (6).pdf17 Jun 2026
Withdrawal Update Form 3File: FORM 3 (43)_compressed.pdf17 Jun 2026
Withdrawal Update Form 1File: Architect Form 1 Tirupati 27-10-2025.pdf2 Dec 2025
Withdrawal Update Form 1File: Architect Form 1 Tirupati 27-10-2025.pdf2 Dec 2025
Withdrawal Update Form 2File: Engineer Form 2 Tirupati 27-10-2025.pdf2 Dec 2025
Withdrawal Update Form 2File: Engineer Form 2 Tirupati 27-10-2025.pdf2 Dec 2025
Withdrawal Update Form 3File: Revised Form 3 Tirupati Final upto Q2.pdf2 Dec 2025
Withdrawal Update Form 3File: Revised Form 3 Tirupati Final upto Q2.pdf2 Dec 2025
Withdrawal Update Form 1File: Architect Form 1 Tirupati 23-07-2025.pdf7 Nov 2025
Withdrawal Update Form 1File: Architect Form 1 Tirupati 27-10-2025.pdf7 Nov 2025
Withdrawal Update Form 2File: Engineer Form 2 Tirupati 24-07-2025.pdf7 Nov 2025
Withdrawal Update Form 2File: Engineer Form 2 Tirupati 27-10-2025.pdf7 Nov 2025
Withdrawal Update Form 3File: Revised Form 3 Final Tirupati Final upto Q1.pdf7 Nov 2025
Withdrawal Update Form 3File: Revised Form 3 Tirupati Final upto Q2.pdf7 Nov 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Tirupati 17-04-2025.pdf22 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Tirupati-3.pdf22 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 Tirupati 17-04-2025.pdf22 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Tirupati 09-01-2025.pdf21 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tirupati.pdf21 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 Tirupati 09-01-2025.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Tirupati 08-10-2024.pdf25 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Tirupati Final-2.pdf25 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 Tirupati 08-10-2024.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Tirupati 05-04-2024.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 Tirupati 05-04-2024.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Tirupati.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Tirupati 06-01-2024.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 Tirupati 06-01-2024.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tirupati.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Tirupati 04-10-2023.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 Tirupati 04-10-2023.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Tirupati Final.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form5_Tirupati_22-23.pdf29 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Tirupati 07-07-2023.pdf18 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 Tirupati 07-07-2023.pdf18 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tirupati Final (1).pdf18 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tirupati Final.pdf12 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Tirupati 08-04-2023.pdf21 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 Tirupati 12-04-2023.pdf21 Apr 2023
Other - LegalFile: Interest declaration revised.pdf5 Jan 2023
Copy of the legal title reportFile: Title Certificate tirupati.pdf4 Jan 2023
Copy of the legal title reportFile: Annexure Title Certificate tirupati.pdf4 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest declaration.pdf3 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: TIRUPATI SOCIETY REGISTRAR COMP.pdf3 Jan 2023
Deviation Report with respect to Allotment letterFile: Deviations.pdf6 Dec 2022
Deviation Report with respect to model copy of AgreementFile: Deviations.pdf6 Dec 2022
Declaration in FORM BFile: 1 (1).pdf23 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 Tirupati 15-11-2022.pdf22 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Tirupati.pdf22 Nov 2022
Layout approvalFile: Tirupati IOD Drawing (1).pdf12 Nov 2022
Building plan approvalFile: Tirupati IOD Drawing (1).pdf12 Nov 2022
Details of encumbrances concerned to FinanceFile: Encumbrances Tirupati.pdf12 Nov 2022
Details of encumbrances concerned to LegalFile: Encumbrances Tirupati.pdf12 Nov 2022
Copy of Layout Approval (in case of layout)File: Tirupati IOD Drawing (1).pdf12 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Tirupati IOD Drawing (1).pdf12 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: Tirupati First CC.pdf12 Nov 2022
Declaration about Commencement CertificateFile: Form D Tirupati.pdf12 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Tirupati 12-10-2022.pdf12 Nov 2022
CERSAI detailsFile: CERSAI_Search_Report_200251984394_For_Asset_Based_Search_12_11_2022_16_51_30_514.pdf12 Nov 2022
Proforma of Allotment letterFile: Allotment Letter tirupati CHSL.pdf12 Nov 2022
Proforma of Agreement for saleFile: TIRUPATI RERA MODEL Copy of Agreement.pdf12 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - Tirupati.pdf12 Nov 2022
PAN CardFile: pan.pdf7 Nov 2022

How this compares with Mumbai Suburban

63%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TIRUPATI APARTMENTS CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MULUND WEST6,700+ in Mumbai Suburban

Builder: TIRUPATI APARMTNETS CO OPERATIVE HOUSING SOCIETY LIMITED

TIRUPATI APARMTNETS CO OPERATIVE HOUSING SOCIETY LIMITED has 1 registration on MahaRERA, including TIRUPATI APARTMENTS CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if TIRUPATI APARTMENTS CHSL is delayed beyond 31 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TIRUPATI APARTMENTS CHSL?

The registered promoter entity is TIRUPATI APARMTNETS CO OPERATIVE HOUSING SOCIETY LIMITED, a society as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TIRUPATI APARTMENTS CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TIRUPATI APARTMENTS CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TIRUPATI APARTMENTS CHSL?

The professionals named in the filing: Architect: KUNJ RAMBHIA ARCHITECTS; Architect: Tiwaskar & Associates; Engineer: J W CONSULTANTS; Engineer: Jayant Prakash Joshi; Chartered Accountant: CHIRG SAIYA AND ASSOCIATES; Chartered Accountant: Sachin Dutikrishna Mahanty. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TIRUPATI APARTMENTS CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TIRUPATI APARTMENTS CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TIRUPATI APARTMENTS CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.