ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / THE PEARL

Registration lapsed No litigation declared Others project

THE PEARL

By LIMRA PROPERTIES

RG-MH-63668 · RERA P52100045713 · Last updated on MahaRERA portal: 3 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 15 months past the filed date
  • 3 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2025Possession promised15 months past this date
4 of 11Construction stages donefurthest along: Internal walls, 95%
10 of 13Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

THE PEARL is a Others project by LIMRA PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100045713 on 6 Jun 2022. Possession was promised by 31 Jul 2025 and is now 15 months past that date. 3 of the 13 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameTHE PEARL
  • TypeOthers
  • Location
    • KAUSAR BAUG STREET
    • KAUSAR BAUG
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100045713
  • ReraGenie IDRG-MH-63668

Builder

  • NameLIMRA PROPERTIES
  • Entity typePartnership
  • PartnersLIYAQAT NASSER MOHAMMAD KHAN, AZIZ ABDUL RAUF A R A S SHAIKH SHAIKH

Key dates

15 months past promisethis monthRegisteredJun 2022PromisedJul 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Jun 2022
  • Promised completion31 Jul 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed29 files

Current status

23%3 of 13 units booked
95.0%Work done, per cost certificate

Figures as on 3 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
THE PEARLNA745813

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

THE PEARL: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.35%

Progress on shared amenities15

As on 3 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes45%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes45%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area811 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on31 Jul 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI2002.96
Proposed, not sanctioned758 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKRISHNAKEKAVALI COMPLEX, MAIN KONDHWA ROAD
Estimated costRs 2.29 cr
Cost incurredRs 2.18 cr
Work done95.0%
BuildingWingEstimatedIncurred
THE PEARLNARs 2.29 crRs 2.18 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectZUBAIR BARASKAR
EngineerPagdiwale Sohail Sadique
Chartered AccountantDBT & ASSOCIATES
PartnerRole in project
LIMRA PROPERTIES-

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12501789Aslam Sattar MemonLIMRA PROPERTIES30/05/2025
CC12501788Mehrunnisa Abdul Sattar MemonLIMRA PROPERTIES30/05/2025
CC12601155Asmanaz Imran KhanLIMRA PROPERTIES02/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A FY 25-26.pdf3 Jul 2026
Withdrawal Update Form 1File: Form 1 Architect Q2.pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 25-26 Engineer (1).pdf8 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Q2 25-26.pdf8 Apr 2026
Form 1File: Q1 Architect.pdf14 Aug 2025
Form 2File: Form-2 Q4 with sign and stamp.pdf14 Aug 2025
Form 3File: Q4 Form 3.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory (1).pdf14 Aug 2025
Form 1File: Form 1 Q3 2024-25.pdf1 Aug 2025
Form 2File: Form 2 Final.pdf1 Aug 2025
Form 3File: Form 3 Final.pdf1 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory (1).pdf1 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 limra properties.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Limra Properties.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Limra Properties.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate_compressed.pdf26 May 2022
Layout approvalFile: 7KB Commercial Plan FRESH.pdf24 May 2022
Building plan approvalFile: KB COMMENCEMENT_compressed.pdf24 May 2022
Copy of Layout Approval (in case of layout)File: 7KB Commercial Plan FRESH.pdf24 May 2022
Building Plan Approval / NA Order for plotted developmentFile: KB COMMENCEMENT_compressed.pdf24 May 2022
Commencement Certificates / NA Order for plotted developmentFile: KB COMMENCEMENT_compressed.pdf24 May 2022
Proforma of Allotment letterFile: allotment letter draft.pdf21 May 2022
PAN CardFile: 1 PAN Card.pdf20 May 2022
Copy of the legal title reportFile: 1 Copy of the legal title report.pdf20 May 2022
Details of encumbrancesFile: Encumbrances.pdf20 May 2022
Declaration about Commencement CertificateFile: format D.pdf20 May 2022
Declaration in FORM BFile: form B_compressed.pdf20 May 2022
CERSAI detailsFile: cersai report.pdf20 May 2022
Proforma of Allotment letterFile: agreement format rera.pdf20 May 2022

How this compares with Pune

23%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE PEARL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KAUSAR BAUG13,700+ in Pune

2 kmTHE PEARLCompleted 49Lapsed / revoked 31Other 83Dot size: filed unitsN

Filed coordinates, straight-line distance. 163 registered projects within 2 km.

Builder: LIMRA PROPERTIES

LIMRA PROPERTIES has 1 registration on MahaRERA, including THE PEARL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that THE PEARL shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if THE PEARL is delayed beyond 31 Jul 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE PEARL?

The registered promoter entity is LIMRA PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE PEARL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against THE PEARL?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for THE PEARL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE PEARL?

The professionals named in the filing: Architect: ZUBAIR BARASKAR; Engineer: Pagdiwale Sohail Sadique; Chartered Accountant: DBT & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE PEARL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE PEARL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE PEARL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.