Home / Browse projects / Thane, Maharashtra / THE PARK

Registration lapsed No litigation declared Residential / Group Housing project

THE PARK

By NAYANTARA

RG-MH-04095 · RERA P51700021197 · Last updated on MahaRERA portal: 27 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 34 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
8 of 11Construction stages donefurthest along: Staircases, 80%
0Complaints at MahaRERAon this registration
Jump to the 91 documents Report an error

THE PARK is a Residential / Group Housing project by NAYANTARA in Thane, Maharashtra, registered with MahaRERA as P51700021197 on 14 Jun 2019. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 34 months from the original filing.

At a glance

Project

  • NameTHE PARK
  • TypeResidential / Group Housing
  • Location
    • AAYRE ROAD
    • AAYRE GAON
    • Kopar Road
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700021197
  • ReraGenie IDRG-MH-04095

Builder

  • NameNAYANTARA
  • Entity typePartnership
  • GSTIN27AAPFN7780H2ZK
  • PartnersSARAVANAN SHANKARAN NADAR, ARCHIT ABHAY KAMAT, VISHAL NARAHARI PATIL, RAJU VITTHAL KALAN, CHANDRAKANT ETWAR PATIL

Key dates

7 months past promisethis monthRegisteredJun 2019First promiseMay 2023Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Jun 2019
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 30 May 2023)
  • Buildings1 building record
  • Documents filed91 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
THE PARKNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 80%.

THE PARK: 85% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 27 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Open Space5

Land and ownership8

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,040 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 May 2026
LandownerVillageDistrict
HEMANT NARAYAN MHATREKopar RoadThane
MANISHA KESHAV PATILDOMBIVLIThane
INDUBAI KISAN PATILNANDIVALIThane
BALARAM KRUSHNA PATILDOMBIVLIThane
RAJASHRI BALARAM PATILDOMBIVLIThane
KRUSHAN SUKRYA PATILDOMBIVLIThane
CHANDRABAI KRUSHNA PATILDOMBIVLIThane
YUKTA BALARAM PATILDOMBIVLIThane

Approvals and building plan

Sanctioning authorityKALYAN DOMBIVLI MUNICIPAL CORPORATION
Permissible FSI1275.29
Proposed, not sanctioned799 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHREEJI ARCADE PHADKE ROAD MADAN THAKRE CHOWK DOMBIVLI EAST 421201

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUDAY MANSUKHLAL CHOPDA MANSUKHLAL CHOPDA
EngineerSHANTI CONSULTANT ARVIND PATEL
Chartered AccountantNAYAK DESHPANDE AND CO KAMLESH DESHPANDE
PartnerRole in project
NAYANTARA-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700016852May 2023 → Dec 2024

Reason as filed by the promoterWORK IN PROGRESS DUE TO MATERAIL AND LABOUR SHORTAGE IN BETWEEN PANDEMIC SITUATION WORK PERIOD EXTEND

EXT51700025762May 2023 → Mar 2026

Reason as filed by the promoterAPPROVAL AND FINISHING WORK IS PENDING DUE TO SHORTAGE OF MAT AND LABOUR

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed91

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: form no 1 the park.pdf27 May 2026
Form 2File: form no 02 the park.pdf27 May 2026
Form 3File: form no 3 the park.pdf27 May 2026
Disclosure of Sold and Booked InventoryFile: sold unsold the park.pdf27 May 2026
Form 1File: nayantara f-1.pdf4 Mar 2026
Form 2File: nayantara f-2.pdf4 Mar 2026
Form 3File: nayantara f-3.pdf4 Mar 2026
Disclosure of Sold and Booked InventoryFile: nayantara s-u.pdf4 Mar 2026
Form 1File: NAYANTARA 1.pdf25 Nov 2025
Form 2File: NAYANTARA 2.pdf25 Nov 2025
Form 3File: NAYANTARA 3.pdf25 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD PARK.pdf25 Nov 2025
Form 1File: The Park Architect certificate form 1 30-6-25_0001.pdf19 Jul 2025
Form 2File: The Park Engineers certificate form 2 30-6-25_0001.pdf19 Jul 2025
Form 3File: The Park CA certificate form 3 30-6-25_.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: fffff.pdf19 Jul 2025
Form 1File: FORM NO 01 MARCH 2025.pdf16 Jul 2025
Form 2File: FORM NO 02 MARCH 2025.pdf16 Jul 2025
Form 3File: FORM 3 MARCH 2025.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSLOD.pdf16 Jul 2025
Other - TechnicalFile: IMG_0002.pdf8 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Nayantara The Park CA form 5_0001 (1).pdf2 Apr 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Nayantara TThe Park RERA IDBI bank format B _0001 (1).pdf2 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Nayantara The Park disclosure for secured-unsecured finance_0001.pdf2 Apr 2025
Layout approvalFile: NAYANTARA THE PARK BLUE PRINT PLAN (1) - converted.pdf1 Apr 2025
Layout approvalFile: NAYANTARA THE PARK REVISED PLAN (1) - converted.pdf1 Apr 2025
Building plan approvalFile: Nayantara Hemant mhatre revised bandhkam parvangi.pdf1 Apr 2025
Copy of Layout Approval (in case of layout)File: NAYANTARA THE PARK REVISED PLAN (1) - converted.pdf1 Apr 2025
Copy of Layout Approval (in case of layout)File: NAYANTARA THE PARK BLUE PRINT PLAN (1) - converted.pdf1 Apr 2025
Proforma of Allotment letterFile: Nayantara The Park Allotment letter Annexure 1_0001 - converted.pdf1 Apr 2025
Declaration in FORM BFile: Nayantara The Park Declaration affidavit form B Prashant Shukla _0001.pdf1 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Nayantara The Park Architect certificate form 1_0001.pdf1 Apr 2025
Certificates of CA (Form 3)File: Nayantara The Park Form 3 CA certificate_0001 - converted.pdf1 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nayantara The Park Form 2 Envineers certificate_0001.pdf1 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: Nayantara Hemant mhatre revised bandhkam parvangi.pdf1 Apr 2025
Building Plan Approval (IOD)File: Nayantara Hemant mhatre revised bandhkam parvangi.pdf1 Apr 2025
Other - LegalFile: Nayantara The Park Annexure A declaration cum undertaking_0001.pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: Nayantara The Park disclosure of sold unsold inventory_0001.pdf1 Apr 2025
CERSAI detailsFile: Nayantara The Park Cersai letter_0001.pdf1 Apr 2025
Other - FinanceFile: Nayantara The Park Format A.pdf1 Apr 2025
Other - FinanceFile: Nayantara The Park Declaration about separate bank account_0001.pdf1 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Nayantara The Park Annexure A disclosure of other real estate_0001.pdf1 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Nayantara The Park Prashant shukla Annexure A disclosure of other real estate_0001.pdf1 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Certificate The Park_0001.pdf21 Dec 2024
Disclosure of sold/ booked inventoryFile: Form 1 Architects Certificate The Park_0002.pdf21 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Engineers Certificate The Park_0001.pdf21 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Nayantara The Park Form 2A 2019-2020_0001.pdf8 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Nayantara The Park Form 2A 2020-2021_0001.pdf8 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Nayantara The Park Form 2A 2021-2022_0001.pdf8 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Nayantara The Park Form 2A 2022-2023_0001.pdf8 Jan 2024
Disclosure of sold/ booked inventoryFile: Nayantara The Park Disclosure sold inventory_0001.pdf8 Jan 2024
Certificates of CA (Form 3)File: the park form 3_0001 (1).pdf8 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Nayantara The Park CA Form 5 31-3-20_0001.pdf8 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Nayantara The Park CA Form 5 31-3-20_0001.pdf8 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Nayantara The Park CA Form 5 31-3-22_0001.pdf8 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Nayantara The Park CA Form 5 31-3-23_0001.pdf8 Jan 2024
Declaration about Commencement CertificateFile: Nayantara Format D 1_0001.pdf6 Jan 2024
Declaration about Commencement CertificateFile: Nayantara Format D 2_0001.pdf6 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nayantara The Park Form no 2 Engineer certificate_0001.pdf6 Jan 2024
Proforma of Agreement for saleFile: DRAFT SALE AGREEMENT- THE PARK Blank.pdf6 Jan 2024
Proforma of Allotment letterFile: Nayantara model form of Allotment letter _0001 (1).pdf6 Jan 2024
Details of encumbrances concerned to FinanceFile: Nayantara Encumbrance to Finance_0001 (2 files merged).pdf14 Sep 2023
Details of encumbrances concerned to LegalFile: Nayantara Encumbrance to Finance_0001 (2 files merged).pdf14 Sep 2023
Declaration about Commencement CertificateFile: Nayantara Declaration commencement certificate.pdf14 Sep 2023
Declaration in FORM BFile: Nayantara Declaration form B Prashant Shukla.pdf14 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: latest rera architect certificate.pdf14 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project) (1) (1).pdf14 Sep 2023
Disclosure of sold/ booked inventoryFile: Nayantara Disclosure of sold book inventory_0001.pdf14 Sep 2023
CERSAI detailsFile: CERSAI.pdf14 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Nayantara Annexure A.pdf14 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Nayantara Declaration Separate Bank account.pdf14 Sep 2023
Deviation Report with respect to Allotment letterFile: Nayantara Deviation.pdf14 Sep 2023
Deviation Report with respect to model copy of AgreementFile: Nayantara Deviation.pdf14 Sep 2023
Building plan approvalFile: REVISED SANCTION LETTER 1 (2 files merged).pdf14 Aug 2019
Layout approvalFile: MYSCAN_20190814_0001.pdf14 Aug 2019
Copy of Layout Approval (in case of layout)File: MYSCAN_20190814_0001.pdf14 Aug 2019
Building Plan Approval (IOD)File: REVISED SANCTION LETTER 1 (2 files merged).pdf14 Aug 2019
Commencement Certificates / NA Order for plotted developmentFile: REVISED SANCTION LETTER 1 (2 files merged).pdf14 Aug 2019
PAN CardFile: Nayantara Pancard.pdf30 May 2019
Copy of the legal title reportFile: Serch Report.pdf30 May 2019

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 34 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AAYRE GAON7,600+ in Thane

2 kmTHE PARKCompleted 79Lapsed / revoked 71Other 116Dot size: filed unitsN

Filed coordinates, straight-line distance. 266 registered projects within 2 km.

Builder: NAYANTARA

NAYANTARA has 1 registration on MahaRERA, including THE PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that THE PARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if THE PARK is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE PARK?

The registered promoter entity is NAYANTARA, a partnership as per the filing. Its GSTIN 27AAPFN7780H2ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for THE PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE PARK?

The professionals named in the filing: Architect: UDAY MANSUKHLAL CHOPDA MANSUKHLAL CHOPDA; Engineer: SHANTI CONSULTANT ARVIND PATEL; Chartered Accountant: NAYAK DESHPANDE AND CO KAMLESH DESHPANDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.