Home / Browse projects / Thane, Maharashtra / THE ONE PEARL
THE ONE PEARL
RG-MH-99386 · RERA P51700021190 · Last updated on MahaRERA portal: 8 Apr 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 29 months past the filed date
- Completion date moved by 36 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
THE ONE PEARL is a Residential / Group Housing project by Vibha Realtors in Thane, Maharashtra, registered with MahaRERA as P51700021190 on 14 Jun 2019. Possession was promised by 31 May 2024 and is now 29 months past that date. The completion date has moved by 36 months from the original filing.
At a glance
Project
- NameTHE ONE PEARL
- TypeResidential / Group Housing
- Location
- Samaj Mandir Road
- Ekta Nagar
- Chavindra
- Thane
- 421201
- Pincode421201
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700021190
- ReraGenie IDRG-MH-99386
Builder
- NameVibha Realtors
- Entity typePartnership
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Jun 2019
- Promised completion31 May 2024
- Revised completionRevised to 31 May 2024 (originally 28 May 2021)
- Buildings1 building record
- Documents filed42 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| THE ONE PEARL | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 5%.
THE ONE PEARL: 1% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 1% |
| Slabs of Super Structure | 5% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 8 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Lobby | Yes | 0% |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Anirudha Dastane |
| Engineer | Girish Marathe |
| Chartered Accountant | ANIL V KHATU |
| Partner | Role in project |
|---|---|
| Vibha Realtors | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay in projection completion is due to shortage of funds and other technical reasons
Reason as filed by the promoterDue to Pandemic situation and Lockdown from March 2021 to Jun2021 by State GOVT.
Reason as filed by the promoterDue to Lockdown issued by state government
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Oct 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Oct 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Oct 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 26 Oct 2021
Documents filed42
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Vibha Realtors_2021-22.pdf | 8 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 5_2020-21.pdf | 30 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5_2017-18.pdf | 30 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_2018-19.pdf | 30 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_2019-20.pdf | 30 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_2020-21.pdf | 30 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Vibha FY17-18.pdf | 29 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Vibha ITR FY 18-19.pdf | 29 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Vibha ITR FY 19-20 .pdf | 29 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ITR Fy 2020-21.pdf | 26 Mar 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate 2020_compressed.pdf | 14 Dec 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: engineers certificate 2021_compressed.pdf | 14 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventary The one Pearl.pdf | 14 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: ITR Form_FY 2017-18_merged.pdf | 14 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ITR Form_FY 2018-19_merged.pdf | 14 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: ITR Form _FY 2019-20 Merged .pdf | 14 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: CA Certificate Revise VIBHA REALTORS -ONE PEARL.pdf | 26 Oct 2021 |
| Certificates of CA (Form 3)File: CA Certificate Revise VIBHA REALTORS -ONE PEARL.pdf | 26 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FY 17-18.pdf | 26 Oct 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Archcertificate Vibha .pdf | 26 Oct 2021 |
| OtherFile: Engineering certificate Vibha.pdf | 26 Oct 2021 |
| OtherFile: Archcertificate Vibha .pdf | 26 Oct 2021 |
| OtherFile: CA Certificate Revise VIBHA REALTORS -ONE PEARL.pdf | 26 Oct 2021 |
| Declaration about Commencement CertificateFile: Declaration about CC.pdf | 13 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate Vibha.pdf | 13 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate Vibha.pdf | 13 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: Vibha.pdf | 13 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: vibha itr and balance sheet FY1819.pdf | 13 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Vibha Realtors_ITR V-2020-21.pdf | 13 Sep 2021 |
| PAN CardFile: vibha Realtors Pan Card.pdf | 5 Jun 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vibha Architect Certificate original 1.pdf | 5 Jun 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate1.pdf | 5 Jun 2019 |
| Proforma of Allotment letterFile: RERA - Flat sale - Vibha.pdf | 5 Jun 2019 |
| Building plan approvalFile: AProved plan.pdf | 30 Oct 2018 |
| Layout approvalFile: Lay Out Plan.pdf | 30 Oct 2018 |
| Copy of the legal title reportFile: Title Report.pdf | 30 Oct 2018 |
| Details of encumbrancesFile: Details Of Encumbrances.pdf | 30 Oct 2018 |
| Copy of Layout Approval (in case of layout)File: Lay Out Plan.pdf | 30 Oct 2018 |
| Building Plan Approval (IOD)File: AProved plan.pdf | 30 Oct 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Comence ment certificate.pdf | 30 Oct 2018 |
| Declaration in FORM BFile: Declaration Form B.pdf | 30 Oct 2018 |
| Certificates of CA (Form 3)File: CA Certificate.PDF | 30 Oct 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 42 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep THE ONE PEARL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ekta Nagar7,600+ in Thane
Filed coordinates, straight-line distance. 206 registered projects within 2 km.
MY CITY PHASE II CLUSTER 5 PART II
HORIZON PROJECTS PVT LTD
MY CITY PHASE II CLUSTER 5 PART III
HORIZON PROJECTS PVT LTD
Runwal Gardens Phase 3 Bldg No 27-28
Runwal Residency Private Limited
Runwal Gardens Phase 4 Bldg No. 35-36
Runwal Residency Private Limited
VASTU LUXURIA
LAUKIK DEVELOPMENT CORPORATION
KAPLESHWARA RESIDENCY
KAPLESHWARA HOMES LLP
See every Thane project, with the district possession charts
Builder: Vibha Realtors
Vibha Realtors has 1 registration on MahaRERA, including THE ONE PEARL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that THE ONE PEARL shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if THE ONE PEARL is delayed beyond 31 May 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of THE ONE PEARL?
The registered promoter entity is Vibha Realtors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in THE ONE PEARL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for THE ONE PEARL?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at THE ONE PEARL?
The professionals named in the filing: Architect: Anirudha Dastane; Engineer: Girish Marathe; Chartered Accountant: ANIL V KHATU. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in THE ONE PEARL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback