The Metrozone Kingstone D1
By Sanklecha Construction Private Limited
RG-MH-01483 · RERA P51600005201 · Last updated on MahaRERA portal: 27 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 84 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
The Metrozone Kingstone D1 is a Residential / Group Housing project by Sanklecha Construction Private Limited in Nashik, Maharashtra, registered with MahaRERA as P51600005201 on 10 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 84 months from the original filing.
At a glance
Project
- NameThe Metrozone Kingstone D1
- TypeResidential / Group Housing
- Location
- Nashik (M Corp.)
- Nashik
- 422009
- Pincode422009
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600005201
- ReraGenie IDRG-MH-01483
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed73 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Kingstone D1 | NA | 16 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.
Kingstone D1: 49% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 70% |
| Street Lighting | Yes | 75% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 25% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed30
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Anwar Hussain Thim | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | G V Katale & Assocites |
| Partner | Role in project |
|---|---|
| Sanklecha Construction Private Limited | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterdelay in Govt. Permission like Environment & Corporation sanction, New Laws, Covid 19 and Demonetization
Reason as filed by the promoterWe are in process of Increase the floors & area according to the DCPR. Now We Get revised sanction from Nashik Muncipal Corporation. So We are appliing for Extension & Correction in the area of project
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 31/2011 | Civil Judge Senior Division Nashik | Pending on Exhibit hearing |
| 144/2014 | Civil Judge Senior Division Nashik | Pending on Exhibit hearing |
| 744/2012 | Civil Judge Senior Division Nashik | Pending on Exhibit hearing |
| 229/2012 | Civil Judge Senior Division Nashik | Pending on Exhibit hearing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed73
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: 2324 D1 Form 1 Q4.pdf | 27 May 2026 |
| Form 2File: 2324 D1 Form 2 Q4.pdf | 27 May 2026 |
| Form 3File: 2324 D1 Form 3 Q4.pdf | 27 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 2324 D1 Inventory Q4.pdf | 27 May 2026 |
| Form 1File: Q1 2425 D1 Form 1.pdf | 27 May 2026 |
| Form 2File: Q1 2425 D1 Form 2.pdf | 27 May 2026 |
| Form 3File: Q1 2425 D1 Form 3.pdf | 27 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Q1 2425 D1 Inventory.pdf | 27 May 2026 |
| Form 1File: Q4 2425 D1 Form 1.pdf | 27 May 2026 |
| Form 2File: Q4 2425 D1 Form 2.pdf | 27 May 2026 |
| Form 3File: Q4 2425 D1 Form 3.pdf | 27 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Q4 2425 D1 Inventory.pdf | 27 May 2026 |
| Form 1File: Q3 2324 D1 Form 1 Q3.pdf | 27 May 2026 |
| Form 2File: Q3 2324 D1 Form 2 Q3.pdf | 27 May 2026 |
| Form 3File: Q3 2324 D1 Form 3 Q3.pdf | 27 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Q3 2324 D1 Inventory Q3.pdf | 27 May 2026 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: D1 Form 1 2425 Q4.pdf | 14 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: D1 CA Certificate Form 3 2324 Q4_compressed.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: D1 CA Certificate Form 3 2425 Q1_compressed.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: D1 CA Certificate Form 3 2425 Q2_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: D1 CA Certificate Form 3 2324 Q4.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: D1 CA Certificate Form 3 2425 Q1.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: D1 CA Certificate Form 3 2425 Q2.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: D1 Engineer certificate 2324 Q4.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: D1 Engineer certificate 2425 Q1.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: D1 Engineer certificate 2425 Q2.pdf | 29 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold - Booked Inventory D1 2324 Q4.pdf | 29 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold - Booked Inventory D1 2425 Q1.pdf | 29 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer certificate for Quality Assurance.pdf | 29 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: D1 CA Certificate Form 5 2324 Q4.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: D1 Q1.pdf | 20 Feb 2024 |
| Certificates of CA (Form 3)File: D1 Q3.pdf | 20 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 D1 Q1.pdf | 19 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 D1 Q3.pdf | 19 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 D1 Q1.pdf | 19 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 D1 Q3.pdf | 19 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: inventory D1.pdf | 19 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Real Estate Disclosure PAS.pdf | 19 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations TVS.pdf | 19 Feb 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: img00347_compressed.pdf | 24 Oct 2023 |
| Declaration about Commencement CertificateFile: Declartion of Commencement.pdf | 24 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 D1.pdf | 24 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 D1.pdf | 24 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality 1920.pdf | 24 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality 2021.pdf | 24 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality 2122.pdf | 24 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality 2223.pdf | 24 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory D1.pdf | 24 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory D1.pdf | 24 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 D1_compressed.pdf | 24 Oct 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclousure PAS.pdf | 24 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: D1 1920.pdf | 24 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: D1 2021.pdf | 24 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: D1 2122.pdf | 24 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: D1 2223.pdf | 24 Oct 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Disclosure of Bank Account.pdf | 24 Oct 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation of Allottement D1.pdf | 24 Oct 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation of Agreement to Sale D1.pdf | 24 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: D11718.pdf | 27 Nov 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: D11819.pdf | 27 Nov 2020 |
| Certificates of CA (Form 3)File: Form 3 CA D-1.pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: D1.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Kingston D1-1 to 3.pdf | 29 Jul 2017 |
| Layout approvalFile: Metrozone layout-ilovepdf-compressed.pdf | 27 Jul 2017 |
| Building plan approvalFile: Building D1.pdf | 27 Jul 2017 |
| PAN CardFile: SCPL Pan Card.pdf | 27 Jul 2017 |
| Copy of the legal title reportFile: SEARCH REPORT TMZ-ilovepdf-compressed (1).pdf | 27 Jul 2017 |
| Details of encumbrancesFile: Encumbrances MZ.pdf | 27 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Metrozone layout-ilovepdf-compressed.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: Building D1.pdf | 27 Jul 2017 |
| Declaration in FORM BFile: TMZ SCPL kingston d-1-ilovepdf-compressed.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: Agreement - Uploadable Metrozone - D1.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: Letter of Allotment.pdf | 27 Jul 2017 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Mango Woods | Near Punydham Aashram Behind EKTA California NIBM Road Pisoli Pune | 78 | Completed | Jul 2016 | Late, Dec 2016 |
| The Comfort Zone | Near Ambad Talathi Office Ambad Nashik | 152 | Completed | Sep 2014 | Late, May 2017 |
| Garden County | Begind Hotel Jatra Adgaon Nashik | 224 | Completed | Apr 2013 | Late, Sep 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 11 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 73 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep The Metrozone Kingstone D1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nashik (M Corp.)4,100+ in Nashik
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
STAR WORLD
DEEPAK KALYANJI CHANDE
VRAJ CENTRAL VISTA
DHAIRYA DEVELOPERS
ROONGTA TECHONE APARTMENT
SHREE TIRUMALA BUILDCON
VRAJ CAPITAL
KAPILAVASTU CREATORS
MAA BHAGWATI RESIDENCY APARTMENT
ROONGTA LANDMARKS LLP
THREE LEAVES PHASE ONE
DEEPAK INFRA AND HOMES PRIVATE LIMITED
See every Nashik project, with the district possession charts
Builder: Sanklecha Construction Private Limited
Sanklecha Construction Private Limited has 12 registrations on MahaRERA, including Waterways and The Metrozone Athens A1. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if The Metrozone Kingstone D1 is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of The Metrozone Kingstone D1?
The registered promoter entity is Sanklecha Construction Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in The Metrozone Kingstone D1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for The Metrozone Kingstone D1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at The Metrozone Kingstone D1?
The professionals named in the filing: Architect: G V Katale & Assocites. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in The Metrozone Kingstone D1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback