Sanklecha Construction Private Limited: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

Sanklecha Construction Private Limited has 12 registrations in this build, including Waterways and The Metrozone Athens A1. Its filings disclose 3 earlier MahaRERA projects: 0 of 3 past projects completed on time.

12Registrations in this build
3Past projects disclosed
+4 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
WaterwaysNashik, Maharashtra19260%Registered
The Metrozone Athens A1Nashik, Maharashtra--Completed
The Metrozone Athens A2Nashik, Maharashtra--Completed
The Metrozone Athens A3Nashik, Maharashtra--Completed
The Metrozone Hampston B1Nashik, Maharashtra--Completed
The Metrozone Hampston B2Nashik, Maharashtra--Completed
The Metrozone Hampston B3Nashik, Maharashtra--Registration lapsed
The Metrozone Aspen C1Nashik, Maharashtra--Completed
The Metrozone Aspen C2Nashik, Maharashtra--Completed
The Metrozone Aspen C3Nashik, Maharashtra--Completed
The Metrozone Kingstone D1Nashik, Maharashtra--Registered
The Metrozone Kingston D2Nashik, Maharashtra10%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Garden County
30 Apr 20132 Sep 2013+4 months
The Comfort Zone
30 Sep 201417 May 2017+32 months
Mango Woods
31 Jul 201614 Dec 2016+4 months

Frequently asked questions

How do I verify Sanklecha Construction Private Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Sanklecha Construction Private Limited?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.