Home / Browse projects / Nashik, Maharashtra / The Hub-B Wing
The Hub-B Wing
RG-MH-99583 · RERA P51600018129 · Last updated on MahaRERA portal: 16 Apr 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
The Hub-B Wing is a Commercial project by shree balaji developers in Nashik, Maharashtra, registered with MahaRERA as P51600018129 on 10 Oct 2018. The registration is recorded completed; possession was promised by 13 Jun 2023. The completion date has moved by 24 months from the original filing.
At a glance
Project
- NameThe Hub-B Wing
- TypeCommercial
- Location
- Mahatma Nagar Road
- Parijat Nagar
- Nashik
- 422005
- Pincode422005
- RERA no.P51600018129
- ReraGenie IDRG-MH-99583
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on10 Oct 2018
- Promised completion13 Jun 2023
- Revised completionRevised to 13 Jun 2023 (originally 30 Jun 2021)
- Buildings1 building record
- Documents filed45 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| The Hub B-wing | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
The Hub B-wing: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Raghunath Tatyaji Shinde | Nashik | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DHIRAJ TUKARAM WALUNJ |
| Engineer | MILIND RATHI |
| Partner | Role in project |
|---|---|
| shree balaji developers | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to covid crisis, we have had to keep site shutdown for about four months last year and 3 months this year. Even currently we are having trouble regarding material supply at site and unreasonable increase in material cost. Our work would be ready by next year, so request you to grant us extension for one year.
Reason as filed by the promoterThe project is completed and we have obtained the Occupancy Certificate from Nashik Municipal Corporation and we are applying for post facto extension till 13.06.2023.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Sep 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Sep 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Sep 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 8 Jul 2023
Documents filed45
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: Form- B.pdf | 16 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RA Report hub Final.pdf | 22 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - The Hub-B Wing.pdf | 11 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: The hub Form- 2A March 2020.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: The hub Form- 2A March 2021.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: The hub Form-2A March 2022.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: The hub Form- 2A March 2023.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: The hub Form-2A March 2024.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE HUB B WING ARCH CERTIFICATE 101018 TO 310319.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE HUB B WING ARCH CERTIFICATE 010419 TO 310320.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE HUB B WING ARCH CERTIFICATE 010420 TO310321.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE HUB B WING ARCH CERTIFICATE 010421 TO 310322.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE HUB B WING ARCH CERTIFICATE 010422 TO 310323.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE HUB B WING ARCH CERTIFICATE 010423 TO 130623.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: THE HUB B WING ENGR CERTIFICATE 101018 TO 310319.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: THE HUB B WING ENGR CERTIFICATE 010419 TO 310320.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: THE HUB B WING ENGR CERTIFICATE 010420 TO 310321.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: THE HUB B WING ENGR CERTIFICATE 010421 TO 310322.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: THE HUB B WING ENGR CERTIFICATE 010422 TO 310323.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: THE HUB B WING ENGR CERTIFICATE 010423 TO 130623.pdf | 15 Feb 2024 |
| Certificates of CA (Form 3)File: THE HUB B WING CA CERTIFICATE 101018 TO 310319.pdf | 15 Feb 2024 |
| Certificates of CA (Form 3)File: THE HUB B WING CA CERTIFICATE 010419 TO 310320.pdf | 15 Feb 2024 |
| Certificates of CA (Form 3)File: THE HUB B WING CA CERTIFICATE 010420TO 310321.pdf | 15 Feb 2024 |
| Certificates of CA (Form 3)File: THE HUB B WING CA CERTIFICATE 010421 TO 310322.pdf | 15 Feb 2024 |
| Certificates of CA (Form 3)File: THE HUB B WING CA CERTIFICATE 010422 TO 310323.pdf | 15 Feb 2024 |
| Certificates of CA (Form 3)File: THE HUB B WING CA CERTIFICATE 010423 TO 130623.pdf | 15 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: The Hub 21-22.pdf | 6 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: The hub 22-23.pdf | 6 Jan 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration rotated-1-24.pdf | 18 Aug 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration rotated-25-48.pdf | 18 Aug 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 8 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: The hub b wing rera audit FY-18-19 (1).pdf | 6 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: The hub b wing rera audit FY-19-20 (1).pdf | 6 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: The hub b wing rera audit FY-20-21 (1).pdf | 6 Sep 2022 |
| Certificates of CA (Form 3)File: CA CERTIFICATE THE HUB B WING.pdf | 4 Oct 2018 |
| Building plan approvalFile: Building plan 2.pdf | 27 Sep 2018 |
| Layout approvalFile: Layout Scan.PDF | 27 Sep 2018 |
| PAN CardFile: PAN SBD.pdf | 27 Sep 2018 |
| Copy of the legal title reportFile: Title Certificate.pdf | 27 Sep 2018 |
| Details of encumbrancesFile: self declaration- hub_1.pdf | 27 Sep 2018 |
| Copy of Layout Approval (in case of layout)File: Layout Scan.PDF | 27 Sep 2018 |
| Building Plan Approval (IOD)File: Building plan 2.pdf | 27 Sep 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement 2.pdf | 27 Sep 2018 |
| Declaration in FORM BFile: Form B-compressed.pdf | 27 Sep 2018 |
| Proforma of Allotment letterFile: Agreement for Sale The HUB B Wing.pdf | 27 Sep 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 21 other registrations, which the RERA portal never shows together
- All 45 filed documents as one ZIP, foldered, with a manifest
Keep The Hub-B Wing on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Parijat Nagar4,100+ in Nashik
SHREEJI EXCELENCIA
SHREEJI DEVELOPERS
HARI VASANT
Hari Vasant Association of Allottees
NATHSEETA YEOLEKAR COMPLEX
DEEPAK INFRA AND HOMES PRIVATE LIMITED
Aaradhya Nakshatra
SHREYASH BUILDCON
Shri Ram Kunj
shree balaji developers
SAI COURT
JAY WIN DEVELOPERS
See every Nashik project, with the district possession charts
Builder: shree balaji developers
SHREE BALAJI DEVELOPERS has 22 registrations on MahaRERA, including SHREE RESIDENCY and PNT SQUARE. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if The Hub-B Wing is delayed beyond 13 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of The Hub-B Wing?
The registered promoter entity is shree balaji developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in The Hub-B Wing?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for The Hub-B Wing?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at The Hub-B Wing?
The professionals named in the filing: Architect: DHIRAJ TUKARAM WALUNJ; Engineer: MILIND RATHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in The Hub-B Wing?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback