Home / Browse projects / Nashik, Maharashtra / HARI VASANT
HARI VASANT
By Hari Vasant Association of Allottees
RG-MH-00492 · RERA P51600000534 · Last updated on MahaRERA portal: 19 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- 31 complaints at MahaRERA
- Completion date moved by 69 months
- 2 extensions taken
Clear
- No litigation declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HARI VASANT is a Residential / Group Housing project by Hari Vasant Association of Allottees in Nashik, Maharashtra, registered with MahaRERA as P51600000534 on 18 Jul 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 69 months from the original filing. 92 of the 204 units on this registration are recorded sold or booked. 31 complaints are on record with the regulator.
At a glance
Project
- NameHARI VASANT
- TypeResidential / Group Housing
- Location
- AASARAM BABU ASHRAM
- GANGAPUR ROAD
- Aanandwali
- Nashik
- 422005
- Pincode422005
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600000534
- ReraGenie IDRG-MH-00492
Builder
- NameHari Vasant Association of Allottees
- Entity typeAOP/BOI
- Managing DirectorNaresh Jagumal Karda
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Jul 2017
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 31 Dec 2020)
- Buildings2 building records
- Documents filed112 files
Current status
Figures as on 19 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 18 | 17 | 102 | 0 | 102 |
| Building B | NA | 19 | 0 | 102 | 0 | 102 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 19 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building ANot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Building BNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 19 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed366
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building A | 111 | 47 | 158 |
| Building B | 33 | 175 | 208 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MANOJ VASANTRAO ADAYPRABHU | Nashik | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building A | NA | Rs 41.42 cr | Rs 16.57 cr |
| Building B | NA | Rs 41.42 cr | Rs 23.20 cr |
| - | NA | Rs 4.25 cr | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prashant Themaskar |
| Engineer | Hindurao Hambare |
| Chartered Accountant | HSB & CO. |
| Chartered Accountant | CA Priti Nimani |
| Partner | Role in project |
|---|---|
| Hari Vasant Association of Allottees | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThere has been delay in construction due to some unavoidable reason, hence we hereby request you to allow the extension of a period of 12 months as we will strive to complete the project as per new timeline after extension ie 30th December, 2021.
Reason as filed by the promoterDue to unavoidable causes
Complaints filed with MahaRERA31
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC001000000050298 | Mahesh Ramesh Bansod | Naresh karda, karda construction | 25/01/2023 |
| CC001000000060307 | VINITA NITIN GOKHALE | KARDA CONSTRUCTIONS LTD. | 18/03/2023 |
| CC001000000080383 | Ashish Ashok Kataria | KBC GLOBAL LIMITED | 19/10/2023 |
| CC001000000080384 | Ashok Motilal Katariya | KBC GLOBAL LIMITED | 19/10/2023 |
| CC001000000080385 | Ashok Motilal Katariya | KBC GLOBAL LIMITED | 21/10/2023 |
| CC001000000080386 | Asha Ashok Katariya | KBC GLOBAL LIMITED | 21/10/2023 |
| CC001000000080387 | Ashish Ashok Kataria | KBC GLOBAL LIMITED | 21/10/2023 |
| CC001000000080388 | Astha Ashish Kataria | KBC GLOBAL LIMITED | 21/10/2023 |
| CC001000000080389 | Shweta Keyur Modi | KBC GLOBAL LIMITED | 21/10/2023 |
| CC001000000080390 | Astha Ashish Kataria | KBC GLOBAL LIMITED | 21/10/2023 |
| CC001000000080358 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 12/10/2023 |
| CC001000000080359 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 12/10/2023 |
| CC001000000080360 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 12/10/2023 |
| CC001000000080361 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 12/10/2023 |
| CC001000000080362 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 12/10/2023 |
| CC001000000080363 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 12/10/2023 |
| CC001000000080364 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 12/10/2023 |
| CC001000000080365 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 12/10/2023 |
| CC001000000080366 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 13/10/2023 |
| CC001000000080367 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 13/10/2023 |
| CC001000000080368 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 13/10/2023 |
| CC001000000080369 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 13/10/2023 |
| CC001000000080370 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 13/10/2023 |
| CC001000000080371 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 13/10/2023 |
| CC001000000080373 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 13/10/2023 |
| CC001000000080374 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 13/10/2023 |
| CC001000000080372 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 13/10/2023 |
| CC001000000080375 | Ashoka Infraways Limited | KBC GLOBAL LIMITED | 12/10/2023 |
| CC001000000090420 | Anup Subhashchandra Katariya | KBC GLOBAL LIMITED | 10/01/2024 |
| CC12400225 | ANUP S KATARIYA | KBC GLOBAL LIMITED | 25/09/2024 |
| CC12502535 | Hari Vasant Association of Allottees | DHARAN INFRA-EPC LIMITED | 23/07/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed112
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: vasant (2021).pdf | 19 Sep 2026 |
| Withdrawal Update Form 1File: vasant (2021).pdf | 19 Sep 2026 |
| Withdrawal Update Form 1File: vasant (2021).pdf | 19 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 June 2025.pdf | 19 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Sept 2025.pdf | 19 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Dec 2025.pdf | 19 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 June 2025.pdf | 19 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Sept 2025.pdf | 19 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Dec 2025.pdf | 19 Sep 2026 |
| Form 2A (FY 2025-2026)File: Form 2A.pdf | 4 Sep 2026 |
| Form 1File: Form 1 3032026 (2).pdf | 14 Aug 2026 |
| Form 2File: Form 2 (3132026).pdf | 14 Aug 2026 |
| Form 3File: Form 3 march 2026 (2).pdf | 14 Aug 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Building A B (March).pdf | 14 Aug 2026 |
| Form 1File: Form 1 3062026 (2).pdf | 14 Aug 2026 |
| Form 2File: Form 2 (30062026).pdf | 14 Aug 2026 |
| Form 3File: Form 3 June 2026 (2).pdf | 14 Aug 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Building A B (June).pdf | 14 Aug 2026 |
| Certificates of CA (Form 3)File: HARI VASANT FORM 3 310325.pdf | 23 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: HARI VASANT 310325.pdf | 23 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: HARI VASANT MARCH (1).pdf | 8 Apr 2025 |
| Certificates of CA (Form 3)File: Form3-311224.pdf | 7 Apr 2025 |
| Declaration in FORM BFile: Hari Vasant form B.pdf | 4 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3-31032023.pdf | 4 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3-300624.pdf | 4 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3-300924.pdf | 4 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-31032024.pdf | 4 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: HARI VASANT JUNE.pdf | 27 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: HARI VASANT SEPT.pdf | 27 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: HARI VASANT DEC.pdf | 27 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Hari Vasant 311224.pdf | 8 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Hari Vasant 311224.pdf | 8 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Hari Vasant 311224.pdf | 8 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 HARI VASANT 30924.pdf | 7 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 HARI VASANT 30624.pdf | 7 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 HARI VASANT 30924.pdf | 7 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A HARI VASANT 30924.pdf | 7 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A HARI VASANT 30624.pdf | 7 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: HARI VASANT.pdf | 29 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Vasant.pdf | 26 Apr 2024 |
| Details of encumbrancesFile: Encumbrance certificate (1)_page-0001.pdf | 4 Mar 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance certificate finance_page-0001.pdf | 4 Mar 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance certificate finance_page-0001.pdf | 4 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank acc details_page-0001.pdf | 4 Mar 2024 |
| Deviation Report with respect to Allotment letterFile: Encumbrance certificate-model allotment letter_page-0001.pdf | 4 Mar 2024 |
| Deviation Report with respect to model copy of AgreementFile: Encumbrance certificate-model agreement_page-0001.pdf | 4 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Hari vasant.pdf | 24 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Vasant.pdf | 20 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Hari Vasant (2020).pdf | 28 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: vasant (2021).pdf | 28 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Hari Vasant (18).pdf | 28 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Hari Vasant 2020.pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: Hari Vasant (18).pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: Hari Vasant (2020).pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: hari vasant (2021).pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: Hari Vasant (2021).pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: vasant (2022).pdf | 28 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari vasant.pdf | 16 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Vasant.pdf | 11 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari vasant.pdf | 15 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Vasant.pdf | 15 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Hari Vasant.pdf | 17 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Vasant.pdf | 7 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Vasant.pdf | 6 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Vasant.pdf | 6 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Vasant.pdf | 5 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Vasant.pdf | 5 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Vasant.pdf | 20 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Hari Vasant.pdf | 20 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Hari VAsant.pdf | 16 Mar 2023 |
| Details of encumbrancesFile: Hari Vasant_page-0001.pdf | 9 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: HARI VASANT.pdf | 29 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Vasant 2a.pdf | 25 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Hari Vasant.pdf | 12 Feb 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: HARI VASANT.pdf | 22 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Vasant.pdf | 14 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: VASANT.pdf | 14 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Vasant 19-20.pdf | 13 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Vasant 20-21.pdf | 13 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Vasant.pdf | 13 Oct 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 112 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep HARI VASANT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GANGAPUR ROAD4,100+ in Nashik
Filed coordinates, straight-line distance. 124 registered projects within 2 km.
SHREEJI EXCELENCIA
SHREEJI DEVELOPERS
NATHSEETA YEOLEKAR COMPLEX
DEEPAK INFRA AND HOMES PRIVATE LIMITED
Aaradhya Nakshatra
SHREYASH BUILDCON
Shri Ram Kunj
shree balaji developers
SAI COURT
JAY WIN DEVELOPERS
Nisham Infinia
Nisham Developers
See every Nashik project, with the district possession charts
Builder: Hari Vasant Association of Allottees
Hari Vasant Association of Allottees has 1 registration on MahaRERA, including HARI VASANT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if HARI VASANT is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HARI VASANT?
The registered promoter entity is Hari Vasant Association of Allottees, an aop/boi as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HARI VASANT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against HARI VASANT?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for HARI VASANT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HARI VASANT?
The professionals named in the filing: Architect: Prashant Themaskar; Engineer: Hindurao Hambare; Chartered Accountant: HSB & CO.; Chartered Accountant: CA Priti Nimani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HARI VASANT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.