The Eminence II

By Benchmarrk Realty LLP

RG-MH-15907 · RERA P52100024443 · Last updated on MahaRERA portal: 24 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 27 months past the filed date
  • Rs 226.00 crore secured on the land, in favour of IDBI TRUSTEE SHIP SERVICES LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2024Possession promised27 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 80%
4 of 14Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

The Eminence II is a Commercial project by Benchmarrk Realty LLP in Pune, Maharashtra, registered with MahaRERA as P52100024443 on 13 Feb 2020. Possession was promised by 30 Jul 2024 and is now 27 months past that date. 10 of the 14 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameThe Eminence II
  • TypeCommercial
  • Location
    • Kate Wasti
    • Punawale
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100024443
  • ReraGenie IDRG-MH-15907

Builder

  • NameBenchmarrk Realty LLP
  • Entity typePartnership
  • CINU68100PN2025PTC237318
  • GSTIN27AANFB7064Q1ZN
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersBenchmarrk Promoters and Builders Pvt Ltd, Akash Rajendra Pharande, Anil Jayram Pharande, Ramesh Jayram Pharande, Ramesh Jayram Pharande, Anil Jayram Pharande, Akash Rajendra Pharande, Benchmarrk Promoters and Builders Pvt Ltd, Ramesh Jayram Pharande, Anil Jayram Pharande, Akash Rajendra Pharande, Benchmarrk Promoters and Builders Pvt Ltd
  • Other registrations10 more →
  • Completed2 of 11
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

27 months past promisethis monthRegisteredFeb 2020PromisedJul 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on13 Feb 2020
  • Promised completion30 Jul 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed37 files

Current status

71%10 of 14 units booked
54.6%Work done, per cost certificate

Figures as on 24 Jan 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The Eminence IINA6401414

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

The Eminence II: 78% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks76%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.22%

Progress on shared amenities15

As on 24 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,259 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofIDBI TRUSTEE SHIP SERVICES LIMITED
Secured amountRs 226.00 crore
CERSAI search filedYes
Declared on29 May 2026
LandownerVillageDistrict
Farheez Eruch AgaChinchwadPune

Approvals and building plan

Sanctioning authorityPCMC
Permissible FSI1254.47
Proposed, not sanctioned1,254 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNigdi, Pune
Estimated costRs 10.13 cr
Cost incurredRs 5.53 cr
Work done54.63%
BuildingWingEstimatedIncurred
The Eminence IINARs 9.75 crRs 5.26 cr
-NARs 37.88 lakhRs 27.07 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVK:A ARCHITECTURE
EngineerMakarand Mesharam
EngineerAbhijit Shivaji Gaikwad
Chartered AccountantCA Jayant Daharwal
Chartered AccountantFAA & Associates LLP
Chartered AccountantR. Devendra Kumar & Associates
PartnerRole in project
BENCHMARRK REALTY PRIVATE LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 May 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE EMINENCE II_ARCHITECT CERTIFICATE_DECEMBER-24_ FORM-1.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: THE EMINENCE II_SOLD-UNSOLD_DECEMBER-24.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE EMINENCE II_ARCHITECT CERTIFICATE_SEP-24_ FORM-1.pdf9 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: THE EMINENECE II_CA CERTIFICATE_FORM-5_2023-24.pdf15 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE EMINENCE II_FORM-1_SEP-2024.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: THE EMINENCE II_FORM-2_SEP-2024.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Puneville_CA certificate The Eminence II_101024_compressed.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: THE EMINENCE II_SOLD UNSOLD_SEP-2024.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE EMINENCE II_ARCHITECT CERTIFICATE_JUNE-24_ FORM-1.pdf24 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: THE EMINENCE II_ENGINEER CERTIFICATE_JUNE-24_FORM-2.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: TH EMINENCE II_SOLD UN-SOLD_JUNE-24.pdf24 Jul 2024
Declaration in FORM BFile: Form B BRLLP The Eminenance II_rotated_compressed.pdf10 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE EMINENCE II_FORM-1_compressed.pdf19 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 11) THE EMINENCE_II_ER_QUALITY_compressed.pdf19 Jun 2024
Disclosure of sold/ booked inventoryFile: THE EMINENCE II_SOLD UNSOLD_compressed.pdf19 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11_THE EMINENCE II_ARCHITECT CERTIFICATE_MAR-24_compressed.pdf21 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11_THE EMINENCE II_ENGINEER CERTIFICATE_MAR-24_FORM-2_compressed.pdf21 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 9_THE EMINENCE II_QUALITY CERTIFICATE_FORM-2A_2023-24_compressed.pdf13 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 9_THE EMINENCE II_P52100024443_2022-23_compressed.pdf13 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 8_THE EMINENCE II_P52100024443_2020-21.pdf16 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 7_THE EMINENCE II_P52100024443_2019-20.pdf15 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: THE EMINENCE II.pdf15 Oct 2022
Layout approvalFile: LAYOUT PLAN.pdf25 May 2021
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf25 May 2021
PAN CardFile: BRLLP PANCARD.pdf7 Feb 2020
Layout approvalFile: AMENITY-2_1-1.pdf28 Jan 2020
Building plan approvalFile: AMENITY-2_1-2.pdf28 Jan 2020
Building plan approvalFile: AMENITY-2_1-3.pdf28 Jan 2020
Copy of the legal title reportFile: TITLE SEARCH.pdf28 Jan 2020
Details of encumbrancesFile: ENCUMBRANCE.pdf28 Jan 2020
Copy of Layout Approval (in case of layout)File: AMENITY-2_1-1.pdf28 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: AMENITY-2_1-2.pdf28 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: AMENITY-2_1-3.pdf28 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: CC_AMENITY-2.pdf28 Jan 2020
Declaration in FORM BFile: FORM B ANIL SIR.pdf28 Jan 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf28 Jan 2020
Proforma of Allotment letterFile: ALLOTMENT LETTER AND AGREEMENT.pdf28 Jan 2020

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Puneville Phase II Cluster AP52100000440Punawale, Pune-Jul 2017CompletedDec 2023Registered original: Dec 2022Dec 2023
The EminenceP52100022805Punawale, Pune15Oct 2019CompletedSep 2023Sep 2023
Puneville Phase IP52100000441Punawale, Pune-Jul 2017CompletedJun 2022Registered original: Dec 2020Late, Jun 2024

How this compares with Pune

71%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Eminence II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Punawale13,700+ in Pune

2 kmThe Eminence IICompleted 104Lapsed / revoked 28Other 100Dot size: filed unitsN

Filed coordinates, straight-line distance. 232 registered projects within 2 km.

Builder: Benchmarrk Realty LLP

Benchmarrk Realty LLP has 11 registrations on MahaRERA, including Puneville Phase I and Puneville Phase II Cluster A. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that The Eminence II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if The Eminence II is delayed beyond 30 Jul 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Eminence II?

The registered promoter entity is Benchmarrk Realty LLP, a partnership as per the filing. Its CIN U68100PN2025PTC237318 and GSTIN 27AANFB7064Q1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Eminence II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for The Eminence II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Eminence II?

The professionals named in the filing: Architect: VK:A ARCHITECTURE; Engineer: Makarand Mesharam; Engineer: Abhijit Shivaji Gaikwad; Chartered Accountant: CA Jayant Daharwal; Chartered Accountant: FAA & Associates LLP; Chartered Accountant: R. Devendra Kumar & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Eminence II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Eminence II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Eminence II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.