Home / Browse projects / Pune, Maharashtra / The Eminence II
The Eminence II
RG-MH-15907 · RERA P52100024443 · Last updated on MahaRERA portal: 24 Jan 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 27 months past the filed date
- Rs 226.00 crore secured on the land, in favour of IDBI TRUSTEE SHIP SERVICES LIMITED
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
The Eminence II is a Commercial project by Benchmarrk Realty LLP in Pune, Maharashtra, registered with MahaRERA as P52100024443 on 13 Feb 2020. Possession was promised by 30 Jul 2024 and is now 27 months past that date. 10 of the 14 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.
At a glance
Project
- NameThe Eminence II
- TypeCommercial
- Location
- Kate Wasti
- Punawale
- Mulshi
- Pune
- 411033
- Pincode411033
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100024443
- ReraGenie IDRG-MH-15907
Builder
- NameBenchmarrk Realty LLP
- Entity typePartnership
- CINU68100PN2025PTC237318
- GSTIN27AANFB7064Q1ZN
- CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersBenchmarrk Promoters and Builders Pvt Ltd, Akash Rajendra Pharande, Anil Jayram Pharande, Ramesh Jayram Pharande, Ramesh Jayram Pharande, Anil Jayram Pharande, Akash Rajendra Pharande, Benchmarrk Promoters and Builders Pvt Ltd, Ramesh Jayram Pharande, Anil Jayram Pharande, Akash Rajendra Pharande, Benchmarrk Promoters and Builders Pvt Ltd
- Other registrations10 more →
- Completed2 of 11
- No longer live3 lapsed, de-registered or revoked
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on13 Feb 2020
- Promised completion30 Jul 2024
- Revised completionNone
- Buildings1 building record
- Documents filed37 files
Current status
Figures as on 24 Jan 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| The Eminence II | NA | 6 | 4 | 0 | 14 | 14 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.
The Eminence II: 78% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 76% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 22% |
Progress on shared amenities15
As on 24 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 30% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 20% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Farheez Eruch Aga | Chinchwad | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| The Eminence II | NA | Rs 9.75 cr | Rs 5.26 cr |
| - | NA | Rs 37.88 lakh | Rs 27.07 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VK:A ARCHITECTURE |
| Engineer | Makarand Mesharam |
| Engineer | Abhijit Shivaji Gaikwad |
| Chartered Accountant | CA Jayant Daharwal |
| Chartered Accountant | FAA & Associates LLP |
| Chartered Accountant | R. Devendra Kumar & Associates |
| Partner | Role in project |
|---|---|
| BENCHMARRK REALTY PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 May 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jan 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed37
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE EMINENCE II_ARCHITECT CERTIFICATE_DECEMBER-24_ FORM-1.pdf | 24 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: THE EMINENCE II_SOLD-UNSOLD_DECEMBER-24.pdf | 24 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE EMINENCE II_ARCHITECT CERTIFICATE_SEP-24_ FORM-1.pdf | 9 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: THE EMINENECE II_CA CERTIFICATE_FORM-5_2023-24.pdf | 15 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE EMINENCE II_FORM-1_SEP-2024.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: THE EMINENCE II_FORM-2_SEP-2024.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Puneville_CA certificate The Eminence II_101024_compressed.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: THE EMINENCE II_SOLD UNSOLD_SEP-2024.pdf | 16 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE EMINENCE II_ARCHITECT CERTIFICATE_JUNE-24_ FORM-1.pdf | 24 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: THE EMINENCE II_ENGINEER CERTIFICATE_JUNE-24_FORM-2.pdf | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: TH EMINENCE II_SOLD UN-SOLD_JUNE-24.pdf | 24 Jul 2024 |
| Declaration in FORM BFile: Form B BRLLP The Eminenance II_rotated_compressed.pdf | 10 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: THE EMINENCE II_FORM-1_compressed.pdf | 19 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 11) THE EMINENCE_II_ER_QUALITY_compressed.pdf | 19 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: THE EMINENCE II_SOLD UNSOLD_compressed.pdf | 19 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11_THE EMINENCE II_ARCHITECT CERTIFICATE_MAR-24_compressed.pdf | 21 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11_THE EMINENCE II_ENGINEER CERTIFICATE_MAR-24_FORM-2_compressed.pdf | 21 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 9_THE EMINENCE II_QUALITY CERTIFICATE_FORM-2A_2023-24_compressed.pdf | 13 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 9_THE EMINENCE II_P52100024443_2022-23_compressed.pdf | 13 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 8_THE EMINENCE II_P52100024443_2020-21.pdf | 16 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 7_THE EMINENCE II_P52100024443_2019-20.pdf | 15 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: THE EMINENCE II.pdf | 15 Oct 2022 |
| Layout approvalFile: LAYOUT PLAN.pdf | 25 May 2021 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf | 25 May 2021 |
| PAN CardFile: BRLLP PANCARD.pdf | 7 Feb 2020 |
| Layout approvalFile: AMENITY-2_1-1.pdf | 28 Jan 2020 |
| Building plan approvalFile: AMENITY-2_1-2.pdf | 28 Jan 2020 |
| Building plan approvalFile: AMENITY-2_1-3.pdf | 28 Jan 2020 |
| Copy of the legal title reportFile: TITLE SEARCH.pdf | 28 Jan 2020 |
| Details of encumbrancesFile: ENCUMBRANCE.pdf | 28 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: AMENITY-2_1-1.pdf | 28 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: AMENITY-2_1-2.pdf | 28 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: AMENITY-2_1-3.pdf | 28 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: CC_AMENITY-2.pdf | 28 Jan 2020 |
| Declaration in FORM BFile: FORM B ANIL SIR.pdf | 28 Jan 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 28 Jan 2020 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER AND AGREEMENT.pdf | 28 Jan 2020 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Puneville Phase II Cluster AP52100000440 | Punawale, Pune | - | Jul 2017 | Completed | Dec 2023Registered original: Dec 2022 | Dec 2023 |
| The EminenceP52100022805 | Punawale, Pune | 15 | Oct 2019 | Completed | Sep 2023 | Sep 2023 |
| Puneville Phase IP52100000441 | Punawale, Pune | - | Jul 2017 | Completed | Jun 2022Registered original: Dec 2020 | Late, Jun 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 10 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 37 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep The Eminence II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Punawale13,700+ in Pune
Filed coordinates, straight-line distance. 232 registered projects within 2 km.
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: Benchmarrk Realty LLP
Benchmarrk Realty LLP has 11 registrations on MahaRERA, including Puneville Phase I and Puneville Phase II Cluster A. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that The Eminence II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if The Eminence II is delayed beyond 30 Jul 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of The Eminence II?
The registered promoter entity is Benchmarrk Realty LLP, a partnership as per the filing. Its CIN U68100PN2025PTC237318 and GSTIN 27AANFB7064Q1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in The Eminence II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for The Eminence II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at The Eminence II?
The professionals named in the filing: Architect: VK:A ARCHITECTURE; Engineer: Makarand Mesharam; Engineer: Abhijit Shivaji Gaikwad; Chartered Accountant: CA Jayant Daharwal; Chartered Accountant: FAA & Associates LLP; Chartered Accountant: R. Devendra Kumar & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in The Eminence II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback