Home / Browse projects / Mumbai Suburban, Maharashtra / TEN BKC
TEN BKC
By MIG (Bandra) Realtors & Builders Private Limited
RG-MH-11450 · RERA P51800004889 · Last updated on MahaRERA portal: 20 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- Litigation declared, 30 cases
- 82 complaints at MahaRERA
- Completion date moved by 24 months
- 2 extensions taken
- Rs 2,400.00 crore secured on the land, in favour of HDFC BANK
Clear
- Separate project account declared
- Allotment letter follows the model form
7 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TEN BKC is a Residential / Group Housing project by MIG (Bandra) Realtors & Builders Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004889 on 9 Aug 2017. Possession was promised by 5 Jun 2025 and is now 16 months past that date. The completion date has moved by 24 months from the original filing. 0 of the 1 unit on this registration is recorded sold or booked, and 75 of 165 construction stages are filed complete. 82 complaints are on record with the regulator.
At a glance
Project
- NameTEN BKC
- TypeResidential / Group Housing
- Location
- Madhusudan Kalelkar Marg
- Bandra East
- Andheri
- Mumbai Suburban
- 400051
- Pincode400051
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800004889
- ReraGenie IDRG-MH-11450
Builder
- NameMIG (Bandra) Realtors & Builders Private Limited
- Entity typeCompany
- DirectorsFaizan Raza Khan Pasha, Jessie Kuruvilla
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Aug 2017
- Promised completion5 Jun 2025
- Revised completionRevised to 5 Jun 2025 (originally 6 Jun 2023)
- Buildings15 building records
- Documents filed198 files
Current status
Figures as on 20 Feb 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing 1 | NA | 27 | 22 | 1 | 0 | 1 |
| WING 2 | NA | 27 | 22 | 0 | 0 | 0 |
| WING 3 | NA | 27 | 22 | 0 | 0 | 0 |
| WING 4 | NA | 27 | 22 | 0 | 0 | 0 |
| WING 5 | NA | 34 | 29 | 0 | 0 | 0 |
| WING 6 | NA | 34 | 29 | 0 | 0 | 0 |
| WING 7 | NA | 34 | 29 | 0 | 0 | 0 |
| WING 8 | NA | 34 | 29 | 0 | 0 | 0 |
| WING 9 | NA | 34 | 29 | 0 | 0 | 0 |
| WING 10 | NA | 27 | 22 | 0 | 0 | 0 |
| WING 11 | NA | 27 | 22 | 0 | 0 | 0 |
| WING 12 | NA | 27 | 22 | 0 | 0 | 0 |
| WING 13 | NA | 27 | 22 | 0 | 0 | 0 |
| WING 14 | NA | 27 | 22 | 0 | 0 | 0 |
| WING 15 | NA | 27 | 22 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building15
As on 20 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
75 of 165 construction stages are filed complete across 15 buildings. The stage furthest along is Internal walls, at 99%.
Wing 158%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 65% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 28% |
WING 257%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 58% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 28% |
WING 355%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 43% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 38% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 28% |
WING 457%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 38% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 28% |
WING 575%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 94% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 81% |
WING 673%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 88% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 81% |
WING 772%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 94% |
| Sanitary Fittings within the flats / premises | 27% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 79% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 89% |
WING 871%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 23% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 89% |
WING 960%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 71% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 63% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 28% |
WING 1060%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 76% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 58% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 28% |
WING 1160%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 63% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 28% |
WING 1260%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 72% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 28% |
WING 1372%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 99% |
| Sanitary Fittings within the flats / premises | 29% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 93% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 72% |
WING 1459%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 69% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 28% |
WING 1558%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 59% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 28% |
Progress on shared amenities34
As on 20 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 30% |
| Landscaping & Tree Planting | Yes | 30% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 90% |
| Fire protection and fire safety requirements | Yes | 35% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| Squash Court | Yes | 100% |
| Senior Citizen Area | Yes | 0% |
| Salon and Spa | Yes | 0% |
| Welfare Centre | Yes | 0% |
| Walking Path | Yes | 0% |
| Tiered Landscape Gardens | No | Not applicable |
| Swimming Pool including Kids Pool | Yes | 100% |
| Swimming Pool | No | Not applicable |
| Reflexology Path | Yes | 0% |
| Multipurpose Hall | Yes | 100% |
| Kids Pool | No | Not applicable |
| Clubhouse | Yes | 0% |
| Kids Play Area with play Equipment | Yes | 0% |
| Kids Play Area | No | Not applicable |
| Game Simulator | Yes | 0% |
| Fitness Centre | Yes | 75% |
| Community Building | No | Not applicable |
| Convenience Centre | No | Not applicable |
| Convenience Store | Yes | 0% |
Parking filed915
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing 1 | 55 | 55 |
| WING 2 | 50 | 50 |
| WING 3 | 79 | 79 |
| WING 4 | 55 | 55 |
| WING 5 | 30 | 30 |
| WING 6 | 30 | 30 |
| WING 7 | 76 | 76 |
| WING 8 | 82 | 82 |
| WING 9 | 121 | 121 |
| WING 10 | 37 | 37 |
| WING 11 | 80 | 80 |
| WING 12 | 55 | 55 |
| WING 13 | 55 | 55 |
| WING 14 | 55 | 55 |
| WING 15 | 55 | 55 |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Radius Estates & Developers Private Limited | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Space Age Consultants |
| Architect | Girish Chaudhari |
| Architect | ARCHITECT HAFEEZ CONTRACTOR Design Architect |
| Engineer | Jagdish Kadu |
| Chartered Accountant | B B Jain & Associates |
| Partner | Role in project |
|---|---|
| MIG (Bandra) Realtors & Builders Private Limited | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. We, hereby apply for extension of registration u/s 6 of the Act r/w Rule 7 of the Rules in respect of Project: TEN BKC, No. P51800004889 which expires on 6th June 2023. This is a redevelopment project. The obligation to undertake construction was that of the Co-promoter, Radius Estates & Developers Pvt. Ltd.(Radius). Radius has gone into CIRP under Insolvency Code and a Resolution plan submitted by Adani Goodhomes Pvt. Ltd. has been approved by the Committee of Creditors (83.93% voting in favour). Project Completion Date proposed in the Resolution Plan is 6th June 2024. Adani has also been
Reason as filed by the promoterthe date of 6th June 2024 was proposed in the Resolution Plan which was submitted by Adani Goodhomes Pvt. Ltd. with the Committee of Creditors in December 2021, it was on the basis of a site condition, where work could commence immediately on 1st January 2022. However, after the Resolution Plan was approved by the Committee of Creditors on 21st December 2021 and Adani Goodhomes Pvt. Ltd. was permitted to enter upon the site on 27th December 2021 under the Construction Management Agreement, and after entering the site, Adani Goodhomes Private Limited commenced collating all the drawings of the
Litigation declared30
| Case | Court | Status |
|---|---|---|
| WP No 550 of 2017/2015 | High Court Bombay | challenged the levy of development charges by MCGM |
| Suit No 19 of 2018/2017 | High Court Bombay | interse dispute amongst family members of a member on claim to flat vacated |
| Suit No 2518/2017 | City Civil Court | interse dispute amongst family members of a member on claim to flat vacated |
| Suit No 756/2015 | High Court Bombay | interse dispute amongst family members of three suit flats vacated |
| Suit No 1075/2015 | City Civil Court | interse dispute amongst family members of a member on claim to flat vacated |
| WP No 2521/2018 | High Court Bombay | Matter pending in regards to set off of Stamp Duty on APAA to be executed by the Society Members |
| NA/2020 | Before the Ld Sole Arbitrator | Dispute between Society and Promoter Society has sought to illegally terminate the DA As per the pro |
| WP No 572/2020 | High Court Bombay | challenged the levy of off site infrastructure charge by MHADA |
| WP No 2287/2019 | High Court Bombay | challenged the levy of premium by MHADA |
| Suit No 525/2019 | City Civil Court Dindoshi | interse dispute amongst family members of a member on claim to flat vacated |
| Testamentary Petition No 444/2015 | High Court Bombay | interse dispute amongst family members of a member on claim to flat vacated |
| Suit No 607/2017 | High Court Bombay | interse dispute amongst family members of a member on claim to flat vacated |
| 1390/2020 | NCLT MUMBAI Bench | Disposed Off |
| AT006000000133991/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order for refund |
| AT006000000134129/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000134130/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000134135/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000134000/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000133998/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000134001/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000134002/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000134003/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000134004/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000134005/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000133993/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000133992/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000133994/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000133995/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000133996/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
| AT006000000133997/2022 | Maharashtra Real Estate Appellate Tribunal | Appeal filed against the order |
Complaints filed with MahaRERA82
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000194108 | Ashutosh Tikekar | Radius Estates and Developers Pvt. Ltd. | 21/09/2020 |
| CC006000000057286 | SANJAY KABRA | MIG (Bandra) Realtors and Builders Pvt.Ltd. | 14/12/2018 |
| CC006000000262080 | Sanjay Kabra | MIG(Bandra) Realtors and Builders Pvt.Ltd. | 05/08/2022 |
| CC006000000591225 | Sanjay Kabra | MIG (Bandra) Realtors & Builders Private Limited | 18/07/2024 |
| CC006000000110869 | Amit Saxena | MIG (BANDRA) REALTORS & BUILDERS PRIVATE LIMITED | 11/09/2019 |
| CC006000000110882 | Milee Shetty | MIG (Bandra) Realtors and builders Private limited | 12/09/2019 |
| CC006000000193073 | Samir T. Hosangady | Radius Estates and Developers Pvt Ltd | 19/03/2020 |
| CC006000000193176 | Mohan Vamsi Vinjamur | Radius Estates and Developers Private Ltd | 17/04/2020 |
| CC006000000171654 | AMIT SURENDRA SINGH | SANJAY CHHABRIA | 02/10/2020 |
| CC006000000196347 | Suman Manglunia & Ajay Manglunia | MIG (BANDRA) REALTORS AND BUILDERS PVT LTD | 25/03/2021 |
| CC006000000192739 | MR. SAJID SULAIMAN AND MRS. AYISHA SAJID | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 30/06/2020 |
| CC006000000192741 | MR. SHIVASHISH MISRA | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 07/07/2020 |
| CC006000000192742 | MR. VENKATESHAM NEELA AND MRS. HARIKA NEELA | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 04/07/2020 |
| CC006000000192758 | MR. MADHUSUDHANA REDDY UPPARLAPALLI | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 07/07/2020 |
| CC006000000192759 | MR.GAUTAM BHARGAVA AND MRS.RIDHI BHARGAVA | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 06/07/2020 |
| CC006000000192760 | MR. AKILESH ESWARAN & MRS. PIA MUKHERJEE | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 30/06/2020 |
| CC006000000192762 | MR. SATISH AGRAWAL | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 24/06/2020 |
| CC006000000192926 | MR. VENKATAKRISHNAN NEELAKANTAN | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 24/06/2020 |
| CC006000000192927 | MR. SIDDHARTH ANKATHIL AND MRS. KIVYA GUPTA | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 04/07/2020 |
| CC006000000192928 | MR. VIPUL KANT MISHRA AND MRS. ALKA MISHRA | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 25/06/2020 |
| CC006000000192946 | MR.VAIKUNTAM SRINIVASAN AND MRS. JANAKI SRINIVASAN | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 02/07/2020 |
| CC006000000193009 | MR. ABDUL ABDULLA RAOOF AND MRS. SULEKA ABDUL RAOOF | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 21/07/2020 |
| CC006000000193013 | MR. RAJARAM PRAKASH WAGH AND MRS. VRUNDA PRAKASH WALAWALKAR | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 16/11/2020 |
| CC006000000193014 | MR. YADAGIRI RAO JUPALLY AND MRS. JYOTHSNA KADAPARTHI | RADIUS ESTATES ND DEVELOPERS PRIVATE LIMITED | 30/06/2020 |
| CC006000000193069 | MR. RAMANATHAN ELAYAPERUMAL & MRS. RAJALAKSHMI ALSO KNOWN AS KANNATHAL VAIRAVAN | RADIUS ESTATES AND DEVELOPERS PRIVATE LIMITED | 24/06/2020 |
| CC006000000193754 | Kunal Chaudhary | Radius Estates & Developers Pvt. Ltd. (Formerly known as Vishwaroop Estates & Developers Pvt. Ltd.) | 04/09/2020 |
| CC006000000195529 | MR. AKSHAY SANDEEP PASARKAR AND MRS. ARCHANA PASARKAR | MIG (BANDRA) REALTORS AND BUILDERS PRIVATE LIMITED | 09/01/2021 |
| CC006000000196468 | Nirav Vikram Maniar | MIG (Bandra) Realtors and Builders Pvt. Ltd | 26/04/2021 |
| CC006000000196434 | Chirag Oza | Radius Ten BKC | 22/03/2021 |
| CC006000000196993 | RAMJEET SINGH ARORA | RADIUS ESTATE & DEVELOPERS PVT. LTD. | 13/05/2021 |
| CC006000000196997 | MURKALA KRISHNARAO | RADIUS ESTATE & DEVELOPERS PVT. LTD. | 13/05/2021 |
| CC006000000197083 | MRS. BINA KHAYALIRAM JOSHI | RADIUS ESTATES & DEVELOPERS PVT LTD | 26/05/2021 |
| CC006000000396398 | Radius Estates & Developers Private Limited | Kunal Chaudhary | 24/06/2023 |
| CC006000000398066 | Radius Estates & Developers Private Limited | Sajid Sulaiman | 04/11/2023 |
| CC006000000398067 | Radius Estates & Developers Private Limited | Shivashish Mishra | 04/11/2023 |
| CC006000000398068 | Radius Estates & Developers Private Limited | Venkatesham Neela | 05/11/2023 |
| CC006000000398069 | Radius Estates & Developers Private Limited | Madhusudhana Reddy Upparlapalli | 05/11/2023 |
| CC006000000398070 | Radius Estates & Developers Private Limited | Gautam Bhargava | 05/11/2023 |
| CC006000000398071 | Radius Estates & Developers Private Limited | Akilesh Eswaran | 05/11/2023 |
| CC006000000398072 | Radius Estates & Developers Private Limited | Satish Agrawal | 05/11/2023 |
| CC006000000398073 | Radius Estates & Developers Private Limited | Venkatkrishnan Neelkantan | 05/11/2023 |
| CC006000000398074 | Radius Estates & Developers Private Limited | Siddharth Anathil | 05/11/2023 |
| CC006000000398075 | Radius Estates & Developers Private Limited | Vipulkant Mishra | 05/11/2023 |
| CC006000000398076 | Radius Estates & Developers Private Limited | Vaikuntan Srinivasan | 05/11/2023 |
| CC006000000398077 | Radius Estates & Developers Private Limited | Abdul Abdulla Raoof | 05/11/2023 |
| CC006000000398078 | Radius Estates & Developers Private Limited | Yadagiri Rao Jupally | 05/11/2023 |
| CC006000000398079 | Radius Estates & Developers Private Limited | Ramanathan Elayaperumal | 05/11/2023 |
| CC006000000398084 | Radius Estates & Developers Private Limited | Samir Shah | 06/11/2023 |
| CC006000000398085 | Radius Estates & Developers Private Limited | Ramanjeet Singh Arora | 06/11/2023 |
| CC006000000398086 | Radius Estates & Developers Private Limited | Murkala Krishnarao | 06/11/2023 |
| CC006000000398087 | Radius Estates & Developers Private Limited | Manish Ratilal Patel | 06/11/2023 |
| CC006000000398088 | Radius Estates & Developers Private Limited | Lilian Prem | 06/11/2023 |
| CC006000000398089 | Radius Estates & Developers Private Limited | Chetan Kamat | 06/11/2023 |
| CC006000000398090 | Radius Estates & Developers Private Limited | Bhaskar Neela | 06/11/2023 |
| CC006000000398091 | Radius Estates & Developers Private Limited | Bala Raman Nayar | 06/11/2023 |
| CC006000000398092 | Radius Estates & Developers Private Limited | Samir Taranath Hosangady | 06/11/2023 |
| CC006000000398093 | Radius Estates & Developers Private Limited | Rajaram Wagh | 06/11/2023 |
| CC006000000429578 | Radius Estates & Developers Private Limited | Ajay Luthra | 09/03/2024 |
| CC006000000591139 | MIG (Bandra) Realtors & Builders Private Limited | Sanjay Kabra | 12/07/2024 |
| CC12401233 | Amin Abdul Rasool Virji | MIG (Bandra) Realtors & Builders Private Limited | 25/12/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Nov 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed198
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 198 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240630 FORM 1.pdf | 20 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240930 FORM 1.pdf | 20 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20241231 FORM 1.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: 20240630 FORM 3.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: 20240930 FORM 3.pdf | 20 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240630 FORM 2.pdf | 20 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240930 FORM 2.pdf | 20 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240930 FORM 2.pdf | 20 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: March 2024.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold InventoryList for March 2023.pdf | 5 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold InventoryList for March 2024.pdf | 5 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: MIG Form 5 March 2023.pdf | 5 Jun 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Annexure F.pdf | 3 Jun 2024 |
| Declaration in FORM BFile: 2024 Form B Ten BKC.pdf | 3 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20230930 FORM 1.pdf | 3 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20231231 FORM 1.pdf | 3 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240331 FORM 1.pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20220630 FORM 2.pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20220930 FORM 2.pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20221231 FORM 2.pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20230331 FORM 2.pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20230630 FORM 2.pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20230930 FORM 2.pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20231231 FORM 2.pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240331 FORM 2.pdf | 3 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 20220331 FORM 2A.pdf | 3 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Ten BKC 2022 2023.pdf | 3 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Ten BKC 2023 2024.pdf | 3 Jun 2024 |
| Certificates of CA (Form 3)File: 20221231 FORM 3.pdf | 3 Jun 2024 |
| Certificates of CA (Form 3)File: 20230331 FORM 3.pdf | 3 Jun 2024 |
| Certificates of CA (Form 3)File: 20230630 FORM 3.pdf | 3 Jun 2024 |
| Certificates of CA (Form 3)File: 20230930 FORM 3.pdf | 3 Jun 2024 |
| Certificates of CA (Form 3)File: 20231231 FORM 3.pdf | 3 Jun 2024 |
| Certificates of CA (Form 3)File: 20240331 FORM 3.pdf | 3 Jun 2024 |
| Certificates of CA (Form 3)File: 20220930 FORM 3 A.pdf | 3 Aug 2023 |
| Certificates of CA (Form 3)File: 20220930 FORM 3 B.pdf | 3 Aug 2023 |
| Certificates of CA (Form 3)File: 20220930 FORM 3 C.pdf | 3 Aug 2023 |
| Declaration in FORM BFile: 2023 FORM B.pdf | 24 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220630 FORM 1.pdf | 22 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220930 FORM 1.pdf | 22 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20221231 FORM 1.pdf | 22 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20230331 FORM 1.pdf | 22 May 2023 |
| Form 2AFile: 20220331 FORM 2A.pdf | 22 May 2023 |
| Certificates of CA (Form 3)File: 20220630 FORM 3 A.pdf | 22 May 2023 |
| Certificates of CA (Form 3)File: 20220630 FORM 3 B.pdf | 22 May 2023 |
| Certificates of CA (Form 3)File: 20220630 FORM 3 C.pdf | 22 May 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 20230327 Circular No 43 Self Declaration.pdf | 29 Mar 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 20230327 Order No 34 Declaration compressed.pdf | 29 Mar 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 20230328 Circular No 43 Declaration cum undertaking.pdf | 29 Mar 2023 |
| Proforma of Agreement for saleFile: TEN BKC AFS DB VR 2023.pdf | 25 Feb 2023 |
| Proforma of Agreement for saleFile: TEN BKC AFS RD VR 2023.pdf | 25 Feb 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: September 2023.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 20190930 FORM 5.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 20200929 FORM 5.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 20201027 FORM 5 R.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 20220915 FORM MIG.pdf | 2 Feb 2023 |
| Proforma of Agreement for saleFile: DB RERA Agreement for Sale Part I.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: DB RERA Agreement for Sale Part II.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: DB RERA Agreement for Sale Part III.pdf | 4 Jan 2023 |
| Proforma of Allotment letterFile: DB RERA Agreement for Sale Part IV.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: DB RERA Agreement for Sale Part IV.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: DB RERA Agreement for Sale Part V.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: DB RERA Agreement for Sale Part VI.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: DB RERA Agreement for Sale Part VII.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: DB RERA Agreement for Sale Part VIII.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: DB RERA Agreement for Sale Part I X.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: RD RERA Agreement for Sale Part I.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: RD RERA Agreement for Sale Part II.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: RD RERA Agreement for Sale Part III.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: RD RERA Agreement for Sale Part IV.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: RD RERA Agreement for Sale Part V.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: RD RERA Agreement for Sale Part VI.pdf | 4 Jan 2023 |
| Proforma of Agreement for saleFile: RD RERA Agreement for Sale Part VII.pdf | 4 Jan 2023 |
| Building plan approvalFile: 20220509 Amended IOD MIG Group I Ten BKC Letter.pdf | 9 Nov 2022 |
| Building Plan Approval (IOD)File: 20220509 Amended IOD MIG Group I Ten BKC Letter.pdf | 9 Nov 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220616 Ten BKC Further CC.pdf | 9 Nov 2022 |
| Declaration about Commencement CertificateFile: 20221102 Declaration of CC.pdf | 9 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220331 FORM 1.pdf | 7 Nov 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20221107 FORM 2.pdf | 7 Nov 2022 |
| Certificates of CA (Form 3)File: 20220331 FORM 3 page 1-4.pdf | 7 Nov 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 7 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 198 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep TEN BKC on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bandra East6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 159 registered projects within 2 km.
12 PEGASUS
Jayant Enterprises S N Project
Kalpataru Magnus
Kalpataru Properties Pvt. Ltd.
Plotted Development Scheme at Sindhudurhnagari
MAHARASHTRA HOUSING AND AREA DEVELOPMENT A
SAJAY AVENUE 18
Vinca Realtors Private Limited
Sahakar excel Acropolis - I
EXCEL ENTERPRISES REALTY LLP
ADDRESS 51
V LAXMI EKTA DEVELOPERS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: MIG (Bandra) Realtors & Builders Private Limited
MIG (Bandra) Realtors & Builders Private Limited has 1 registration on MahaRERA, including TEN BKC. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that TEN BKC shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if TEN BKC is delayed beyond 5 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TEN BKC?
The registered promoter entity is MIG (Bandra) Realtors & Builders Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TEN BKC?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against TEN BKC?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for TEN BKC?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TEN BKC?
The professionals named in the filing: Architect: Space Age Consultants; Architect: Girish Chaudhari; Architect: ARCHITECT HAFEEZ CONTRACTOR Design Architect; Engineer: Jagdish Kadu; Chartered Accountant: B B Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TEN BKC?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback