SWIZ HEIGHTS
RG-MH-59010 · RERA P51800005779 · Last updated on MahaRERA portal: 17 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 11 complaints at MahaRERA
- Completion date moved by 72 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SWIZ HEIGHTS is a Residential / Group Housing project by Mohid Construction Co in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005779 on 14 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 72 months from the original filing. 11 complaints are on record with the regulator.
At a glance
Project
- NameSWIZ HEIGHTS
- TypeResidential / Group Housing
- Location
- R T O Lane
- Andheri (W)
- Andheri
- Mumbai Suburban
- 400053
- Pincode400053
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800005779
- ReraGenie IDRG-MH-59010
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed92 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SWIZ HEIGHTS | NA | 20 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
SWIZ HEIGHTS: 81% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities16
As on 17 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 40% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| FITNESS CENTRE | Yes | 0% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | IBADUT REHMAN MOMIN |
| Engineer | Ziaur Rehman Khan |
| Chartered Accountant | Mahesh Shrikant Bajaj |
| Chartered Accountant | ADP & Associates |
| Partner | Role in project |
|---|---|
| Mohid Construction Co | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to scarcity of river sand and non availability of labours due to prolonged monsoon.
Reason as filed by the promoterThat our above project is a SRA project with two phases therein for sale component and SWIZ HEIGHTS phase 1 had expired on 30.12.2021 . That in the month of April 2024, we have received notice from RERA to have separate bank accounts for both the phases of the project. When intimated to RERA with respect to the status of completion of the project and the above fact, we have been advised by the RERA to upload the OC along with Form 4 or open the new bank accounts for both the phases of the project. That we are yet to receive the occupancy certificate for both the phases of the project, hence we
Complaints filed with MahaRERA11
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000089543 | Bipinkumar Gorakhnath Singh | Mohid Construction Co (Swiz Heights) | 31/05/2019 |
| CC006000000221077 | sandeep kumar | Mohid Construction Co | 09/05/2022 |
| CC006000000195852 | ASHOK RAMANLAL GANDHI | MOHID CONSTRUCTION CO. | 03/02/2021 |
| CC006000000197292 | CHINTAN ASHOKKUMAR GANDHI | MOHID CONSTRUCTION CO | 17/06/2021 |
| CC006000000197293 | GAURAV ASHOKKUMAR GANDHI | MOHID CONSTRUCTION CO | 17/06/2021 |
| CC006000000197985 | Mamta Rochlani | Mohid Construction Company | 03/09/2021 |
| CC006000000199290 | Mr. Vishal Khanna and Mrs. Karishma Khanna | Mohid Construction Company | 05/12/2021 |
| CC006000000220995 | Aatish Anaji More | M/s. Mohid Constructions Company | 29/04/2022 |
| CC006000000251849 | Atulkumar Jagdish Singh | M/s. Mohid Constructions | 11/07/2022 |
| CC006000000292863 | Pradnya Krishnakant Rane | M/s. Mohid Constructions Company | 03/10/2022 |
| CC006000000408356 | Kavita Ajay Patole | M/s. Mohid Constructions Company | 20/12/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Jul 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed92
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: 1 FORM 1 SWIZ HEIGHTS 310325.pdf | 17 Jan 2026 |
| Form 2File: FORM 2 SWIZ HEIGHTS-31-03-2025.pdf | 17 Jan 2026 |
| Form 3File: 1 FORM 3 SWIZ HEIGHTS-310325.pdf | 17 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: INVENTORY SWIZ HEIGHTS-31-03-2025.pdf | 17 Jan 2026 |
| Form 1File: 2 FORM 1 SWIZ HEIGHTS -30-06-2025.pdf | 17 Jan 2026 |
| Form 2File: FORM 2 SWIZ HEIGHTS-30-06-2025.pdf | 17 Jan 2026 |
| Form 3File: 2 FORM 3 SWIZ HEIGHTS -30-06-25.pdf | 17 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: INVENTORY SWIZ HEIGHTS-30-06-2025.pdf | 17 Jan 2026 |
| Form 1File: 3 FORM 1 SWIZ HEIGHTS -30-09-25.pdf | 17 Jan 2026 |
| Form 2File: FORM 2 SWIZ HEIGHTS-30-09-2025.pdf | 17 Jan 2026 |
| Form 3File: 3 FORM 3 SWIZ HEIGHTS -30-09-25.pdf | 17 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: INVENTORY SWIZ HEIGHTS-30-09-2025.pdf | 17 Jan 2026 |
| Form 1File: 4 FORM 1 SWIZ HEIGHTS -31-12-2025.pdf | 17 Jan 2026 |
| Form 2File: FORM 2 SWIZ HEIGHTS-31-12-2025.pdf | 17 Jan 2026 |
| Form 3File: 4 FORM 3 SWIZ HEIGHTS -31-12-2025.pdf | 17 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: INVENTORY SWIZ HEIGHTS-31-12-2025.pdf | 17 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 Swizz Heights.pdf | 17 Jan 2026 |
| Certificates of CA (Form 3)File: Revised_Form 3 Swiz Heights 31_12_2024.pdf | 22 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Swiz Heights 30_09_2022.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Swiz Heights 31_12_24.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Swiz Height 300924.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Swiz Height 300624.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 as on 31032024.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Swiz Heights 31_12_23.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Swiz Heights 30-06-2023.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Swiz Heights 31_03_2023.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Swiz Heights 31_3_2022.pdf | 17 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 31_03_2022.pdf | 17 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 30_09_2022.pdf | 17 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 31_03_2023.pdf | 17 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights_30_6_23.pdf | 17 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 31_12_23.pdf | 17 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 Swiz Heights 31_03_24.pdf | 17 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz height 300624.pdf | 17 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz height 300924.pdf | 17 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 31_12_24.pdf | 17 Mar 2025 |
| Declaration in FORM BFile: RS 500 STAMP PAPER_Form B Swiz Heights.pdf | 18 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 Swiz Heights 31_12_24.pdf | 22 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 31_12_24.pdf | 22 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Swiz Heights 31_03_24.pdf | 21 Jan 2025 |
| Declaration in FORM BFile: Form B Swiz Heights.pdf | 18 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31_12_24.pdf | 17 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure inventory Swiz Height.pdf | 9 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Swiz Height 31_3_2023.pdf | 9 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Swiz Heights 31_3_24.pdf | 9 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Swiz Height 300624.pdf | 30 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Swiz Heights 310324.pdf | 30 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Swiz Height 300624.pdf | 30 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Swiz Height 300924.pdf | 30 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Swiz Height 300624.pdf | 30 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Swiz Height 300924.pdf | 30 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 as on 31032024.pdf | 30 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 Swiz Heights 310324.pdf | 30 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz height 300624.pdf | 30 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz height 300924.pdf | 30 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Mohid Form 5 FY 22-23.pdf | 28 Dec 2023 |
| Certificates of CA (Form 3)File: Swiz Heights Form 3.pdf | 2 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf | 15 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf | 15 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf | 15 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf | 15 Apr 2023 |
| Certificates of CA (Form 3)File: Swiz heights CA certificate 31-03-2018.pdf | 13 Mar 2023 |
| Certificates of CA (Form 3)File: Swiz heights CA certificate 31-03-2019.pdf | 13 Mar 2023 |
| Certificates of CA (Form 3)File: Swiz heights CA certificate 31-03-2020.pdf | 13 Mar 2023 |
| Certificates of CA (Form 3)File: Swiz heights CA certificate 31-03-2021.pdf | 13 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUNE.pdf | 14 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 DEC.pdf | 14 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUNE.pdf | 14 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 DEC.pdf | 14 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mohid Architect cert_compressed.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Mohid Engineers FORM 2A.pdf | 7 Oct 2021 |
| Certificates of CA (Form 5)File: Mohid Construction RERA Audit Report.pdf | 21 Jun 2019 |
| Proforma of Allotment letterFile: Agreement for sale-Compressed.pdf | 14 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: SWIZ CC.pdf | 13 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: SWIZ CC.pdf | 13 Jul 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer cert.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Building plan approvalFile: Intimation of Approval.pdf | 30 Jul 2017 |
| Layout approvalFile: plan layout compressed.pdf | 30 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| MOHID HEIGHTS | 825 PART OF VILLAGE AMBIVALI SR NO 111D ANDHERI MUMBAI | 193 | Completed | Jan 2007 | Late, Oct 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 92 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SWIZ HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri (W)6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 285 registered projects within 2 km.
LIVSMART KURLA
D. K. REALTY (INDIA) PVT. LTD.
MOONGIPA ARCADE
MOONGIPA REALTY PRIVATE LIMITED
LINKBAY RESIDENCES PHASE I
PORTSMOUTH BUILDCON PRIVATE LIMITED
Purva Estrella
Puravankara Ltd
78 LAKE TOWN
ANIRDESH DEVELOPERS PRIVATE LIMITED
Transcon Triumph Tower 2
Transcon Triumph Phase 2 Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: Mohid Construction Co
Mohid Construction Co has 3 registrations on MahaRERA, including SWIZ HEIGHTS and MAHAKALI HILLS. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that SWIZ HEIGHTS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SWIZ HEIGHTS is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SWIZ HEIGHTS?
The registered promoter entity is Mohid Construction Co, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SWIZ HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SWIZ HEIGHTS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SWIZ HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SWIZ HEIGHTS?
The professionals named in the filing: Architect: IBADUT REHMAN MOMIN; Engineer: Ziaur Rehman Khan; Chartered Accountant: Mahesh Shrikant Bajaj; Chartered Accountant: ADP & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SWIZ HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback