Home / Browse projects / Mumbai Suburban, Maharashtra / SWIZ HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

SWIZ HEIGHTS

By Mohid Construction Co

RG-MH-59010 · RERA P51800005779 · Last updated on MahaRERA portal: 17 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 11 complaints at MahaRERA
  • Completion date moved by 72 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
8 of 11Construction stages donefurthest along: Installation of Lifts, 95%
11Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

SWIZ HEIGHTS is a Residential / Group Housing project by Mohid Construction Co in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005779 on 14 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 72 months from the original filing. 11 complaints are on record with the regulator.

At a glance

Project

  • NameSWIZ HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • R T O Lane
    • Andheri (W)
    • Andheri
    • Mumbai Suburban
    • 400053
  • Pincode400053
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800005779
  • ReraGenie IDRG-MH-59010

Builder

  • NameMohid Construction Co
  • Entity typeOthers
  • ProprietorZAHUR MOHID Abdulaziz Mohid
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed92 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SWIZ HEIGHTSNA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

SWIZ HEIGHTS: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities16

As on 17 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
FITNESS CENTREYes0%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area646 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI4858.03
Proposed, not sanctioned2,795 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKandivali East Thakur Village Branch

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectIBADUT REHMAN MOMIN
EngineerZiaur Rehman Khan
Chartered AccountantMahesh Shrikant Bajaj
Chartered AccountantADP & Associates
PartnerRole in project
Mohid Construction Co-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005206Dec 2019 → Dec 2020

Reason as filed by the promoterDue to scarcity of river sand and non availability of labours due to prolonged monsoon.

EXT51800027219Dec 2019 → Dec 2025

Reason as filed by the promoterThat our above project is a SRA project with two phases therein for sale component and SWIZ HEIGHTS phase 1 had expired on 30.12.2021 . That in the month of April 2024, we have received notice from RERA to have separate bank accounts for both the phases of the project. When intimated to RERA with respect to the status of completion of the project and the above fact, we have been advised by the RERA to upload the OC along with Form 4 or open the new bank accounts for both the phases of the project. That we are yet to receive the occupancy certificate for both the phases of the project, hence we

Complaints filed with MahaRERA11

Case no.ComplainantRespondentFiled
CC006000000089543Bipinkumar Gorakhnath SinghMohid Construction Co (Swiz Heights)31/05/2019
CC006000000221077sandeep kumarMohid Construction Co09/05/2022
CC006000000195852ASHOK RAMANLAL GANDHIMOHID CONSTRUCTION CO.03/02/2021
CC006000000197292CHINTAN ASHOKKUMAR GANDHIMOHID CONSTRUCTION CO17/06/2021
CC006000000197293GAURAV ASHOKKUMAR GANDHIMOHID CONSTRUCTION CO17/06/2021
CC006000000197985Mamta RochlaniMohid Construction Company03/09/2021
CC006000000199290Mr. Vishal Khanna and Mrs. Karishma KhannaMohid Construction Company05/12/2021
CC006000000220995Aatish Anaji MoreM/s. Mohid Constructions Company29/04/2022
CC006000000251849Atulkumar Jagdish SinghM/s. Mohid Constructions11/07/2022
CC006000000292863Pradnya Krishnakant RaneM/s. Mohid Constructions Company03/10/2022
CC006000000408356Kavita Ajay PatoleM/s. Mohid Constructions Company20/12/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jul 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 1 FORM 1 SWIZ HEIGHTS 310325.pdf17 Jan 2026
Form 2File: FORM 2 SWIZ HEIGHTS-31-03-2025.pdf17 Jan 2026
Form 3File: 1 FORM 3 SWIZ HEIGHTS-310325.pdf17 Jan 2026
Disclosure of Sold and Booked InventoryFile: INVENTORY SWIZ HEIGHTS-31-03-2025.pdf17 Jan 2026
Form 1File: 2 FORM 1 SWIZ HEIGHTS -30-06-2025.pdf17 Jan 2026
Form 2File: FORM 2 SWIZ HEIGHTS-30-06-2025.pdf17 Jan 2026
Form 3File: 2 FORM 3 SWIZ HEIGHTS -30-06-25.pdf17 Jan 2026
Disclosure of Sold and Booked InventoryFile: INVENTORY SWIZ HEIGHTS-30-06-2025.pdf17 Jan 2026
Form 1File: 3 FORM 1 SWIZ HEIGHTS -30-09-25.pdf17 Jan 2026
Form 2File: FORM 2 SWIZ HEIGHTS-30-09-2025.pdf17 Jan 2026
Form 3File: 3 FORM 3 SWIZ HEIGHTS -30-09-25.pdf17 Jan 2026
Disclosure of Sold and Booked InventoryFile: INVENTORY SWIZ HEIGHTS-30-09-2025.pdf17 Jan 2026
Form 1File: 4 FORM 1 SWIZ HEIGHTS -31-12-2025.pdf17 Jan 2026
Form 2File: FORM 2 SWIZ HEIGHTS-31-12-2025.pdf17 Jan 2026
Form 3File: 4 FORM 3 SWIZ HEIGHTS -31-12-2025.pdf17 Jan 2026
Disclosure of Sold and Booked InventoryFile: INVENTORY SWIZ HEIGHTS-31-12-2025.pdf17 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 Swizz Heights.pdf17 Jan 2026
Certificates of CA (Form 3)File: Revised_Form 3 Swiz Heights 31_12_2024.pdf22 Mar 2025
Certificates of CA (Form 3)File: Form 3 Swiz Heights 30_09_2022.pdf17 Mar 2025
Certificates of CA (Form 3)File: Form 3 Swiz Heights 31_12_24.pdf17 Mar 2025
Certificates of CA (Form 3)File: Form 3 Swiz Height 300924.pdf17 Mar 2025
Certificates of CA (Form 3)File: Form 3 Swiz Height 300624.pdf17 Mar 2025
Certificates of CA (Form 3)File: Form 3 as on 31032024.pdf17 Mar 2025
Certificates of CA (Form 3)File: Form 3 Swiz Heights 31_12_23.pdf17 Mar 2025
Certificates of CA (Form 3)File: Form 3 Swiz Heights 30-06-2023.pdf17 Mar 2025
Certificates of CA (Form 3)File: Form 3 Swiz Heights 31_03_2023.pdf17 Mar 2025
Certificates of CA (Form 3)File: Form 3 Swiz Heights 31_3_2022.pdf17 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 31_03_2022.pdf17 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 30_09_2022.pdf17 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 31_03_2023.pdf17 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights_30_6_23.pdf17 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 31_12_23.pdf17 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 Swiz Heights 31_03_24.pdf17 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz height 300624.pdf17 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz height 300924.pdf17 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 31_12_24.pdf17 Mar 2025
Declaration in FORM BFile: RS 500 STAMP PAPER_Form B Swiz Heights.pdf18 Feb 2025
Certificates of CA (Form 3)File: Form 3 Swiz Heights 31_12_24.pdf22 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz Heights 31_12_24.pdf22 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Swiz Heights 31_03_24.pdf21 Jan 2025
Declaration in FORM BFile: Form B Swiz Heights.pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31_12_24.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure inventory Swiz Height.pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Swiz Height 31_3_2023.pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Swiz Heights 31_3_24.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Swiz Height 300624.pdf30 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Swiz Heights 310324.pdf30 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Swiz Height 300624.pdf30 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Swiz Height 300924.pdf30 Dec 2024
Certificates of CA (Form 3)File: Form 3 Swiz Height 300624.pdf30 Dec 2024
Certificates of CA (Form 3)File: Form 3 Swiz Height 300924.pdf30 Dec 2024
Certificates of CA (Form 3)File: Form 3 as on 31032024.pdf30 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 Swiz Heights 310324.pdf30 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz height 300624.pdf30 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Swiz height 300924.pdf30 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Mohid Form 5 FY 22-23.pdf28 Dec 2023
Certificates of CA (Form 3)File: Swiz Heights Form 3.pdf2 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf15 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf15 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf15 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf15 Apr 2023
Certificates of CA (Form 3)File: Swiz heights CA certificate 31-03-2018.pdf13 Mar 2023
Certificates of CA (Form 3)File: Swiz heights CA certificate 31-03-2019.pdf13 Mar 2023
Certificates of CA (Form 3)File: Swiz heights CA certificate 31-03-2020.pdf13 Mar 2023
Certificates of CA (Form 3)File: Swiz heights CA certificate 31-03-2021.pdf13 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUNE.pdf14 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 DEC.pdf14 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUNE.pdf14 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 DEC.pdf14 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mohid Architect cert_compressed.pdf7 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Mohid Engineers FORM 2A.pdf7 Oct 2021
Certificates of CA (Form 5)File: Mohid Construction RERA Audit Report.pdf21 Jun 2019
Proforma of Allotment letterFile: Agreement for sale-Compressed.pdf14 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: SWIZ CC.pdf13 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: SWIZ CC.pdf13 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-ilovepdf-compressed.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer cert.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Certificate-ilovepdf-compressed.pdf31 Jul 2017
Building plan approvalFile: Intimation of Approval.pdf30 Jul 2017
Layout approvalFile: plan layout compressed.pdf30 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MOHID HEIGHTS825 PART OF VILLAGE AMBIVALI SR NO 111D ANDHERI MUMBAI193CompletedJan 2007Late, Oct 2011

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 72 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SWIZ HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri (W)6,700+ in Mumbai Suburban

2 kmSWIZ HEIGHTSCompleted 90Lapsed / revoked 69Abeyance 1Other 125Dot size: filed unitsN

Filed coordinates, straight-line distance. 285 registered projects within 2 km.

Builder: Mohid Construction Co

Mohid Construction Co has 3 registrations on MahaRERA, including SWIZ HEIGHTS and MAHAKALI HILLS. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that SWIZ HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SWIZ HEIGHTS is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SWIZ HEIGHTS?

The registered promoter entity is Mohid Construction Co, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SWIZ HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SWIZ HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SWIZ HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SWIZ HEIGHTS?

The professionals named in the filing: Architect: IBADUT REHMAN MOMIN; Engineer: Ziaur Rehman Khan; Chartered Accountant: Mahesh Shrikant Bajaj; Chartered Accountant: ADP & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWIZ HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWIZ HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWIZ HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.