ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / SWED GANGA

Registered No litigation declared Others project

SWED GANGA

By SHREE SAI REALTORS

RG-MH-17848 · RERA P99000055974 · Last updated on MahaRERA portal: 6 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Rs 12.00 crore secured on the land, in favour of SMFG INDIA HOME FINANCE COMPANY LIMITED

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 80%
124 of 152Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

SWED GANGA is a Others project by SHREE SAI REALTORS in Palghar, Maharashtra, registered with MahaRERA as P99000055974 on 2 May 2024. Possession is promised by 31 Dec 2027. 28 of the 152 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSWED GANGA
  • TypeOthers
  • Location
    • ACHOLE
    • vasai
    • Vasai-Virar City (M Corp)
    • Palghar
    • 401209
  • Pincode401209
  • RERA no.P99000055974
  • ReraGenie IDRG-MH-17848

Builder

  • NameSHREE SAI REALTORS
  • Entity typePartnership
  • PartnersBHAVANA SANDEEP MEHTA, SANDEEP KANAIYALAL MEHTA, CHIRAG JAYANTILAL GOHIL, BHUPESH CHINTAMAN PATIL, MEETA BHAVESH MEHTA
  • Other registrations3 more →
  • Completed1 of 4
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 May 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed58 files

Current status

18%28 of 152 units booked
46.6%Work done, per cost certificate

Figures as on 6 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GARDEN CHSLNA161512032152

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.

GARDEN CHSL: 45% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed214

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots214
Closed/Covered143
Open Space71

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,048 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofSMFG INDIA HOME FINANCE COMPANY LIMITED
Secured amountRs 12.00 crore
CERSAI search filedYes
Declared on21 Aug 2025
LandownerVillageDistrict
GARDEN CHSLVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityVASAI VIRAL CITY MUNCIPAL CORARATION
Permissible FSI9654.85
Proposed, not sanctioned8,755 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK LTD11 ANAJANA APARTMENT S V ROAD SHIMPOLI JUNCTION BORIVALI WEST
Estimated costRs 43.49 cr
Cost incurredRs 20.26 cr
Work done46.59%
BuildingWingEstimatedIncurred
GARDEN CHSLNARs 41.74 crRs 20.26 cr
-NARs 1.75 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANISH SHAH
ArchitectMEGHA FERNANDES
EngineerHARESH PATEL
EngineerPRAGNESH OZA
Chartered AccountantNEHALI & CO
Chartered AccountantKOTHARI JAIN & ASSOCIATES
PartnerRole in project
SHREE SAI REALTORS-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12602137Neelam Ashok DubeySHREE SAI REALTORS11/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Mar 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: SSR RERA Form 1 March 2026.pdf6 Jun 2026
Withdrawal Update Form 2File: Pragnesh Oza.pdf6 Jun 2026
Withdrawal Update Form 3File: SSR Form 3 March 2026.pdf6 Jun 2026
Withdrawal Update Form 1File: Form 1 Dec 2025 -SSR.pdf3 Jun 2026
Withdrawal Update Form 2File: Form 2 Dec 2025 Revised - SSR.pdf3 Jun 2026
Withdrawal Update Form 3File: Form 3 Dec 2025 - SSR.pdf3 Jun 2026
Withdrawal Update Form 1File: form1 swed ganga.pdf7 Nov 2025
Withdrawal Update Form 2File: SWED GANGA FORM2.pdf7 Nov 2025
Withdrawal Update Form 3File: form 3 swed ganga sept 25 NEW.pdf7 Nov 2025
Form 2A (FY 2024-2025)File: form 2A - Swed Ganag for March 2025.pdf11 Sep 2025
Withdrawal Update Form 1File: Form 1 SSR June 2025.pdf8 Sep 2025
Withdrawal Update Form 2File: Shree Sai Realtors Form 2 June 2025.pdf8 Sep 2025
Withdrawal Update Form 3File: Shree Sai Realtors Form 3 June 2025.pdf8 Sep 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 (1).pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate feb 2025 - SSR (1).pdf17 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclouser of inventory for bank change (1).pdf17 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 dec 24 final.pdf10 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 oct to dec 24.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 (1).pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 April to June 2024.pdf30 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2024.pdf30 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2 April to June 2024.pdf30 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: shree sai realtor form 3 oct (1).pdf16 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf10 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf10 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 july to sep 24.pdf10 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Garden CHSL.pdf9 Dec 2024
Details of encumbrances concerned to FinanceFile: SMFG Encumbrance Certificate.pdf6 Nov 2024
Details of encumbrances concerned to LegalFile: SMFG Encumbrance Certificate.pdf6 Nov 2024
Other - TechnicalFile: Declaration cum Undertaking- SSR (1).pdf26 Mar 2024
Proforma of Allotment letterFile: Allotment Letter Garden CHSL 1-3 (1) (1).pdf15 Mar 2024
Deviation Report with respect to Allotment letterFile: No deviation Allotment - Garden CHSL (1).pdf15 Mar 2024
Deviation Report with respect to model copy of AgreementFile: Deviation agreement Garden chsl.pdf15 Mar 2024
Copy of the legal title reportFile: title.pdf14 Mar 2024
Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale FINAL (1).pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate garden chsl new.pdf11 Mar 2024
Building plan approvalFile: Shree Sai realtors- CC 23-1-24.pdf1 Mar 2024
Layout approvalFile: Shree Sai Realtors Layout Plan with CC Dated 23-1-24 (1).pdf1 Mar 2024
Layout approvalFile: Shree Sai realtors Ground 1st and 2nd podium floor plan 23-2-24 (1).pdf1 Mar 2024
Layout approvalFile: Shree Sai Realtors 3rd 4 th 5th 6th and 7th floorPlan 23-1-24.pdf1 Mar 2024
Layout approvalFile: Shree Sai realtors -8th 9th and 12th floor plan 23-1-24 (1).pdf1 Mar 2024
Layout approvalFile: Shree Sai Realtors - 10th 11th 13th 14th floor Plan 23-1-24 (2).pdf1 Mar 2024
PAN CardFile: shreesai realtors Pan.pdf1 Mar 2024
Details of encumbrances concerned to FinanceFile: No encumbrances Self Declaration - SSR.pdf1 Mar 2024
Details of encumbrances concerned to LegalFile: No encumbrances Self Declaration - SSR.pdf1 Mar 2024
Copy of Layout Approval (in case of layout)File: Shree Sai Realtors Layout Plan with CC Dated 23-1-24 (1).pdf1 Mar 2024
Copy of Layout Approval (in case of layout)File: Shree Sai realtors Ground 1st and 2nd podium floor plan 23-2-24 (1).pdf1 Mar 2024
Copy of Layout Approval (in case of layout)File: Shree Sai Realtors 3rd 4 th 5th 6th and 7th floorPlan 23-1-24.pdf1 Mar 2024
Copy of Layout Approval (in case of layout)File: Shree Sai realtors -8th 9th and 12th floor plan 23-1-24 (1).pdf1 Mar 2024
Copy of Layout Approval (in case of layout)File: Shree Sai Realtors - 10th 11th 13th 14th floor Plan 23-1-24 (2).pdf1 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Shree Sai realtors- CC 23-1-24.pdf1 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Shree Sai realtors- CC 23-1-24.pdf1 Mar 2024
Declaration about Commencement CertificateFile: CC Declaration - Garden CHSL.pdf1 Mar 2024
Declaration in FORM BFile: Form B- GARDEN CHSL (1).pdf1 Mar 2024
CERSAI detailsFile: Cersai Declaration - GARDEN CHSL.pdf1 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DOI - GARDEN CHSL (1) (1) (1) (2).pdf1 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Details Letter - GARDEN CHSL.pdf1 Mar 2024

How this compares with Palghar

18%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SWED GANGA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near vasai3,200+ in Palghar

Builder: SHREE SAI REALTORS

SHREE SAI REALTORS has 4 registrations on MahaRERA, including SAI GRANDEUR and Sai Shrushti. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if SWED GANGA is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SWED GANGA?

The registered promoter entity is SHREE SAI REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SWED GANGA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SWED GANGA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SWED GANGA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SWED GANGA?

The professionals named in the filing: Architect: MANISH SHAH; Architect: MEGHA FERNANDES; Engineer: HARESH PATEL; Engineer: PRAGNESH OZA; Chartered Accountant: NEHALI & CO; Chartered Accountant: KOTHARI JAIN & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWED GANGA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWED GANGA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWED GANGA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.