ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Sunder Srushti Wing D6

Registered No litigation declared Residential / Group Housing project

Sunder Srushti Wing D6

By SURESH DHARMAVAT AND ASSOCIATES

RG-MH-52068 · RERA P52100048328 · Last updated on MahaRERA portal: 24 Apr 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

Sunder Srushti Wing D6 is a Residential / Group Housing project by SURESH DHARMAVAT AND ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100048328 on 26 Dec 2022. Possession is promised by 31 Dec 2026.

At a glance

Project

  • NameSunder Srushti Wing D6
  • TypeResidential / Group Housing
  • Location
    • Sun City Road
    • Vadgaon Budruk
    • Wadgaon Bk
    • Haveli
    • Pune
    • 411051
  • Pincode411051
  • RERA no.P52100048328
  • ReraGenie IDRG-MH-52068

Builder

  • NameSURESH DHARMAVAT AND ASSOCIATES
  • Entity typePartnership
  • PartnersSURESH DEVARAM DHARMAVAT, YASH SURESH DHARMAVAT
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Dec 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing D6NA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Wing D6: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed99

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots99
Closed/Covered32
Open Space67

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area733 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Murlidhar Khade & 27 OthersWadgaon BkPune

Approvals and building plan

Permissible FSI4233.0
Proposed, not sanctioned4,233 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShashi Chambers, Pune Satara Road, Near ST Stand, Pune

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPandit Joshi and Associates
EngineerG A Bhilare Consultants Private Limited
Chartered AccountantV T & Associates
PartnerRole in project
SURESH DHARMAVAT AND ASSOCIATES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Nov 2024

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf24 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf13 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf7 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (2022-23).pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf8 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf8 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf16 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf16 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf11 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Details.pdf9 Dec 2022
CERSAI detailsFile: CERSAI Report.pdf8 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf8 Dec 2022
Other - FinanceFile: Encumbrance Certificate.pdf8 Dec 2022
Layout approvalFile: Layout.pdf24 Nov 2022
Building plan approvalFile: Plan 1.pdf24 Nov 2022
Building plan approvalFile: Plan 2.pdf24 Nov 2022
Building plan approvalFile: Plan 3.pdf24 Nov 2022
PAN CardFile: PAN Card.pdf24 Nov 2022
Copy of the legal title reportFile: Title Search Report Annexure.pdf24 Nov 2022
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate.pdf24 Nov 2022
Details of encumbrances concerned to LegalFile: Encumbrance Certificate.pdf24 Nov 2022
Copy of Layout Approval (in case of layout)File: Layout.pdf24 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan 1.pdf24 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan 2.pdf24 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan 3.pdf24 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf24 Nov 2022
Declaration about Commencement CertificateFile: Format D.pdf24 Nov 2022
Declaration in FORM BFile: Form B.pdf24 Nov 2022
Proforma of Allotment letterFile: Allotment Letter.pdf24 Nov 2022
Proforma of Agreement for saleFile: Sample Agreement.pdf24 Nov 2022
Deviation Report with respect to Allotment letterFile: Deviation Report - Allotment Letter.pdf24 Nov 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report - Agreement.pdf24 Nov 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SUNDER SANSKRUTI PHASE 2SHREE JAGDAMBA MATAJI MANDIR MARG DHARMAVAT NAGAR WADGAON KHURD PUNE 411041130CompletedDec 2017Jun 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sunder Srushti Wing D6 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vadgaon Budruk13,700+ in Pune

Builder: SURESH DHARMAVAT AND ASSOCIATES

SURESH DHARMAVAT AND ASSOCIATES has 3 registrations on MahaRERA, including SUNDER SANSKRUTI PHASE 3 and Sunder Sanskruti Phase 4. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Sunder Srushti Wing D6 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sunder Srushti Wing D6?

The registered promoter entity is SURESH DHARMAVAT AND ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sunder Srushti Wing D6?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sunder Srushti Wing D6?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sunder Srushti Wing D6?

The professionals named in the filing: Architect: Pandit Joshi and Associates; Engineer: G A Bhilare Consultants Private Limited; Chartered Accountant: V T & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sunder Srushti Wing D6?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sunder Srushti Wing D6. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sunder Srushti Wing D6 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.