Home / Browse projects / Pune, Maharashtra / VENKATESH SKYDALE PHASE 4
VENKATESH SKYDALE PHASE 4
RG-MH-16303 · RERA P52100025615 · Last updated on MahaRERA portal: 25 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- 1 complaint at MahaRERA
Clear
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 3 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VENKATESH SKYDALE PHASE 4 is a Others project by Shree Venkatesh Buildcon in Pune, Maharashtra, registered with MahaRERA as P52100025615 on 1 Jul 2020. Possession is promised by 30 Jun 2027. 108 of the 126 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameVENKATESH SKYDALE PHASE 4
- TypeOthers
- Location
- VITTHALWADI SINHAGAD ROAD
- HINGANE KHURD
- Pune (M Corp.)
- Pune City
- Pune
- 411051
- Pincode411051
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100025615
- ReraGenie IDRG-MH-16303
Builder
- NameShree Venkatesh Buildcon
- Entity typePartnership
- GSTIN27ABGFS4527F1Z4
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersANKUSH BHIMRAO ASABE, LAHURAJ BHIMRAO ASABE, VITTHAL BAJIRAO GOSAVI
- Other registrations3 more →
- Completed3 of 4
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Jul 2020
- Promised completion30 Jun 2027
- Revised completionNone
- Buildings1 building record
- Documents filed252 files
Current status
Figures as on 25 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D BUILDING | NA | 27 | 22 | 126 | 0 | 126 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
D BUILDING: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 25 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed120
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership9
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| ANAND BAJIRAO GOSAVI AND OTHERS | Pune (M Corp.) | Pune |
| TULSHIDAS BAJIRAO GOSAVI AND OTHERS | Pune (M Corp.) | Pune |
| GANESH RAMBHAU GOSAVI AND OTHERS | Pune (M Corp.) | Pune |
| TUSHAR SAMBHAJI GOSAVI AND OTHERS | Pune (M Corp.) | Pune |
| SAGAR DIGAMBAR GOSAVI AND OTHERS | Pune (M Corp.) | Pune |
| ULKA D GOSAVI | Pune (M Corp.) | Pune |
| MADHUKAR TUKARAM GOSAVI AND OTHERS | Pune (M Corp.) | Pune |
| VITTHAL BAJIRAO GOSAVI AND OTHERS | Pune (M Corp.) | Pune |
| KETAN SAMBHAJI GOSAVI | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| D BUILDING | NA | Rs 65.86 cr | Rs 65.86 cr |
| - | NA | Rs 2.78 cr | Rs 2.78 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | S A V L I ARCHITECTS |
| Engineer | MILIND KADAM |
| Chartered Accountant | PRITAM LAKHOTIA |
| Chartered Accountant | AVINASH UTGIKAR |
| Partner | Role in project |
|---|---|
| Shree Venkatesh Buildcon | - |
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 382/2021 | CIVIL | PENDING |
| 382/2021/2021 | SMALL CAUSE COURT | Ongoing |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12401232 | Shree Venkatesh Buildcon | Anish Umesh Sharma | 25/12/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Nov 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Nov 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed252
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 252 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: ARCH CERTIFICATE SKYDALE PH-4-WING D.pdf | 25 Feb 2026 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE SKYDALE WING D-PH-4-20-2-2026.pdf | 25 Feb 2026 |
| Withdrawal Update Form 3File: CA CERTIFICATE SKYDALE WING D-PH-4-20-2-2026.pdf | 25 Feb 2026 |
| Withdrawal Update Form 1File: ARCH CERTIFICATE SKYDALE WING D-DEC-25.pdf | 6 Jan 2026 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE SKYDALE WING D-DEC-25.pdf | 6 Jan 2026 |
| Withdrawal Update Form 3File: CA CERTIFICATE SKYDALE PHASE -4-DEC-25.pdf | 6 Jan 2026 |
| Withdrawal Update Form 1File: ARCH CERTIFICATE SKYDALE PH-4-05-12-25.pdf | 9 Dec 2025 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE SKYDALE PH-4-05-12-25.pdf | 9 Dec 2025 |
| Withdrawal Update Form 3File: CA CERTIFICATE SKYDALE PH-4-05-12-2025.pdf | 9 Dec 2025 |
| Form 5 (FY 2022-2023)File: FORM 5 SKYDALE MAR-23- PHASE -4.pdf | 18 Oct 2025 |
| Form 5 (FY 2021-2022)File: FORM 5 VENKATESH SKYDALE PHASE -4.pdf | 18 Oct 2025 |
| Form 5 (FY 2020-2021)File: Form 5 20-21 SKYDALE PHASE 4-14-6-2021.pdf | 18 Oct 2025 |
| Form 5 (FY 2023-2024)File: FORM 5 SKYDALE WING D-PH-4-MAR-24.pdf | 16 Oct 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 SKYDALE PH-4_15-10-2025.pdf | 14 Oct 2025 |
| Withdrawal Update Form 1File: ARCH CERTIFICATE SKYDALE PH-4-SEPT-25.pdf | 9 Oct 2025 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE SKYDALE PH-4-SEPT-25.pdf | 9 Oct 2025 |
| Withdrawal Update Form 3File: CA CERTIFICATE SKYDALE PH-4-SEPT-2025.pdf | 9 Oct 2025 |
| Withdrawal Update Form 1File: ARCH CERTIFICATE SKYDALE-JUN-2025.pdf | 15 Jul 2025 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE SKYDALE-JUN-2025.pdf | 15 Jul 2025 |
| Withdrawal Update Form 3File: CA CERTIFICATE SKDALE PH-4-JUN-2025.pdf | 15 Jul 2025 |
| Form 1File: ARCH CERTIFICATE SKYDALE WING D.pdf | 12 Jun 2025 |
| Form 2File: ENGG CERTIFICATE SKYDALE PH-4.pdf | 12 Jun 2025 |
| Form 3File: CA CERTIFICATE SKYDALE PH-4 WING D.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY SKYDALE WING D.pdf | 12 Jun 2025 |
| Form 1File: ARCH CERTIFICATE SKYDALE WING D.pdf | 12 Jun 2025 |
| Form 2File: ENGG CERTIFICATE SKYDALE WING D.pdf | 12 Jun 2025 |
| Form 3File: CA CERTIFICATE SKYDALE WING D PH-4.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSER OF SOLD INVENTORY SKYDALE WING D.pdf | 12 Jun 2025 |
| Form 1File: ARCH CERTIFICATE SKYDALE PH-4.pdf | 12 Jun 2025 |
| Form 2File: ENGG CERTIFICATE SKYDALE PH-4.pdf | 12 Jun 2025 |
| Form 3File: CA CERTIFICATE SKYDALE PH-4.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSER OF SOLD UNSOLD INVENTORY 2-1-25.pdf | 12 Jun 2025 |
| Form 1File: ARCH CERTIFICATE SKYDALE PH-4.pdf | 12 Jun 2025 |
| Form 2File: ENGG CERTIFICATE SKYDALE PH-4.pdf | 12 Jun 2025 |
| Form 3File: CA CERTIFICATE SKYDALE PH-4.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSER OF SOLD INVENTORY SKYDALE PH-4-2-4-2025.pdf | 12 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SKYDALE PH-4.pdf | 11 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SKYDALE PH-4.pdf | 11 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SKYDALE PH-4.pdf | 11 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE SKYDALE PH-4.pdf | 11 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD INVENTORY SKYDALE PH-4-2-4-2025.pdf | 11 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A SKYDALE PH-4-MAR-25.pdf | 11 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A SKYDALE PH-4-DEC-24.pdf | 11 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SKYDALE PH-4.pdf | 10 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SKYDALE PH-4.pdf | 10 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE SKYDALE PH-4.pdf | 10 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD UNSOLD INVENTORY 2-1-25.pdf | 10 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SKYDALE D WING.pdf | 7 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SKYDALE D WING.pdf | 7 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE SKYDALE WING D.pdf | 7 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY SKYDALE D WING.pdf | 7 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SKYDALE WING D.pdf | 30 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY SKYDALE D WING.pdf | 30 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SKYDALE WING D.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SKYDALE WING D PH-4.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE SKYDALE WING D.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD INVENTORY SKYDALE WING D.pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A SKYDALE PH-4-SEPT-24.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SKYDALE WING D-PH-4-MAR-24.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SKYDALE WING D.pdf | 8 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE SKYDALE PH-4.pdf | 8 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A SKYDALE PH-4-JUNE-24.pdf | 8 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY SKYDALE WING D.pdf | 8 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SKYDALE PH-4 WING D.pdf | 8 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SKYDALE WING D.pdf | 15 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE SKYDALE WING D.pdf | 15 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SKYDALE D WING.pdf | 15 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE VENKATESH SKYDALE WING D PH-4.pdf | 21 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE SKYDALE WING D PH-4.pdf | 21 May 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY SKYDALE WING D PH-4.pdf | 21 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE VENKATESH SKYDALE WING D PH-4.pdf | 21 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SKYDALE PH-4 WING D.pdf | 6 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE SKYDALE PH-4.pdf | 6 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A SKYDALE PH-4-MAR-24.pdf | 6 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD UNSOLD INVENTORY SKYDALE PH-4.pdf | 6 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE VENKATESH SKYDALE PH-4.pdf | 6 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE VENKATESH SKYDALE PH-4.pdf | 6 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SKYDALE PH-4-WING D-8-3-24.pdf | 23 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE SKYDALE PH-4-WING D-8-3-24.pdf | 23 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE VENKATESH SKYDALE PH-4.pdf | 23 Mar 2024 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| VENKATESH GRAFFITI PHASE 1 | SR NO 31 PLUS 35 PART KESHAV NAGAR MUNDHWA PUNE 411036 | 358 | Completed | Jul 2017 | Apr 2017 |
| VENKATESH LAKE VISTA | SR NO 8 PLUS 9 PART DATTANAGAR JAMBHULWADI ROAD AMBEGAON KHURD PUNE 411046 | 672 | Completed | Dec 2015 | Dec 2015 |
| VENKATESH SHARVIL | SR NO 26 PART DHAYARI PUNE 411041 | 186 | Completed | Mar 2014 | Jul 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 252 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VENKATESH SKYDALE PHASE 4 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near HINGANE KHURD13,700+ in Pune
Filed coordinates, straight-line distance. 131 registered projects within 2 km.
Aura Waters Phase II
Ranawat Properties
OM PARADISE
OM GHULE LEGACIES LLP
Aura Waters Phase -I
Ranawat Properties
RAMANA PRIMAVISTA
RAJENDRA VINAYAK PATAHRE
Kanchan Heights
Orbiz Estate
PARK LIFE WING C
KUDALE PATIL AND JADHAV VENTURES
Builder: Shree Venkatesh Buildcon
Shree Venkatesh Buildcon has 4 registrations on MahaRERA, including VENKATESH SKYDALE PHASE 1 and Venkatesh Skydale Phase 2. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if VENKATESH SKYDALE PHASE 4 is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VENKATESH SKYDALE PHASE 4?
The registered promoter entity is Shree Venkatesh Buildcon, a partnership as per the filing. Its GSTIN 27ABGFS4527F1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VENKATESH SKYDALE PHASE 4?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VENKATESH SKYDALE PHASE 4?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VENKATESH SKYDALE PHASE 4?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VENKATESH SKYDALE PHASE 4?
The professionals named in the filing: Architect: S A V L I ARCHITECTS; Engineer: MILIND KADAM; Chartered Accountant: PRITAM LAKHOTIA; Chartered Accountant: AVINASH UTGIKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VENKATESH SKYDALE PHASE 4?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback