Sumit Atulyam
By Sumit Matunga Builders Private Limited
RG-MH-30633 · RERA P51900030966 · Last updated on MahaRERA portal: 20 Dec 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sumit Atulyam is a Residential / Group Housing project by Sumit Matunga Builders Private Limited in Mahim, 400016, registered with MahaRERA as P51900030966 on 29 Sep 2021. Possession was promised by 31 Dec 2024 and is now 22 months past that date.
At a glance
Project
- NameSumit Atulyam
- TypeResidential / Group Housing
- Location
- Sitaram Ganesh Desai marg
- Mahim
- 400016
- Pincode400016
- RERA no.P51900030966
- ReraGenie IDRG-MH-30633
Builder
- NameSumit Matunga Builders Private Limited
- Entity typeCompany
- Managing DirectorMitaram Ramlal Jangid
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 Sep 2021
- Promised completion31 Dec 2024
- Revised completionNone
- Buildings2 building records
- Documents filed95 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Sumit Atulyam Phase I Wing A Wing and Wing B upto 17th Floor | NA | 26 | 0 | 0 | 0 | 0 |
| Sumit Atulyam Phase II - Wing B, 18th to 21st Floor | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 20 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 85%.
Sumit Atulyam Phase I Wing A Wing and Wing B upto 17th Floor84%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
Sumit Atulyam Phase II - Wing B, 18th to 21st Floor27%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 20 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 60% |
| Electrical meter room, sub-station, receiving station | Yes | 20% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed115
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Sumit Atulyam Phase I Wing A Wing and Wing B upto 17th Floor | 95 | 95 |
| Sumit Atulyam Phase II - Wing B, 18th to 21st Floor | 20 | 20 |
Land and ownership5
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Sanjay Damodardas Shah HUF | - | Mumbai City |
| Uday Damodardas Shah HUF | - | Mumbai City |
| Sanjay Damodardas Shah | - | Mumbai City |
| Uday Damodardas Shah | - | Mumbai City |
| Nilam Apartment Co operative Society Ltd | - | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pandurang Narayan Bhobe |
| Engineer | KC Shah & Associates |
| Chartered Accountant | RS Gokani & Co Charted Accountant |
| Partner | Role in project |
|---|---|
| Sumit Matunga Builders Private Limited | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Oct 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Sep 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Jun 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed95
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sumit Atulyam CA Cert Nov 2023.pdf | 20 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sumit Atulyam Engg Cert March 2023.pdf | 27 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sumit Atulyam CA cert.pdf | 27 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sumit Atulyam Phase 1 oct 2023 arch cert.pdf | 25 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arcenciel Phase 2 oct 2023 arch cert.pdf | 25 Oct 2023 |
| Details of encumbrancesFile: Letter to RERA 29092023.pdf | 29 Sep 2023 |
| Building plan approvalFile: Plan 1 25072022.pdf | 16 Jun 2023 |
| Building plan approvalFile: Plan 2 25072022.pdf | 16 Jun 2023 |
| Building plan approvalFile: Plan 3 25072022.pdf | 16 Jun 2023 |
| Building plan approvalFile: Plan 4 25072022.pdf | 16 Jun 2023 |
| Building plan approvalFile: Plan 5 25072022.pdf | 16 Jun 2023 |
| Building plan approvalFile: Plan 6 25072022.pdf | 16 Jun 2023 |
| Building plan approvalFile: Plan 7 25072022.pdf | 16 Jun 2023 |
| Building plan approvalFile: Plan 8 25072022.pdf | 16 Jun 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 1 25072022.pdf | 16 Jun 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 2 25072022.pdf | 16 Jun 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 3 25072022.pdf | 16 Jun 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 4 25072022.pdf | 16 Jun 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 5 25072022.pdf | 16 Jun 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 6 25072022.pdf | 16 Jun 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 7 25072022.pdf | 16 Jun 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 8 25072022.pdf | 16 Jun 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Atulyam CC 26052023.pdf | 16 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SUMIT ATULYAM PHASE 1.pdf | 10 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SUMIT ATULYAM PHASE 2.pdf | 10 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Atulyam Arch Certificate phase 1 - Aug 2022.pdf | 3 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Atulyam Arch Certificate phase 2 - Aug 2022.pdf | 3 Aug 2022 |
| Building plan approvalFile: Amended Plan letter.pdf | 12 Apr 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Amended Plan letter.pdf | 12 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Atulyam Further CC.pdf | 12 Apr 2022 |
| Building plan approvalFile: 1 Drawings 30122021.pdf | 2 Feb 2022 |
| Building plan approvalFile: 2 Drawings 30122021.pdf | 2 Feb 2022 |
| Building plan approvalFile: 3 Drawings 30122021.pdf | 2 Feb 2022 |
| Building plan approvalFile: 4 Drawings 30122021.pdf | 2 Feb 2022 |
| Building plan approvalFile: 6 Drawings.pdf | 2 Feb 2022 |
| Building plan approvalFile: 6 Drawings 30122021.pdf | 2 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 Drawings 30122021.pdf | 2 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 2 Drawings 30122021.pdf | 2 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 3 Drawings 30122021.pdf | 2 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 4 Drawings 30122021.pdf | 2 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 6 Drawings.pdf | 2 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 6 Drawings 30122021.pdf | 2 Feb 2022 |
| Building plan approvalFile: IOD as on 30122021 Sumit Atulyam.pdf | 1 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: IOD as on 30122021 Sumit Atulyam.pdf | 1 Feb 2022 |
| Details of encumbrancesFile: Encumbrance 25012022.pdf | 25 Jan 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sumit Atulyam Phase 1 Form 2 engg 31122021.pdf | 14 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sumit Atulyam Form 2A 31122021.pdf | 14 Jan 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sumit Atulyam Phase 2 Architect Certificate 26112021.pdf | 6 Jan 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sumit Atulyam Phase 1 Architect Certificate 26112021.pdf | 6 Jan 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 Sumit Atulyam 31122021.pdf | 6 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Sumit Atulyam 2020 2021.pdf | 6 Jan 2022 |
| Copy of the legal title reportFile: Indenture of Mortgage Capri Global Capital Ltd and SMBPL 12102021.pdf | 16 Oct 2021 |
| Details of encumbrancesFile: Indenture of Mortgage Capri Global Capital Ltd and SMBPL 12102021.pdf | 16 Oct 2021 |
| Layout approvalFile: Profoma A Building Plan Summary.pdf | 17 Sep 2021 |
| Building plan approvalFile: Profoma A Building Plan Summary.pdf | 17 Sep 2021 |
| Copy of the legal title reportFile: Title Certificate.pdf | 17 Sep 2021 |
| Copy of the legal title reportFile: Title Certificate.pdf | 17 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: Profoma A Building Plan Summary.pdf | 17 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Profoma A Building Plan Summary.pdf | 17 Sep 2021 |
| Building plan approvalFile: 1 IOD PLAN.pdf | 7 Sep 2021 |
| Building plan approvalFile: 3 IOD PLAN.pdf | 7 Sep 2021 |
| Layout approvalFile: 1 IOD PLAN.pdf | 7 Sep 2021 |
| Layout approvalFile: 2 IOD PLAN.pdf | 7 Sep 2021 |
| Layout approvalFile: 3 IOD PLAN.pdf | 7 Sep 2021 |
| Building plan approvalFile: IOD CERTIFICATE 19082021.pdf | 7 Sep 2021 |
| Building plan approvalFile: 2 IOD PLAN.pdf | 7 Sep 2021 |
| Details of encumbrancesFile: Letter of Nil Encumberance Sumit Atulyam.pdf | 7 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 1 IOD PLAN.pdf | 7 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 2 IOD PLAN.pdf | 7 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 3 IOD PLAN.pdf | 7 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: IOD CERTIFICATE 19082021.pdf | 7 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 IOD PLAN.pdf | 7 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 2 IOD PLAN.pdf | 7 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 3 IOD PLAN.pdf | 7 Sep 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 19082021.pdf | 7 Sep 2021 |
| Declaration about Commencement CertificateFile: Format D Sumit Atulyam.pdf | 7 Sep 2021 |
| Declaration in FORM BFile: Declaration Form B compressed.pdf | 7 Sep 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Phase 1 07092021.pdf | 7 Sep 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Phase 2 07092021.pdf | 7 Sep 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 07092021.pdf | 7 Sep 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 95 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Sumit Atulyam on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mahim
Island Cove
LH Residential Housing Private Limited
Midtown Bay
Rising Sun Impex Private Limited
Island Cove Tower 4
LH Residential Housing Private Limited, Sh
Bayline Residences
HRUB Infra Projects Pvt Ltd
VITALIS
SURAJ ESTATE DEVELOPERS LTD
Suraj One Business Bay
ICONIC PROPERTY DEVELOPERS PVT LTD
Builder: Sumit Matunga Builders Private Limited
Sumit Matunga Builders Private Limited has 1 registration on MahaRERA, including Sumit Atulyam. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that Sumit Atulyam shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Sumit Atulyam is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sumit Atulyam?
The registered promoter entity is Sumit Matunga Builders Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sumit Atulyam?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Sumit Atulyam?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sumit Atulyam?
The professionals named in the filing: Architect: Pandurang Narayan Bhobe; Engineer: KC Shah & Associates; Chartered Accountant: RS Gokani & Co Charted Accountant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sumit Atulyam?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback