Home / Browse projects / Nashik, Maharashtra / STAR LINE
STAR LINE
RG-MH-09037 · RERA P51600013960 · Last updated on MahaRERA portal: 10 Feb 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 2 months past the filed date
- Completion date moved by 83 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
STAR LINE is a Commercial project by DEEPAK KALYANJI CHANDE in Nashik, Maharashtra, registered with MahaRERA as P51600013960 on 2 Nov 2017. Possession was promised by 31 Aug 2026 and is now 2 months past that date. The completion date has moved by 83 months from the original filing.
At a glance
Project
- NameSTAR LINE
- TypeCommercial
- Location
- MUMBAI AGRA HIGHWAY
- NEAR TRACTOR HOUSE
- Nashik
- 422011
- Pincode422011
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600013960
- ReraGenie IDRG-MH-09037
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on2 Nov 2017
- Promised completion31 Aug 2026
- Revised completionRevised to 31 Aug 2026 (originally 30 Sep 2019)
- Buildings1 building record
- Documents filed34 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| STAR LINE | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 10 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 75%.
STAR LINE: 49% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 65% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 10 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 20% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 25% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed100
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| PRAKASH RAMAN CHOUDHARI | Nashik | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SUMIT KUMATH |
| Engineer | SANJEEV PATEL |
| Partner | Role in project |
|---|---|
| DEEPAK KALYANJI CHANDE | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs we completed 100% construction works of Basement, Ground Floors, part completion for the same is received, and Also completed RCC Super Structure of First, Second and Third Floor as approved by Municipal Authority. Initially we intent to complete it on customized basis of as per client need but booking have not taken place. Hence we kindly request to you please grant us extension. Currently we are in process to construct and run the Hotel or Hospital, as soon as building plan is approved we will upload it on RERA website.
Reason as filed by the promoterAs we completed 100% construction works of Basement, Ground Floors and Also completed RCC Super Structure of First, Second and Third Floor as approved by Municipal Authority. Initially we intent to complete it on customized basis of as per client need but however booking have not taken place. But now we decided to go ahead and complete the project as per approved plans. Hence we kindly request to you please grant us extension. Also another one reason for delay was hard rock at basement bottom which require 4-6 months to excavate.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Oct 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Oct 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Oct 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Oct 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed34
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Star Line.pdf | 10 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Star Line.pdf | 4 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A Star Line 19-20_compressed.pdf | 21 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A Star Line 19-20_compressed.pdf | 21 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Star Line_compressed.pdf | 21 Aug 2021 |
| Declaration about Commencement CertificateFile: Format D Star Line.pdf | 16 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Starline_Dwarka.pdf | 16 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 star line_compressed.pdf | 14 Aug 2021 |
| Certificates of CA (Form 5)File: Starline_Dwarka.pdf | 26 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 7 Mar 2020 |
| Certificates of CA (Form 3)File: Star Line-CA- Certificate_compressed.pdf | 7 Mar 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Star Line.pdf | 14 Nov 2019 |
| Certificates of CA (Form 3)File: CA Certificate 1.pdf | 21 Oct 2019 |
| Certificates of CA (Form 5)File: Star Line.pdf | 21 Oct 2019 |
| Details of encumbrancesFile: Mortgage Deed.pdf | 26 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect's Certificate (Star Line).pdf | 30 Nov 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: STAR LINE.pdf | 3 Nov 2018 |
| Certificates of CA (Form 5)File: star line-1.pdf | 10 Oct 2018 |
| Proforma of Allotment letterFile: UploadAgreement for Sale Copy.pdf | 26 Oct 2017 |
| Proforma of Allotment letterFile: Allotment_Letter_-_Draft.pdf | 26 Oct 2017 |
| Details of encumbrancesFile: eNCUMBRANCES.pdf | 25 Oct 2017 |
| Declaration in FORM BFile: Promoter.pdf | 25 Oct 2017 |
| Building plan approvalFile: 1 1.pdf | 24 Oct 2017 |
| Building plan approvalFile: 2 2.pdf | 24 Oct 2017 |
| Building Plan Approval (IOD)File: 1 1.pdf | 24 Oct 2017 |
| Building Plan Approval (IOD)File: 2 2.pdf | 24 Oct 2017 |
| Certificates of CA (Form 3)File: 1 3.pdf | 24 Oct 2017 |
| Certificates of CA (Form 3)File: 4-7.pdf | 24 Oct 2017 |
| Layout approvalFile: 1.pdf | 17 Oct 2017 |
| Copy of the legal title reportFile: title search-1.pdf | 17 Oct 2017 |
| Copy of the legal title reportFile: title search-2.pdf | 17 Oct 2017 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 17 Oct 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate-1.pdf | 17 Oct 2017 |
| PAN CardFile: PAN.pdf | 13 Oct 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SAI ANAND PRIDE | SINNAR GHOTI ROAD NEAR NAVJEEVAN SCHOOL SINNAR NASHIK | 112 | Completed | Apr 2017 | Apr 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 9 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 34 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep STAR LINE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR TRACTOR HOUSE4,100+ in Nashik
Filed coordinates, straight-line distance. 110 registered projects within 2 km.
Anandvan Housing Complex
Ravi Mahajan Buildcon LLP
SHREEJI INFINIA
SHREEJI LIFE SPACE
Waterways
Sanklecha Construction Private Limited
Shreejis Gujral Arcade
SHREEJI LIFE SPACE
VRAJ METROPOLIS SOUTH
SHREE INFRA SPACE
ALEEF BREEZE APARTMENT
KHATIB BUILDERS AND DEVELOPERS
See every Nashik project, with the district possession charts
Builder: DEEPAK KALYANJI CHANDE
DEEPAK KALYANJI CHANDE has 10 registrations on MahaRERA, including SAI RATAN RESIDENCY and STAR LINE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if STAR LINE is delayed beyond 31 Aug 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of STAR LINE?
The registered promoter entity is DEEPAK KALYANJI CHANDE, an individual as per the filing. Its GSTIN 27AAYPC1156H1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in STAR LINE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for STAR LINE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at STAR LINE?
The professionals named in the filing: Architect: SUMIT KUMATH; Engineer: SANJEEV PATEL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in STAR LINE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback