ReraGenieLog inGet a buyer report

Home / Browse projects / Sindhudurg, Maharashtra / SRISHTI AANGAN PHASE 2

Completed No litigation declared Others project

SRISHTI AANGAN PHASE 2

By NEERAJ MOHAN DESAI HUF

RG-MH-29636 · RERA P52900028662 · Last updated on MahaRERA portal: 23 Feb 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.
Sep 2026Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

SRISHTI AANGAN PHASE 2 is a Others project by NEERAJ MOHAN DESAI HUF in Sindhudurg, Maharashtra, registered with MahaRERA as P52900028662 on 25 Mar 2021. The registration is recorded completed; possession was promised by 15 Sep 2026.

At a glance

Project

  • NameSRISHTI AANGAN PHASE 2
  • TypeOthers
  • Location
    • MUNICIPAL ROAD
    • BEHIND KALSULKAR ENGLISH SCHOOL
    • Sawantwadi (M Cl)
    • Sawantwadi
    • Sindhudurg
    • 416510
  • Pincode416510
  • RERA no.P52900028662
  • ReraGenie IDRG-MH-29636

Builder

  • NameNEERAJ MOHAN DESAI HUF
  • Entity typeOthers
  • Named personsNEERAJ MOHAN DESAI HUF, VAIDYEHI NEERAJ DESAI
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredMar 2021PromisedSep 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Mar 2021
  • Promised completion15 Sep 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SRISHTI AANGAN PHASE 2NA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

SRISHTI AANGAN PHASE 2: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,950 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
MANU LAWRENCE FERRAOAndheriMumbai Suburban
LESLIE LAWRENCE FERRAO-Mumbai City

Approvals and building plan

Permissible FSI1944.27
Proposed, not sanctioned1,944 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRANESHWAR PLAZA NEAR MOTI TALAV SAWANTWADI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYESHWANT A NAIK
EngineerYESHWANT A NAIK
Chartered AccountantC A RANADE & CO
PartnerRole in project
NEERAJ MOHAN DESAI HUF-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Apr 2024

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 June 2021.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 March 2021.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 16 Dec 2024.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15 Sep 2024.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14 June 2024.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13 March 2024.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12 Dec 2023.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 Sep 2023.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 June 2023.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 March 2023.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Dec 2022.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 Sep 2022.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 June 2022.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 March 2022.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Dec 2021.pdf23 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Sep 2021.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 16 Dec 2024.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 15 Sep 2024.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 14 june 2024.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 13 March 2024.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12 Dec 2023.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 sep 2023.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 June 2023.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 March 2023.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 sep 2022.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 june 2022.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 March 2022.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Dec 2021.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Sep 2021.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 june 2021.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 March 2021.pdf23 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 Dec 2022.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 Sep 2022.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 16 Dec 2024.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 15 Sep 24.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 14 June 2024.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13 March 2024.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 Dec 2023.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 Sep 2023.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 June 2023.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 March 2023.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 Dec 2022.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 June 2022.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 March 2022.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Dec 2021.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Sep 2021.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 June 2021.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 March 2021.pdf23 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory Phase 2.pdf23 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE 21-22.pdf23 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE 22-23.pdf23 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QUALITY ASSURANCE 23-24.pdf23 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Certificate No 5.pdf21 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FOC ORDER.pdf21 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: C A Certificate No 5.pdf13 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SRISHTI CREATORS PHASE II.pdf17 Dec 2022
Copy of the legal title reportFile: Search Report New.pdf15 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: Muncipal Permission-compressed.pdf15 Mar 2021
Layout approvalFile: N 1-converted.pdf14 Mar 2021
Building plan approvalFile: N 2-converted.pdf14 Mar 2021
Building plan approvalFile: N 1-converted.pdf14 Mar 2021
PAN CardFile: HUF PAN.pdf14 Mar 2021
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf14 Mar 2021
Copy of Layout Approval (in case of layout)File: N 1-converted.pdf14 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: N 2-converted.pdf14 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: N 1-converted.pdf14 Mar 2021
Declaration in FORM BFile: FORM B PROMOTAR.pdf14 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf14 Mar 2021
Proforma of Allotment letterFile: Final Agreemnet for sale.pdf14 Mar 2021
Proforma of Allotment letterFile: ALLOTMENT LETTER-compressed.pdf14 Mar 2021

How this compares with Sindhudurg

21%of Sindhudurg projects moved their completion datethis one has not
30%of Sindhudurg registrations have lapsed or been cancelledthis one is completed

Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.

Keep SRISHTI AANGAN PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BEHIND KALSULKAR ENGLISH SCHOOL530+ in Sindhudurg

Builder: NEERAJ MOHAN DESAI HUF

NEERAJ MOHAN DESAI HUF has 2 registrations on MahaRERA, including SRISHTI AANGAN and SRISHTI AANGAN PHASE 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sindhudurg district page.

Frequently asked questions

What are my rights if SRISHTI AANGAN PHASE 2 is delayed beyond 15 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SRISHTI AANGAN PHASE 2?

The registered promoter entity is NEERAJ MOHAN DESAI HUF, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SRISHTI AANGAN PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SRISHTI AANGAN PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SRISHTI AANGAN PHASE 2?

The professionals named in the filing: Architect: YESHWANT A NAIK; Engineer: YESHWANT A NAIK; Chartered Accountant: C A RANADE & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SRISHTI AANGAN PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SRISHTI AANGAN PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SRISHTI AANGAN PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.