Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
22 of 30Construction stages doneacross 3 buildings; furthest along: Staircases, 75%
11 of 141Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 329 documents Report an error

SPLENDOUR COUNTY WAGHOLI is a Others project by PS DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100021548 on 8 Jul 2019. Possession was promised by 15 Jun 2026 and is now 4 months past that date. The completion date has moved by 24 months from the original filing. 130 of the 141 units on this registration are recorded sold or booked, and 22 of 30 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSPLENDOUR COUNTY WAGHOLI
  • TypeOthers
  • Location
    • NAGAR ROAD
    • BEHIND WAGHESHWAR MANDIR
    • WAGHOLI
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100021548
  • ReraGenie IDRG-MH-01955

Builder

  • NamePS DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAHFP6567G1ZU
  • PartnerFAKIRA BABURAO PAWAR
  • Declared earlier projects3 →

Key dates

4 months past promisethis monthRegisteredJul 2019First promiseJun 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Jul 2019
  • Promised completion15 Jun 2026
  • Revised completionRevised to 15 Jun 2026 (originally 15 Jun 2024)
  • Buildings3 building records
  • Documents filed329 files

Current status

92%130 of 141 units booked
98.7%Work done, per cost certificate

Figures as on 17 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D BUILDINGNA141272072
G BUILDINGNA1412551368
COMMERCIAL BUILDINGNA33011

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 30 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 75%.

D BUILDING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G BUILDING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
COMMERCIAL BUILDING48%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed257

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots257
Closed/Covered83
Open Space167
Stilt / Ground7
BuildingClosed/CoveredOpen SpaceStilt / GroundTotal
D BUILDING2472096
G BUILDING59950154
COMMERCIAL BUILDING0077

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area16,310 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Jun 2025
LandownerVillageDistrict
VIJAYSINGH JAYSINGHRAO JADHAVRAOPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPUNE METROPOLITAN REGION DEVELOPMENT AUTHORITY PUNE
Permissible FSI9428.04
Proposed, not sanctioned9,428 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDR KETKAR MARG 79 3 KAMALA NEHARU PARK ERANDAWANA PUNE 411004
Estimated costRs 41.06 cr
Cost incurredRs 40.53 cr
Work done98.7%
BuildingWingEstimatedIncurred
D BUILDINGNARs 19.43 crRs 19.43 cr
G BUILDINGNARs 18.89 crRs 18.89 cr
-NARs 2.10 crRs 2.02 cr
COMMERCIAL BUILDINGNARs 65.21 lakhRs 20.01 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIKAS ACHALKAR
EngineerBICS THROUGH PROPRIETOR PRASAD C KHANDEKAR
Chartered AccountantGAJENDRA S JAIN
PartnerRole in project
PS DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100022953Jun 2024 → Jun 2025

Reason as filed by the promoterDue to delayed in obtaining revised plan sanction from Municipal Corporation and other various reasons beyond our control the Projected completion date may need to extend up 15/06/2025. We have already completed construction of D Wing and only Wing G is under construction. Hence we request you to extend the date of completion.

EA11072502050Jun 2024 → Jun 2026

Reason as filed by the promoterDue to delay in obtaining revision in sanction plan from Municipal Corporation and some other reasons beyond our control the Projected completion date may need to extend up 15/06/2026. We have already completed construction of D Wing and G Wing. But as per proposed revision in plan, one commercial unit will be proposed as new separate building and hence we need to revise Maharera account. To complete such proposed buildings construction and to obtain Occupation Certificate from Municipal Corporation, we need to extend the date of Completion of Project. Hence, we request you to extend the date

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12400508PS DEVELOPERSMr Mahesh Aba Avhale (Respondent)22/10/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jun 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Oct 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jan 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Oct 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Nov 2022

Documents filed329

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 329 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 01 Splendour Couny 30 June 2026.pdf17 Jul 2026
Withdrawal Update Form 2File: Form 02 Splendour County 30-06-2026.pdf17 Jul 2026
Withdrawal Update Form 3File: Form 03 Splendour County 30-06-26.pdf17 Jul 2026
Form 5 (FY 2019-2020)File: Form 5 FY 2019-20.pdf15 Jun 2026
Form 5 (FY 2020-2021)File: Form 5 FY 2020-21.pdf15 Jun 2026
Form 5 (FY 2025-2026)File: FORM 5 FY 2025-26.pdf15 Jun 2026
Form 1File: Form 01 Q1 ( 2020-21).pdf8 Jun 2026
Form 2File: Form 02 Q1 ( 2020-21).pdf8 Jun 2026
Form 3File: Form3 Q1 2020-21.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Form 01 Q1 ( 2020-21).pdf8 Jun 2026
Form 1File: Form 01 Q3 ( 2020-21).pdf8 Jun 2026
Form 2File: Form 02 Q3 ( 2020-21).pdf8 Jun 2026
Form 3File: Form3 Q3 2020-21.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Form 01 Q3 ( 2020-21).pdf8 Jun 2026
Form 1File: Form 01 Q4 ( 2020-21).pdf8 Jun 2026
Form 2File: Form 02 Q4 ( 2020-21).pdf8 Jun 2026
Form 3File: Form3 Q4 2020-21.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Form 01 Q4 ( 2020-21).pdf8 Jun 2026
Form 1File: Form 01 Q3 ( 2019-20).pdf8 Jun 2026
Form 2File: Form 02 Q3 ( 19-20).pdf8 Jun 2026
Form 3File: Form3 Q1 2019-20.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Form 01 Q3 ( 2019-20).pdf8 Jun 2026
Form 1File: Form 01 Q2 ( 2019-20).pdf8 Jun 2026
Form 2File: Form 02 Q2 ( 2019-20).pdf8 Jun 2026
Form 3File: Form3 Q1 2019-20.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Form 01 Q2 ( 2019-20).pdf8 Jun 2026
Form 1File: Form 01 Q1 ( 2020-21).pdf8 Jun 2026
Form 3File: Form3 Q1 2020-21.pdf8 Jun 2026
Form 2File: Form 02 Q2 ( 2020-21).pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Form 02 Q2 ( 2020-21).pdf8 Jun 2026
Form 1File: Form 01 Q3 ( 2020-21).pdf8 Jun 2026
Form 2File: Form 02 Q3 ( 2020-21).pdf8 Jun 2026
Form 3File: Form3 Q3 2020-21.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Form 01 Q3 ( 2020-21).pdf8 Jun 2026
Form 1File: Form 1- Architects Certificate.pdf4 Jun 2026
Form 2File: Form 2- Engineers Certificate.pdf4 Jun 2026
Form 3File: Form 3 CA Certificate.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: Booked Inventory.pdf4 Jun 2026
Form 1File: Form 1 Architects Certificate.pdf4 Jun 2026
Form 2File: Form 2 Engineers certificate.pdf4 Jun 2026
Form 3File: Form-3 CA certificate.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: Booked Inventory.pdf4 Jun 2026
Form 1File: Form 1 Architect Certificate.pdf4 Jun 2026
Form 2File: Form 2 engineers certificate.pdf4 Jun 2026
Form 3File: Form 3 CA Certificate.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory.pdf4 Jun 2026
Form 1File: FORM 1 - ARCHITECT CERTIFICATE.pdf4 Jun 2026
Form 2File: FORM 2 - ENGINEERERS CERTIFICATE.pdf4 Jun 2026
Form 3File: FORM 3 - CA CERTIFICATE.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: FORM 2A - Quality Assurance Ceriticate.pdf4 Jun 2026
Form 1File: FORM 1 Architect Certificate.pdf4 Jun 2026
Form 2File: FORM 2 Engineers Certificate.pdf4 Jun 2026
Form 3File: FORM 3 CA Certificate.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold_Booked_Inventory_Q3.pdf4 Jun 2026
Form 1File: FORM 1 Architect Certificate.pdf4 Jun 2026
Form 2File: FORM 2 Engineers Certificate.pdf4 Jun 2026
Form 3File: FORM 3 CA Certificate.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold_Booked_Inventory_Q2.pdf4 Jun 2026
Form 1File: FORM NO 1 Architect CERT.pdf4 Jun 2026
Form 2File: FORM NO 2 ENG CERT.pdf4 Jun 2026
Form 3File: FORM NO 3 CA CERT.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory Q1.pdf4 Jun 2026
Form 1File: FORM NO 1 - ARCHITECT CERTIFICATE.pdf4 Jun 2026
Form 2File: FORM NO 2 - ENGINEER CERTIFICATE.pdf4 Jun 2026
Form 3File: FORM NO 3 - CA CERTIFICATE.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory Q4.pdf4 Jun 2026
Form 1File: Form1 Architects Certificate.pdf4 Jun 2026
Form 2File: Form2 Engineers Certificate.pdf4 Jun 2026
Form 3File: Form3 CA Certificate.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTRY.pdf4 Jun 2026
Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf4 Jun 2026
Form 2File: FORM 2 ENGINEERS CERTIFICATE.pdf4 Jun 2026
Form 3File: FORM 3 CA CERTIFICATE.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD - UNSOLD INVENTORY.pdf4 Jun 2026
Form 1File: ARCHITECTS CERTIFICATE FORM 1 (1).pdf4 Jun 2026
Form 2File: ENGINEERS CERTIFICATE FORM 2.pdf4 Jun 2026
Form 3File: CA CERTIFICATE.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf4 Jun 2026
Form 1File: Architect Certificate Form 1.pdf4 Jun 2026
Form 2File: Engineers Certificate Form 2.pdf4 Jun 2026

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SPLENDOUR PARKWAGHOLI40CompletedFeb 2016Feb 2016
SPLENDOUR COUNTY WAGHOLI F WINGWAGHOLI78CompletedFeb 2016Feb 2016
SPLENDOUR COUNTY E WINGWAGHOLI59CompletedFeb 2016Feb 2016

How this compares with Pune

92%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SPLENDOUR COUNTY WAGHOLI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BEHIND WAGHESHWAR MANDIR13,700+ in Pune

2 kmSPLENDOUR COUNTY WAGHOLICompleted 61Lapsed / revoked 20Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 120 registered projects within 2 km.

Builder: PS DEVELOPERS

PS DEVELOPERS has 1 registration on MahaRERA, including SPLENDOUR COUNTY WAGHOLI. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SPLENDOUR COUNTY WAGHOLI shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SPLENDOUR COUNTY WAGHOLI is delayed beyond 15 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SPLENDOUR COUNTY WAGHOLI?

The registered promoter entity is PS DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAHFP6567G1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SPLENDOUR COUNTY WAGHOLI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SPLENDOUR COUNTY WAGHOLI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SPLENDOUR COUNTY WAGHOLI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SPLENDOUR COUNTY WAGHOLI?

The professionals named in the filing: Architect: VIKAS ACHALKAR; Engineer: BICS THROUGH PROPRIETOR PRASAD C KHANDEKAR; Chartered Accountant: GAJENDRA S JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SPLENDOUR COUNTY WAGHOLI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SPLENDOUR COUNTY WAGHOLI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SPLENDOUR COUNTY WAGHOLI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.