Red flags
- Registration lapsed
- Possession 4 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SPARKLE Phase II is a Residential / Group Housing project by SKYRISE VENTURES LLP in Near Gokul Nagar, 411015, registered with MahaRERA as P52100055140 on 4 Mar 2024. Possession was promised by 30 Jun 2026 and is now 4 months past that date.
At a glance
Project
- NameSPARKLE Phase II
- TypeResidential / Group Housing
- Location
- D P Road
- Near Gokul Nagar
- 411015
- Pincode411015
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100055140
- ReraGenie IDRG-MH-58476
Builder
- NameSKYRISE VENTURES LLP
- Entity typePartnership
- PartnersMUKESH TILAKCHAND AGARWAL, AMIT RAJENDRA GOYAL, ARUN SHAM AGARWAL, VIHAAN LANDMARKS LLP through its authorized representative KAPIL SHAMLAL GOYAL
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Mar 2024
- Promised completion30 Jun 2026
- Revised completionNone
- Buildings1 building record
- Documents filed45 files
Current status
Figures as on 13 Dec 2024, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SPARKLE B WING | NA | 14 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 13 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 0%.
SPARKLE B WING: 45% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities30
As on 13 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| Automatic Gearless Lift | Yes | 0% |
| CCTV Common Area | Yes | 0% |
| Children Play area | Yes | 0% |
| Club House | Yes | 0% |
| Gym | Yes | 0% |
| Indoor Games | Yes | 0% |
| Jogging and Walking Track | Yes | 0% |
| Led Light for Common Area | Yes | 0% |
| Library | Yes | 0% |
| Multipurpose Court | Yes | 0% |
| Power Backup for Common area and Lift | Yes | 0% |
| Senior Citizen Seat out | Yes | 0% |
| Smart Security System | Yes | 0% |
| Society Office | Yes | 0% |
| Yoga Area | Yes | 0% |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SPARKLE B WING | NA | Rs 32.00 cr | Rs 5.15 cr |
| - | NA | Rs 4.50 cr | Rs 1.78 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Cubix Architect Associates |
| Engineer | Sunil Abhang Sunil Abhang |
| Chartered Accountant | Sumit R Chandwani |
| Chartered Accountant | Yogesh Gupta |
| Partner | Role in project |
|---|---|
| SKYRISE VENTURES LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Feb 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Feb 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Feb 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed45
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Skyrise Ventures LLP Form 5 FY 23-24 Phase II-2.pdf | 13 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Skyrise Ventures LLP Form 5 FY 23-24 Phase II-2.pdf | 13 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q3 Phase 2.pdf | 11 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q3 Phase 2.pdf | 11 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q3 Phase 2.pdf | 2 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q3 Phase 2_compressed.pdf | 2 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q3 Phase 2.pdf | 2 Dec 2024 |
| Layout approvalFile: 2 Copy of Layout Approval (in case of layout) (13).pdf | 29 Feb 2024 |
| Copy of Layout Approval (in case of layout)File: 2 Copy of Layout Approval (in case of layout) (13).pdf | 29 Feb 2024 |
| Other - LegalFile: Sale Deed Dhanori Sparkle_compressed.pdf | 22 Feb 2024 |
| Copy of the legal title reportFile: sPARKLELEGAL REPORT MAHARREREA.pdf | 21 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sparkle Phase 2.pdf | 21 Feb 2024 |
| Other - TechnicalFile: Order 50 Sparkle (1).pdf | 16 Feb 2024 |
| Layout approvalFile: 1 RPlan Sparkle layout (1).pdf | 15 Feb 2024 |
| Building plan approvalFile: 2 Rplan Sparkle Parking Layout.pdf | 15 Feb 2024 |
| Copy of Layout Approval (in case of layout)File: 1 RPlan Sparkle layout (1).pdf | 15 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2 Rplan Sparkle Parking Layout.pdf | 15 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: interest Din.pdf | 5 Feb 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank details sparkl.pdf | 5 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: encumbrance .pdf | 2 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: En legal Sparkle B.pdf | 2 Feb 2024 |
| Details of encumbrances concerned to LegalFile: encumbrance .pdf | 2 Feb 2024 |
| Details of encumbrances concerned to LegalFile: En legal Sparkle B.pdf | 2 Feb 2024 |
| Proforma of Agreement for saleFile: RERA AGREEMENT PDF SPARKLE.pdf | 2 Feb 2024 |
| Deviation Report with respect to Allotment letterFile: deviation Allotment L.pdf | 2 Feb 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Agreement .pdf | 2 Feb 2024 |
| Building plan approvalFile: 4 Rplan Sparkle Wing A Flats.pdf | 31 Jan 2024 |
| Building plan approvalFile: 5 Rplan Sparkle Wing A building design.pdf | 31 Jan 2024 |
| Building plan approvalFile: 6 Rplan Sparkle Wing B Flats.pdf | 31 Jan 2024 |
| Building plan approvalFile: 7 Rpaln Sparkle Wing B building design.pdf | 31 Jan 2024 |
| Layout approvalFile: 3 R Plan Sparkle Wing A shops.pdf | 31 Jan 2024 |
| Copy of Layout Approval (in case of layout)File: 3 R Plan Sparkle Wing A shops.pdf | 31 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4 Rplan Sparkle Wing A Flats.pdf | 31 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 5 Rplan Sparkle Wing A building design.pdf | 31 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 6 Rplan Sparkle Wing B Flats.pdf | 31 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 7 Rpaln Sparkle Wing B building design.pdf | 31 Jan 2024 |
| Declaration in FORM BFile: Form B Sparkle B.pdf | 27 Jan 2024 |
| Declaration about Commencement CertificateFile: Cc Dcl sparkle .pdf | 17 Jan 2024 |
| CERSAI detailsFile: Cersai D B.pdf | 15 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC2523 23 Sparkle B.pdf | 13 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sparkle B.pdf | 13 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sparkle B.pdf | 13 Jan 2024 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER as per rera PDF.pdf | 13 Jan 2024 |
| PAN CardFile: PAN.pdf | 11 Jan 2024 |
| CERSAI detailsFile: CERSAI report 2024 SVLLP.pdf | 11 Jan 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| CASTLE ROYAO | Sr. No. 286 hissa 2 Lohegaon | 80 | Completed | Dec 2019 | Dec 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 45 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SPARKLE Phase II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Gokul Nagar
Filed coordinates, straight-line distance. 75 registered projects within 2 km.
Kohinoor Viva Pixel- Phase II
RISING ASSOCIATES
VIVACITY
REALCON LANDMARKS LLP
TRIAA VASANTAM CITY CENTER PHASE 1
Triaa Realtors LLP
QUE 101 PHASE I
ANNR Unique Realty LLP
NYATI ERA I
NYATI CONSTRUCTION PRIVATE LIMITED
ONE ARETHA PHASE 1
Triaa Landmarks LLP
Builder: SKYRISE VENTURES LLP
SKYRISE VENTURES LLP has 2 registrations on MahaRERA, including SPARKLE and SPARKLE Phase II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What does it mean that SPARKLE Phase II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SPARKLE Phase II is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SPARKLE Phase II?
The registered promoter entity is SKYRISE VENTURES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SPARKLE Phase II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SPARKLE Phase II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SPARKLE Phase II?
The professionals named in the filing: Architect: Cubix Architect Associates; Engineer: Sunil Abhang Sunil Abhang; Chartered Accountant: Sumit R Chandwani; Chartered Accountant: Yogesh Gupta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SPARKLE Phase II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback