Home / Browse projects / Pune, Maharashtra / SOORDAS
SOORDAS
RG-MH-13064 · RERA P52100023121 · Last updated on MahaRERA portal: 16 Jan 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 45 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SOORDAS is a Residential / Group Housing project by HARIVIJAY INFRACON in Pune, Maharashtra, registered with MahaRERA as P52100023121 on 2 Dec 2019. Possession was promised by 11 Jan 2023 and is now 45 months past that date.
At a glance
Project
- NameSOORDAS
- TypeResidential / Group Housing
- Location
- T.M.V COLONY ROAD
- MUKUND NAGAR
- Gultekadi
- Haveli
- Pune
- 411037
- Pincode411037
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100023121
- ReraGenie IDRG-MH-13064
Builder
- NameHARIVIJAY INFRACON
- Entity typePartnership
- GSTIN27AAIFH4164Q1ZR
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnerAMOL HARIVIJAY JOSHI
- Other registrations4 more →
- Completed2 of 5
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 Dec 2019
- Promised completion11 Jan 2023
- Revised completionNone
- Buildings1 building record
- Documents filed22 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SOORDAS | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
SOORDAS: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed16
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SOORDAS C.H.S. LTD | Gultekadi | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rajas Joshi |
| Engineer | Amol Bapat |
| Chartered Accountant | Unmesh Patwardhan |
| Chartered Accountant | Sandeep Bhadale |
| Partner | Role in project |
|---|---|
| HARIVIJAY INFRACON | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Oct 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Oct 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Oct 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 16 Jan 2024
Documents filed22
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4-Soordas.pdf | 16 Jan 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: SoordasConveyance.pdf | 19 May 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Arch Certificate_Soordas.pdf | 24 Jan 2023 |
| Status of ConveyanceFile: Soordas Conveyance deed Index II.pdf | 20 Jan 2023 |
| Foreclosure of the ProjectFile: Soordas complition certificate .PDF | 20 Jan 2023 |
| Other - TechnicalFile: Form 4 Arch Certificate_Soordas.pdf | 20 Jan 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Soordas complition certificate .PDF | 23 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 26 Nov 2019 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 26 Nov 2019 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf | 26 Nov 2019 |
| PAN CardFile: Harivijay Infracon PAN.pdf | 25 Nov 2019 |
| Proforma of Allotment letterFile: Agreement To Sell - Draft.pdf | 25 Nov 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3-signed.pdf | 7 Nov 2019 |
| Proforma of Allotment letterFile: Proforma of allotment letter.pdf | 9 Oct 2019 |
| Layout approvalFile: Plan_compressed (1).pdf | 4 Oct 2019 |
| Building plan approvalFile: Plan_compressed (1).pdf | 4 Oct 2019 |
| Copy of Layout Approval (in case of layout)File: Plan_compressed (1).pdf | 4 Oct 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan_compressed (1).pdf | 4 Oct 2019 |
| Copy of the legal title reportFile: Soordas Title Search report_compressed.pdf | 3 Oct 2019 |
| Details of encumbrancesFile: Soordas Title Search report_compressed.pdf | 3 Oct 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_compressed.pdf | 3 Oct 2019 |
| Declaration in FORM BFile: Declaration Form B.pdf | 3 Oct 2019 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| KalpanaP52100052449 | Mitramandal Co Operative Housing Society Parvati, Pune | - | Sep 2023 | Completed | Jun 2025 | May 2025 |
| Yashodhan | Plot No 16 Adwait Co-op Society Off Paud Road Erandawane Pune 411004 | 4 | - | Completed | Sep 2019 | May 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 22 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SOORDAS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MUKUND NAGAR13,700+ in Pune
MAHA TRADE MARKET PH- 2
JAIRAJ REALTY LLP
MAHA TRADE MARKET PH- 1
JAIRAJ REALTY LLP
SOLITAIRE BUSINESS HUB PHASE I, SOLITAIRE WORL
Classic Promoters and Builders Private Lim
SOLITAIRE BUSINESS HUB PHASE II, SOLITAIRE WOR
Classic Promoters and Builders Private Lim
World One Solitaire World
Classic Promoters and Builders Private Lim
HILL TOWN A B AND C WING
HILL TOWN CONSTRUCTIONS
Builder: HARIVIJAY INFRACON
HARIVIJAY INFRACON has 5 registrations on MahaRERA, including SOORDAS and AMBAR VIHAR. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that SOORDAS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SOORDAS is delayed beyond 11 Jan 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SOORDAS?
The registered promoter entity is HARIVIJAY INFRACON, a partnership as per the filing. Its GSTIN 27AAIFH4164Q1ZR can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SOORDAS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SOORDAS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SOORDAS?
The professionals named in the filing: Architect: Rajas Joshi; Engineer: Amol Bapat; Chartered Accountant: Unmesh Patwardhan; Chartered Accountant: Sandeep Bhadale. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SOORDAS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback