Home / Browse projects / Thane, Maharashtra / SITA HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

SITA HEIGHTS

By NAMDEV SAKHARAM PATIL

RG-MH-56211 · RERA P51700016332 · Last updated on MahaRERA portal: 2 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 45 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
12 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 95%
0Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

SITA HEIGHTS is a Residential / Group Housing project by NAMDEV SAKHARAM PATIL in Thane, Maharashtra, registered with MahaRERA as P51700016332 on 3 May 2018. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 45 months from the original filing.

At a glance

Project

  • NameSITA HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • MAHARASHTRA
    • AT VILLAGE KATAI
    • Katai
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700016332
  • ReraGenie IDRG-MH-56211

Builder

  • NameNAMDEV SAKHARAM PATIL
  • Entity typeIndividual

Key dates

10 months past promisethis monthRegisteredMay 2018First promiseMar 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 May 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Mar 2022)
  • Buildings2 building records
  • Documents filed86 files

Current status

69.5%Work done, per cost certificate

Figures as on 2 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA80000
WING BNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 2 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 95%.

WING A87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes80%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes70%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes75%
Energy managemcntYes75%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes70%
Open ParkingYes70%

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Closed/Covered29
Open Space31
BuildingClosed/CoveredOpen SpaceTotal
WING A201838
WING B91322

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,490 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 May 2025

Approvals and building plan

Sanctioning authorityMumbai Metropolitan Region Development Authority
Permissible FSI2569.69
Proposed, not sanctioned2,570 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCOMMERCE PLAZA TONDON ROAD DOMBIVLI EAST
Estimated costRs 11.87 cr
Cost incurredRs 8.25 cr
Work done69.48%
BuildingWingEstimatedIncurred
WING ANARs 5.81 crRs 4.12 cr
-NARs 5.81 crRs 4.12 cr
WING BNARs 25.00 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectG N GANDHE
EngineerRAJESH THAKARE & ASSOCIATES
Chartered AccountantLALIT SHARMA & ASSOCIATES
Chartered AccountantJKS & CO
Chartered AccountantJKS
PartnerRole in project
NAMDEV SAKHARAM PATIL-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018972Mar 2022 → Dec 2025

Reason as filed by the promoterAFTER THE ONSET OF COVID 19 THE DEVELOPER FACED FINANCIAL CRISIS AND BOOKINGS WERE ALSO NON EXISTENT, DUE TO SHORTAGE OF FUNDS , TEH DEVELOPER COULD NOT COMMENCE THE WORK. NOW, THE WORK HAS SLOWLY STARTED AND WE ARE IN POSITION TO COMPLETE IT. HENCE, WE SEEK A FUTHER EXTENSION TILL 31.12.2025 TO FINISH THE DEVELOPMENT WORK WHILE ADHERING TO GOVT. GUIDELEINES

EXT51700011982Mar 2022 → Mar 2023

Reason as filed by the promoterAs we are aware the entire nation was passing through a Pandemic being COVID-19. The Pandemic is still continuing. Covid-19 infections were took pickup in the month of Feb-21 To till date and lockdown were imposed from April, 2021 to till date in our region, however difficulties faced due to Pandemic we could not complete development work in time. Hence we seek further extension till 30th March, 2023 to complete development work by following government guidelines.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: arch certi.pdf2 Jul 2025
Withdrawal Update Form 2File: Thakare Form.pdf2 Jul 2025
Withdrawal Update Form 3File: Form-3 31st December 2024 (1).pdf2 Jul 2025
Form 2A (FY 2018-2019)File: Form 2A 2019.pdf2 Jul 2025
Form 2A (FY 2019-2020)File: Form 2A 2020.pdf2 Jul 2025
Form 2A (FY 2020-2021)File: Form 2A 2021.pdf2 Jul 2025
Form 2A (FY 2021-2022)File: Form 2A 2022.pdf2 Jul 2025
Form 2A (FY 2022-2023)File: Form 2A 2023.pdf2 Jul 2025
Form 2A (FY 2025-2026)File: Form 2A 2026.pdf2 Jul 2025
Form 5 (FY 2018-2019)File: FORM 5_2018-19.pdf2 Jul 2025
Form 5 (FY 2019-2020)File: FORM 5_2019-20.pdf2 Jul 2025
Form 5 (FY 2020-2021)File: FORM 5_2019-20.pdf2 Jul 2025
Form 5 (FY 2021-2022)File: FORM 5_2021-22.pdf2 Jul 2025
Form 5 (FY 2022-2023)File: FORM 5_2022-23.pdf2 Jul 2025
Form 5 (FY 2023-2024)File: FORM 5_2023-24.pdf2 Jul 2025
Form 5 (FY 2024-2025)File: FORM 5_2024-25.pdf2 Jul 2025
Form 2A (FY 2024-2025)File: New Doc 06-26-2025 10.55 (1).pdf29 Jun 2025
Form 2A (FY 2023-2024)File: New Doc 06-26-2025 10.56 (1).pdf29 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1.pdf24 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2.pdf24 May 2024
Disclosure of sold/ booked inventoryFile: Details of Inventory Sold.pdf24 May 2024
Certificates of CA (Form 3)File: Form 3 CA Certificate 15-05-2024.pdf24 May 2024
Building plan approvalFile: BLUE PRINT.pdf15 May 2024
Details of encumbrances concerned to FinanceFile: SEARCH TITLE REPORT.pdf15 May 2024
Details of encumbrances concerned to LegalFile: SEARCH TITLE REPORT.pdf15 May 2024
Building Plan Approval (IOD)File: BLUE PRINT.pdf15 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Revised MMRDA CC Granted 06-01-2022.pdf15 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2021.pdf15 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2022.pdf15 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2023.pdf15 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2024.pdf15 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_01-07-2021.pdf15 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_01-07-2022.pdf15 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_01-07-2023.pdf15 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_01-01-2022.pdf15 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_01-01-2023.pdf15 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_01-01-2024.pdf15 May 2024
Disclosure of sold/ booked inventoryFile: Shivani Format B.pdf15 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Form E shivani construction PART A.pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5_2018-19.pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5_2021-22.pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5_2022-23.pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_2023-24.pdf15 May 2024
Proforma of Agreement for saleFile: GetUserDocumentFileContent (5).pdf15 May 2024
Proforma of Agreement for saleFile: SITA HEIGHTS - FLAT NO A 701- GAYASILAL LALANJU PAL-SMITA.pdf15 May 2024
Proforma of Allotment letterFile: SITA HEIGHTS - FLAT NO A 701- GAYASILAL LALANJU PAL-SMITA.pdf15 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: GetUserDocumentFileContent (6).pdf15 May 2024
Deviation Report with respect to Allotment letterFile: GetUserDocumentFileContent (5).pdf15 May 2024
Deviation Report with respect to Allotment letterFile: SITA HEIGHTS - FLAT NO A 701- GAYASILAL LALANJU PAL-SMITA.pdf15 May 2024
Deviation Report with respect to model copy of AgreementFile: SITA HEIGHTS - FLAT NO A 701- GAYASILAL LALANJU PAL-SMITA.pdf15 May 2024
Other - LegalFile: SEARCH TITLE REPORT.pdf15 May 2024
Other - TechnicalFile: COPY OF LAYOUT.pdf15 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2_11zon.pdf25 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM2A 30-06-19_3_11zon.pdf25 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM2A 30-09-19_7_11zon.pdf25 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM2A 31-12-19_16_11zon.pdf25 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM2A 31-03-20_12_11zon.pdf25 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM2A 30-06-20_4_11zon.pdf25 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM2A 30-09-20_8_11zon.pdf25 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM2A 31-12-20_17_11zon.pdf25 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM2A 31-03-21_13_11zon.pdf25 Jun 2022
Layout approvalFile: LATEST APPROVED PLAN.pdf6 Jun 2022
Building plan approvalFile: SITA HEIGHTS REVISED PLAN APPROVAL.pdf6 Jun 2022
Copy of Layout Approval (in case of layout)File: LATEST APPROVED PLAN.pdf6 Jun 2022
Building Plan Approval (IOD)File: SITA HEIGHTS REVISED PLAN APPROVAL.pdf6 Jun 2022
Declaration about Commencement CertificateFile: Commencement Certificate.pdf6 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate.pdf6 Jun 2022
CERSAI detailsFile: Cersai Undertaking.pdf6 Jun 2022
Disclosure of sold/ booked inventoryFile: Booking.pdf6 Jun 2022
Certificates of CA (Form 3)File: FORM-3.pdf6 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5-18-19.pdf6 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 2019-20.pdf6 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5-20-21.pdf6 Jun 2022
Layout approvalFile: LAYOUT PLAN.pdf26 Apr 2018
Building plan approvalFile: COMMENCEMENT CERTIFICATE-compressed.pdf26 Apr 2018
PAN CardFile: Namdev Patil_PAN.pdf26 Apr 2018
Copy of the legal title reportFile: TITLE CERTIFICATE-compressed.pdf26 Apr 2018
Details of encumbrancesFile: SELF DECLARATION-ENCRUMBACE.pdf26 Apr 2018
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf26 Apr 2018
Building Plan Approval (IOD)File: COMMENCEMENT CERTIFICATE-compressed.pdf26 Apr 2018

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 45 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SITA HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AT VILLAGE KATAI7,600+ in Thane

2 kmSITA HEIGHTSCompleted 20Lapsed / revoked 6Other 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 55 registered projects within 2 km.

Builder: NAMDEV SAKHARAM PATIL

NAMDEV SAKHARAM PATIL has 1 registration on MahaRERA, including SITA HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that SITA HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SITA HEIGHTS is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SITA HEIGHTS?

The registered promoter entity is NAMDEV SAKHARAM PATIL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SITA HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SITA HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SITA HEIGHTS?

The professionals named in the filing: Architect: G N GANDHE; Engineer: RAJESH THAKARE & ASSOCIATES; Chartered Accountant: LALIT SHARMA & ASSOCIATES; Chartered Accountant: JKS & CO; Chartered Accountant: JKS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SITA HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SITA HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SITA HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.