Home / Browse projects / SINNARWALA BUSINESS PARK
SINNARWALA BUSINESS PARK
RG-MH-15559 · RERA P51600046908 · Last updated on MahaRERA portal: 30 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 31 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SINNARWALA BUSINESS PARK is a Commercial project by SHAKTI CONSTRUCTION in SINNAR, 422103, registered with MahaRERA as P51600046908 on 19 Sep 2022. Possession was promised by 31 Mar 2024 and is now 31 months past that date.
At a glance
Project
- NameSINNARWALA BUSINESS PARK
- TypeCommercial
- Location
- PLOT NO.1
- S NO.1067 B+C
- SINNAR
- 422103
- Pincode422103
- RERA no.P51600046908
- ReraGenie IDRG-MH-15559
Builder
- NameSHAKTI CONSTRUCTION
- Entity typePartnership
- PartnersMEHMOOD IBRAHIM DARUWALE, TARAMATI SANJAY GADE, TRIMBAK BHIKAJI KHALKAR
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Sep 2022
- Promised completion31 Mar 2024
- Revised completionNone
- Buildings1 building record
- Documents filed55 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SINNARWALA BUSINESS PARK | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.
SINNARWALA BUSINESS PARK: 46% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership5
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MALEKA MUSTAFA KAPADIA | Mumbai City | Mumbai City |
| TRAMBAK BHIKAJI KHALKAR | Nashik | Nashik |
| FAKHERA KHOZEMA GITTYAM ( FAKIRA SAFAKAR BOHRI) | Mumbai City | Mumbai City |
| MEHMOOD IBRAHIM DARUWALE | - | Nashik |
| ARIF SHAFKATHUSEN SINNARWALA (ARIF S. BOHRI) | - | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRAKASH PAWAR & ASSOCIATES |
| Engineer | PRAKASH PAWAR & ASSOCIATES |
| Chartered Accountant | ABHISHEK MUKUND KSHATRIYA |
| Partner | Role in project |
|---|---|
| SHAKTI CONSTRUCTION | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Aug 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed55
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: REVISED FORM B.pdf | 30 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architech certificate JUNE 2024.pdf | 30 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architech certificate SEP 2024.pdf | 30 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 signed.pdf | 30 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 signed.pdf | 30 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate JUNE 2024.pdf | 30 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate SEP 2024.pdf | 30 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD INVENTORY DISCLOSURE.pdf | 30 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf | 30 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 30 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf | 30 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 7 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 7 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 COMPRESSED.pdf | 7 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 compressed.pdf | 7 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED compressed.pdf | 7 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 compressed SIGNED.pdf | 7 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf | 21 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 21 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate.pdf | 21 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER.pdf | 21 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED compressed.pdf | 21 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 signed compressed.pdf | 21 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5_20231121_0001.pdf | 21 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf | 16 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate FORM1.pdf | 16 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 16 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf | 16 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA SIGNED.pdf | 16 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer's certificate.pdf | 20 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A engineer certificate.pdf | 20 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: quality assurance certificate.pdf | 20 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED_compressed.pdf | 20 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 architech certificate.pdf | 26 Dec 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 engineer certificate.pdf | 26 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA SIGNED_compressed.pdf | 26 Dec 2022 |
| Proforma of Agreement for saleFile: proforma agreement for sale.pdf | 26 Dec 2022 |
| Copy of the legal title reportFile: LEGAL TITLE REPORT_compressed.pdf | 19 Aug 2022 |
| Details of encumbrances concerned to LegalFile: LEGAL AND LITIGATION ENCUMBRANCES.pdf | 19 Aug 2022 |
| Proforma of Allotment letterFile: PROFORMA AGREEMENT FOR SALE.pdf | 19 Aug 2022 |
| Proforma of Allotment letterFile: PROFORMA ALLOTMENT LETTER.pdf | 19 Aug 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: separate bank details.pdf | 19 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: DEVIATION REPORT LETTER OF ALLOTMENT.pdf | 19 Aug 2022 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT PROFORMA AGREEMENT FOR SALE.pdf | 19 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3 shakti_11zon.pdf | 9 Jul 2022 |
| Layout approvalFile: Layout .pdf | 3 May 2022 |
| Building plan approvalFile: building plan 1_merged_11zon.pdf | 3 May 2022 |
| PAN CardFile: Pan No of Entity shakti.pdf | 3 May 2022 |
| Details of encumbrancesFile: Self Declaration shakti.pdf | 3 May 2022 |
| Copy of Layout Approval (in case of layout)File: Layout .pdf | 3 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: building plan 1_merged_11zon.pdf | 3 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate shakti_compressed.pdf | 3 May 2022 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate shakti.pdf | 3 May 2022 |
| Declaration in FORM BFile: Details of Encumbrance Form B shakti_compressed.pdf | 3 May 2022 |
| CERSAI detailsFile: CERSAI REPORT.pdf | 3 May 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 55 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SINNARWALA BUSINESS PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SINNAR
SAI ANAND PRIDE-B
DEEPAK KALYANJI CHANDE
VEDANT AANANDVAN
GORAKSHNATH DASHRATH MHASKE
AVADHOOT HIGH CITY PHASE 1
Avadhoot Developers
Ramtek Ayodhya
Shinde Construction
SHREE SHANKAR ENCLAVE
Akash Anilkumar Bumb
SHREE GANESH EMPIRE
SHREE GANESH CONSTRUCTION
Builder: SHAKTI CONSTRUCTION
SHAKTI CONSTRUCTION has 1 registration on MahaRERA, including SINNARWALA BUSINESS PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that SINNARWALA BUSINESS PARK shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SINNARWALA BUSINESS PARK is delayed beyond 31 Mar 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SINNARWALA BUSINESS PARK?
The registered promoter entity is SHAKTI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SINNARWALA BUSINESS PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SINNARWALA BUSINESS PARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SINNARWALA BUSINESS PARK?
The professionals named in the filing: Architect: PRAKASH PAWAR & ASSOCIATES; Engineer: PRAKASH PAWAR & ASSOCIATES; Chartered Accountant: ABHISHEK MUKUND KSHATRIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SINNARWALA BUSINESS PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback