Home / Browse projects / Pune, Maharashtra / SILVER TOUCH
SILVER TOUCH
RG-MH-04613 · RERA P52100020228 · Last updated on MahaRERA portal: 27 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 63 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SILVER TOUCH is a Residential / Group Housing project by Silver Touch Developers in Pune, Maharashtra, registered with MahaRERA as P52100020228 on 29 Mar 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 63 months from the original filing. 80 of the 110 units on this registration are recorded sold or booked, and 1 of 22 construction stages are filed complete.
At a glance
Project
- NameSILVER TOUCH
- TypeResidential / Group Housing
- Location
- Chikhali kudalwadi
- Chikhali
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 411062
- Pincode411062
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100020228
- ReraGenie IDRG-MH-04613
Builder
- NameSilver Touch Developers
- Entity typePartnership
- GSTIN27ADMFS5084K1ZD
- PartnersVishwanath Vasant Jare, Sachin Vasant Jare, KETKI VISHAL KOTHARI
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Mar 2019
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 1 Sep 2021)
- Buildings2 building records
- Documents filed94 files
Current status
Figures as on 27 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 8 | 0 | 98 | 0 | 98 |
| B Wing | NA | 8 | 0 | 12 | 0 | 12 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 27 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.
A Wing9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed17
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A Wing | 1 | 10 | 11 |
| B Wing | 1 | 5 | 6 |
Land and ownership10
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Abdul Latif Rafikulla Khan | Pimpri Chinchawad (M Corp.) | Pune |
| Jaywant Bhikaji Balghare | Pimpri Chinchawad (M Corp.) | Pune |
| Kundan Sampat Balghare | Pimpri Chinchawad (M Corp.) | Pune |
| Mahesh Sampat Balghare | Pimpri Chinchawad (M Corp.) | Pune |
| Manisha Sampat Balghare | Pimpri Chinchawad (M Corp.) | Pune |
| Muktabai Bhikaji Balghare | Pimpri Chinchawad (M Corp.) | Pune |
| Pratik Sampat Balghare | Pimpri Chinchawad (M Corp.) | Pune |
| Kundlik Raghoba Parande | - | Pune |
| Sandeep Prakash More | Pimpri Chinchawad (M Corp.) | Pune |
| SANDEEEP PRAKASH MORE | Chikhali | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AMOL KHANDAGALE |
| Engineer | JAY GANESH ASSOCIATES |
| Chartered Accountant | NPSR & Associates - CA. Vivek Lahoti |
| Chartered Accountant | Prashantsing Mohansing Pardeshi |
| Chartered Accountant | KAUSTUBH P GORE |
| Partner | Role in project |
|---|---|
| Silver Touch Developers | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the corona pandemic situation and non availability of constriction workers we need some additional time for completion of work
Reason as filed by the promoterThe construction activity not completed within due date due to shortage of labour / Worker.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Feb 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Feb 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Feb 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed94
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Silvar Touch From -1 SIGN.pdf | 27 Apr 2026 |
| Form 2File: silvr touch from 2 march 2026_0001 (1).pdf | 27 Apr 2026 |
| Form 3File: Form3- Silvertouch (1).pdf | 27 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Silver Touch Sold Unsold Inventory march 2026_0001.pdf | 27 Apr 2026 |
| Form 2A (FY 2024-2025)File: FORM 2 A signed.pdf | 17 Feb 2026 |
| Form 5 (FY 2023-2024)File: form 5 silver 23 24.pdf | 11 Feb 2026 |
| Form 5 (FY 2024-2025)File: silver touch form 5 24-25.pdf | 11 Feb 2026 |
| Form 3File: form 3-Silvertouch..pdf | 21 Jan 2026 |
| Form 1File: form1 sign.pdf | 21 Jan 2026 |
| Form 2File: form 2 sign.pdf | 21 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold and unsold.pdf | 21 Jan 2026 |
| Form 2File: Silver Touch Form 2 engg certificate Sept 2025_0001.pdf | 22 Nov 2025 |
| Form 3File: FROM 3.pdf | 22 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SIILVER TOUCH SOLD UNSOLD INVENTORY SEPT 2025_0001.pdf | 22 Nov 2025 |
| Form 1File: Silver Touch Dev Form 1 Arch Certifiicate Sept 2025...pdf | 22 Nov 2025 |
| Form 1File: silver touch form 1 FINAL.pdf | 14 Aug 2025 |
| Form 2File: Silver Touch Form 2 engg Certificate june 2025 FINAL.pdf | 14 Aug 2025 |
| Form 3File: SilverTouch Developers.pdf | 14 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold final.pdf | 14 Aug 2025 |
| Form 1File: FORM 1 q4 24-25.pdf | 29 May 2025 |
| Form 2File: FORM 2 q4 24-25.pdf | 29 May 2025 |
| Form 3File: form 3 q4 24-25.pdf | 29 May 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND UNSOLD.pdf | 29 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver Arch certificate July to Sept 2022 C.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver Arch certificate Octo To dece 2022 C.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver arch Certificate Jan To March 2023C.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver Arch certificate April To june 2023 C.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver Arch certificate July To Sept 2023_C.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver Arch certificate Octo to Decce 2023C.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver Arch certificate Jan To march 2024_C.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver Arch certificate April to june 2024C.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver Arch certificate July To Sept 2024_C.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver Arch certificate July To Sept 2024_C.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Silver Arch certificate April to June 2022C.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 7FORM 3 for oct to dec 23.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 11 FORM 3 for oct to dec 24.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 10FORM 3 for july to sep 24.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 9FORM 3 for apr to june 24.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 8FORM 3 for jan to march 24.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 5FORM 3 for apr to june 23.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 4FORM 3 for jan to march 23.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 3FORM 3 for oct to dec 22.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 2FORM 3 for july to sep 22.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 1FORM 3 for apr to june 22.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 6FORM 3 for july to sep 23.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver touch eng certifiicate jan to march 2023_compressed.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver touch engg certificate july to sept 2024_0001.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver touch eng certificate april to june 2024.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver touch engg certificate jan to march 2024.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver touch engg certificate octo tto dece 2023_compressed.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver touch engg certificate july to sept 2023_compressed.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver touch eng certificate april to june 2023_compressed.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver touch engg certifiicate octo to dece 2022_compressed.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver touch eng certificate july to sept 2022.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver touch engg certificate apriil to june 2022.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Silver touch engg certificate octo to dece 2024_0001.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Siilver touch engg assurance certificate 2023.pdf | 23 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Silver touch engg assurance certificate 2024.pdf | 23 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: silver touch audit report.pdf | 19 Mar 2024 |
| PAN CardFile: ACE Scanner_2024_02_27.pdf | 27 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: new book sold status_compressed.pdf | 20 Mar 2023 |
| Declaration about Commencement CertificateFile: FORM D.pdf | 9 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QULITY ASSURance_compressed.pdf | 9 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSER SOLD AND BOOKED_compressed.pdf | 9 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Rera Audit 2022.pdf | 24 Feb 2023 |
| Declaration about Commencement CertificateFile: silver touc commensment declaration.pdf | 2 Sep 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2A Qulity assurance 2020.pdf | 2 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A Qulity assurance 2020.pdf | 2 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A Qulity assurance 2021cc.pdf | 2 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: silver touch sales or booking_compressed (1).pdf | 2 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Rera Audit Fy 17-18.pdf | 2 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: silver 1819 Audit.pdf | 2 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: silver 1920 Audit.pdf | 2 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Rera Audit 20-21.pdf | 2 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Rera Audit FY 2020 21.pdf | 2 Sep 2021 |
| Certificates of CA (Form 3)File: Silver Touch Developers CA Certificate_compressed.pdf | 28 Mar 2019 |
| Details of encumbrancesFile: Encumbrances.pdf | 22 Mar 2019 |
| Declaration in FORM BFile: Form B - Silver Touch Developers_compressed.pdf | 22 Mar 2019 |
| Proforma of Allotment letterFile: Proforma Allotment Letter.pdf | 22 Mar 2019 |
| Proforma of Allotment letterFile: Draft Agreement.pdf | 22 Mar 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 94 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SILVER TOUCH on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chikhali13,700+ in Pune
Filed coordinates, straight-line distance. 225 registered projects within 2 km.
SHAKUNTAL COMMERCIA
SHAKUNTAL GROUP
Santiago Skyarc
Anjani Promoters
DWARKA BLUE WATER
SHAKUNTAL BUILDCON
24 SUNSHINE TOWERS
SHIV ASSOCIATES
Ganesh Paradise Phase I
EKDANTA NEST LLP
GANESH SIDDHI PHASE 3
S B PATIL SPACES AND INFRA PVT LTD
Builder: Silver Touch Developers
Silver Touch Developers has 1 registration on MahaRERA, including SILVER TOUCH. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SILVER TOUCH is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SILVER TOUCH?
The registered promoter entity is Silver Touch Developers, a partnership as per the filing. Its GSTIN 27ADMFS5084K1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SILVER TOUCH?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SILVER TOUCH?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SILVER TOUCH?
The professionals named in the filing: Architect: AMOL KHANDAGALE; Engineer: JAY GANESH ASSOCIATES; Chartered Accountant: NPSR & Associates - CA. Vivek Lahoti; Chartered Accountant: Prashantsing Mohansing Pardeshi; Chartered Accountant: KAUSTUBH P GORE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SILVER TOUCH?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.