SIGNATURE VILLAS

By SHRISH NIHALCHAND LODHA

RG-MH-44428 · RERA P52100045258 · Last updated on MahaRERA portal: 23 Jul 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 37 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 completed earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 37 months from the original
4 of 11Construction stages donefurthest along: Internal walls, 80%
3 of 8Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

SIGNATURE VILLAS is a Residential / Group Housing project by SHRISH NIHALCHAND LODHA in Pune, Maharashtra, registered with MahaRERA as P52100045258 on 10 May 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 37 months from the original filing. 5 of the 8 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameSIGNATURE VILLAS
  • TypeResidential / Group Housing
  • Location
    • SASANE NAGAR
    • HADAPSAR
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100045258
  • ReraGenie IDRG-MH-44428

Builder

  • NameSHRISH NIHALCHAND LODHA
  • Entity typeIndividual
  • Declared earlier projects2 →

Key dates

this monthRegisteredMay 2022First promiseFeb 2024Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 May 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 28 Feb 2024)
  • Buildings1 building record
  • Documents filed56 files

Current status

62%5 of 8 units booked
100.0%Work done, per cost certificate

Figures as on 23 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SIGNATURE VILLASNA31808

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

SIGNATURE VILLAS: 57% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership9

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area800 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 May 2026
LandownerVillageDistrict
PARSHURAM RAGHUNATH DANGMALI AND FAMILYHadapsarPune
SAHEBRAO DANGMALIHadapsarPune
SUNITA DANGMALIHadapsarPune
SAGAR DANGMALIHadapsarPune
POONAM KAMODHadapsarPune
REKHA DANGMALIHadapsarPune
PRATIK DANGMALIHadapsarPune
SUNNY DANGMALIHadapsarPune
DHANANJAY DANGMALIHadapsarPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI1988.5
Proposed, not sanctioned788 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMARKET YARD BRANCH PUNE
Estimated costRs 1.82 cr
Cost incurredRs 1.82 cr
Work done100.0%
BuildingWingEstimatedIncurred
SIGNATURE VILLASNARs 1.82 crRs 1.82 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCH. PARVEZ JAMADAR AND ASSOCIATES
ArchitectVaibhav Lohar
EngineerMr. Shreyansh Khabiya
EngineerVISHAL VINODKUMAR LODHA
Chartered AccountantCHHALLANI AGARWAL AND ASSOCIATES
Chartered AccountantR R BAFNA AND ASSOCIATES
Chartered AccountantSAC & CO LLP
Chartered AccountantPriyanka Chordiya
PartnerRole in project
SHIRISH NIHALCHAND LODHA-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019187Feb 2024 → Feb 2025

Reason as filed by the promoterDUE TO SHORTAGE OF LABOUR AND MEDICAL CONDITIONS OF THE PROMOTER THE APPLICATION FOR PROJECT EXTENSION IS BEING DONE.

EA27052621121Feb 2024 → Mar 2027

Reason as filed by the promoterThis is to inform that the project has substantially progressed and to complete the balance work and application to be made with the concerned authority for competition of project. The time required to obtaining the Completion Certificate is procedural and beyond the our control. Accordingly, an application for *extension of the project registration* is being filed to ensure compliance with the provisions of the Real Estate (Regulation and Development) Act, 2016.The promoter undertakes to complete all remaining formalities and obtain the Completion Certificate at the earliest. Hence, it is req

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12501307Nilesh Ravindra VadnalSHRISH NIHALCHAND LODHA20/04/2025
CC12501535Abhijit Mahadev JadhavSHRISH NIHALCHAND LODHA08/05/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate form 1.pdf23 Jul 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate.pdf23 Jul 2026
Withdrawal Update Form 3File: Form 3 Adarsh Associates 30 06 2026 Sign.pdf23 Jul 2026
Withdrawal Update Form 1File: Form 1 31032026 sign_compressed.pdf20 Jun 2026
Withdrawal Update Form 2File: FORM 2 31032026 sign.pdf20 Jun 2026
Withdrawal Update Form 3File: Form 3 Adarsh Associates 31032026 site Generated_compressed.pdf20 Jun 2026
Withdrawal Update Form 1File: Form 1 30062025 sign_compressed.pdf17 Jun 2026
Withdrawal Update Form 1File: Form 1 30092025 sign_compressed.pdf17 Jun 2026
Withdrawal Update Form 1File: Form 1 31122025 sign_compressed.pdf17 Jun 2026
Withdrawal Update Form 2File: FORM 2 30062025 sign.pdf17 Jun 2026
Withdrawal Update Form 2File: FORM 2 30092025 sign.pdf17 Jun 2026
Withdrawal Update Form 2File: Form 3 Adarsh Associates 31122025 sign_compressed.pdf17 Jun 2026
Withdrawal Update Form 3File: Form 3 Adarsh Associates 30062025 sign_compressed.pdf17 Jun 2026
Withdrawal Update Form 3File: Form 3 Adarsh Associates 30092025 sign_compressed.pdf17 Jun 2026
Withdrawal Update Form 3File: Form 3 Adarsh Associates 31122025 sign_compressed.pdf17 Jun 2026
Form 2A (FY 2025-2026)File: FORM 2A FY 2025 26.pdf17 Jun 2026
Form 5 (FY 2025-2026)File: Form 5 Adarsh Associates FY 2025 2026 sign.pdf17 Jun 2026
Form 2A (FY 2022-2023)File: Form 2A FY 2022 23.pdf9 Jun 2026
Form 2A (FY 2023-2024)File: FORM 2A FY 2023 24.pdf9 Jun 2026
Form 2A (FY 2024-2025)File: FORM 2A FY 2024 25.pdf9 Jun 2026
Form 5 (FY 2022-2023)File: Form 5 Adarsh Associates FY 2022 2023 sign.pdf6 Jun 2026
Form 5 (FY 2023-2024)File: Form 5 Adarsh Associates FY 2023 2024 sign.pdf6 Jun 2026
Form 5 (FY 2024-2025)File: Form 5 Adarsh Associates FY 2024 2025 sign_compressed.pdf6 Jun 2026
Form 1File: Form 1 31032025 sign_compressed.pdf27 May 2026
Form 2File: FORM 2 31032025 sign.pdf27 May 2026
Form 3File: Form 3 Adarsh Associates 31032025 sign_compressed.pdf27 May 2026
Disclosure of Sold and Booked InventoryFile: 5 Disclosure of Sold and Unsold 31032025 sign.pdf27 May 2026
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer certificate 2A.pdf11 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 2024.pdf11 Apr 2024
Declaration in FORM BFile: FORM B - PROMOTER EXTENDED.pdf20 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITEHT CERTIFICATE.pdf20 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 6 jan 2024.pdf20 Mar 2024
Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD INVENTORY.pdf27 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSER OF INTREST.pdf27 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION ABOUT BANK.pdf27 Feb 2024
Deviation Report with respect to Allotment letterFile: ALLOTMENT LETTER .pdf27 Feb 2024
Deviation Report with respect to Allotment letterFile: MODEL OF AGGREMENT_compressed_compressed-1-24_compressed-13-24.pdf27 Feb 2024
Deviation Report with respect to model copy of AgreementFile: MODEL OF AGGREMENT_compressed_compressed-1-24_compressed-1-12.pdf27 Feb 2024
Proforma of Agreement for saleFile: Model_AFS_in_English (1) (1).pdf24 Feb 2024
Details of encumbrances concerned to FinanceFile: Non encumbrance certificate RERA signature villas.pdf25 Dec 2023
Details of encumbrances concerned to LegalFile: Non encumbrance certificate RERA signature villas.pdf25 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - 2022-23 ADARSH ASSOCIATES.pdf25 Dec 2023
Copy of the legal title reportFile: LEGAL TITLE REPORT-NEW_compressed.pdf25 Apr 2022
Declaration in FORM BFile: form B promoter notarized.pdf26 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEERS CERTIFICATE.pdf8 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Chartered Accountant Certificate.pdf8 Mar 2022
Layout approvalFile: HADAPSAR SANCTIONED PLAN 1,3,4,6,7.pdf24 Feb 2022
Building plan approvalFile: HADAPSAR SANCTIONED PLAN 2,5,8.pdf24 Feb 2022
Copy of Layout Approval (in case of layout)File: HADAPSAR SANCTIONED PLAN 1,3,4,6,7.pdf24 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: HADAPSAR SANCTIONED PLAN 2,5,8.pdf24 Feb 2022
CERSAI detailsFile: CERSAI undertaking for no security intrest rera Hadapsar.pdf24 Feb 2022
PAN CardFile: Pan (Shirish) New.pdf17 Feb 2022
Details of encumbrancesFile: Non encumbrance certificate RERA signature villas.pdf17 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Hadapsar (81 9A).pdf17 Feb 2022
Declaration about Commencement CertificateFile: declaration of commencement certificate RERA signature villas.pdf17 Feb 2022
Proforma of Allotment letterFile: PROFORMA FOR ALLOTMENT.pdf17 Feb 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Signature Park Phase - IP52100054229Mulshi -Marunji, Pune47Jan 2024Certificate SignedMar 2027Not due yet
Atharva Shrishti, Phase 1, Wing AP52100006976PUNE, Pune-Aug 2017Certificate SignedJul 2022Registered original: Jan 2021Jan 2022

How this compares with Pune

62%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 37 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SIGNATURE VILLAS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HADAPSAR13,700+ in Pune

2 kmSIGNATURE VILLASCompleted 4Lapsed / revoked 4Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: SHRISH NIHALCHAND LODHA

SHRISH NIHALCHAND LODHA has 1 registration on MahaRERA, including SIGNATURE VILLAS. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SIGNATURE VILLAS is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SIGNATURE VILLAS?

The registered promoter entity is SHRISH NIHALCHAND LODHA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SIGNATURE VILLAS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SIGNATURE VILLAS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SIGNATURE VILLAS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SIGNATURE VILLAS?

The professionals named in the filing: Architect: ARCH. PARVEZ JAMADAR AND ASSOCIATES; Architect: Vaibhav Lohar; Engineer: Mr. Shreyansh Khabiya; Engineer: VISHAL VINODKUMAR LODHA; Chartered Accountant: CHHALLANI AGARWAL AND ASSOCIATES; Chartered Accountant: R R BAFNA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIGNATURE VILLAS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIGNATURE VILLAS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIGNATURE VILLAS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.