ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Atharva Shrishti, Phase 1, Wing A

Completed No litigation declared Residential / Group Housing project

Atharva Shrishti, Phase 1, Wing A

By ATHARVA BUILDCON

RG-MH-19824 · RERA P52100006976 · Last updated on MahaRERA portal: 5 Feb 2024

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2022Possession promisedregistration recorded completed
3Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

Atharva Shrishti, Phase 1, Wing A is a Residential / Group Housing project by ATHARVA BUILDCON in Pune, Maharashtra, registered with MahaRERA as P52100006976 on 17 Aug 2017. The registration is recorded completed; possession was promised by 27 Jul 2022. The completion date has moved by 18 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameAtharva Shrishti, Phase 1, Wing A
  • TypeResidential / Group Housing
  • Location
    • PUNE
    • MANJARI KH
    • Haveli
    • 412307
  • Pincode412307
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100006976
  • ReraGenie IDRG-MH-19824

Builder

  • NameATHARVA BUILDCON
  • Entity typePartnership
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseJan 2021Revised toJul 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Aug 2017
  • Promised completion27 Jul 2022
  • Revised completionRevised to 27 Jul 2022 (originally 27 Jan 2021)
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ATHARVA SHRUSHTI, PHASE 1, WING ANA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Parking filed45

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots45
Closed/Covered15
Open Space30

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,870 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3487.38
Proposed, not sanctioned3,010 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchG AND G TOWER PUNE SOLAPUR ROAD HADAPSAR PUNE 411028

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATIT ADMULWAR
PartnerRole in project
ATHARVA BUILDCON-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100010959Jan 2021 → Jan 2022

Reason as filed by the promoterDue to COVID-19 and lockdown, the project has been extended.

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000064562Swapnil SisodiyaMahesh Eknath Thorat11/09/2020
CC005000000064792ganesh bavkarAatharva Buildcon01/11/2020
CC005000000106590Nanasaheb Shahurao ShelkeM/S ATHARVA BUILDCON08/02/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Feb 2024

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Completion Certificate.pdf5 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion certificate Wing A.pdf2 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ATHARVA SRUSHTI WING A.pdf18 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect B and C_compressed.pdf6 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 B and C_compressed.pdf6 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March 22 B and C.pdf6 Apr 2023
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY.pdf6 Apr 2023
Certificates of CA (Form 3)File: CA Certificate B C Signed March 2023.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 A 21-22_compressed.pdf24 Mar 2023
OtherFile: NEW PARTNERSHIL DEED_Receipt.pdf20 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Application receipt.pdf19 Jul 2022
Copy of the legal title reportFile: Layout Approval.pdf30 Jun 2022
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf30 Jun 2022
Building Plan Approval (IOD)File: Building Plan 1.pdf30 Jun 2022
Building Plan Approval (IOD)File: Building Plan 2.pdf30 Jun 2022
Building Plan Approval (IOD)File: Building Plan 3.pdf30 Jun 2022
Building Plan Approval (IOD)File: Building Plan 4.pdf30 Jun 2022
Building Plan Approval (IOD)File: Building Plan 5.pdf30 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: CC_compressed.pdf30 Jun 2022
Declaration about Commencement CertificateFile: CC Declaration March 22 A.pdf30 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_compressed.pdf30 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 A wing.pdf30 Jun 2022
Disclosure of sold/ booked inventoryFile: Disclosure of inventory March 22 A.pdf30 Jun 2022
CERSAI detailsFile: Cersai-1-2_compressed.pdf30 Jun 2022
CERSAI detailsFile: Cersai-3-4_compressed.pdf30 Jun 2022
CERSAI detailsFile: Cersai-5-6.pdf30 Jun 2022
Certificates of CA (Form 3)File: CA certificate A Signed _compressed.pdf30 Jun 2022
Declaration about Commencement CertificateFile: commencement certificate Declaration.pdf4 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate_compressed.pdf4 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE.pdf4 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20_merged.pdf4 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21 Merged.pdf4 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 21-22 Q1 Merged.pdf4 Dec 2021
Disclosure of sold/ booked inventoryFile: disclosure of inventory.pdf4 Dec 2021
Certificates of CA (Form 3)File: CA Certificate.pdf4 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 17-18.pdf4 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf4 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf4 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf4 Dec 2021
OtherFile: RESIGN LETTER-compressed.pdf5 Oct 2021
OtherFile: ATHARVA BUILDCON.pdf27 Aug 2020
Details of encumbrancesFile: FORM B ATHARVA SHRUSHTI.pdf31 Jul 2017
Building Plan Approval (IOD)File: 123 PLAN 2.pdf31 Jul 2017
Building Plan Approval (IOD)File: 123 PLAN 3.pdf31 Jul 2017
Declaration in FORM BFile: FORM B ATHARVA SHRUSHTI.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECTS CERTIFICATE ATARVA BUILDCON.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ATHARAVA BUILDCON.pdf31 Jul 2017
Certificates of CA (Form 3)File: FORM 3 BY CA.pdf31 Jul 2017
Proforma of Allotment letterFile: DRAFT AGREEMENT.pdf31 Jul 2017
PAN CardFile: PAN CARD.pdf28 Jul 2017
Copy of the legal title reportFile: SEARCH REPORT.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCE CERTIFICATE.pdf28 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Atharva Shrishti, Phase 1, Wing A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE13,700+ in Pune

2 kmAtharva Shrishti, Phase Completed 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: ATHARVA BUILDCON

ATHARVA BUILDCON has 3 registrations on MahaRERA, including RAJ RESIDENCY and Atharva Shrishti, Phase 1, Wing A. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Atharva Shrishti, Phase 1, Wing A is delayed beyond 27 Jul 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Atharva Shrishti, Phase 1, Wing A?

The registered promoter entity is ATHARVA BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Atharva Shrishti, Phase 1, Wing A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Atharva Shrishti, Phase 1, Wing A?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Atharva Shrishti, Phase 1, Wing A?

The professionals named in the filing: Architect: ATIT ADMULWAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Atharva Shrishti, Phase 1, Wing A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Atharva Shrishti, Phase 1, Wing A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Atharva Shrishti, Phase 1, Wing A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.