Home / Browse projects / Pune, Maharashtra / Siddhivinayak Apartment
Siddhivinayak Apartment
RG-MH-41573 · RERA P52100052325 · Last updated on MahaRERA portal: 6 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 17 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Siddhivinayak Apartment is a Residential / Group Housing project by M/S SIDDHIDATA BUILDCON in Pune, Maharashtra, registered with MahaRERA as P52100052325 on 10 Aug 2023. Possession was promised by 31 May 2025 and is now 17 months past that date.
At a glance
Project
- NameSiddhivinayak Apartment
- TypeResidential / Group Housing
- Location
- Chinchwad
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 411019
- Pincode411019
- RERA no.P52100052325
- ReraGenie IDRG-MH-41573
Builder
- NameM/S SIDDHIDATA BUILDCON
- Entity typePartnership
- PartnersGAURI DHANANJAY DHAM, MANGALA SAMBHAJI INJE, SUMEDH PRAKASH AIREKAR
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Aug 2023
- Promised completion31 May 2025
- Revised completionNone
- Buildings1 building record
- Documents filed53 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Siddhivinayak Apartment | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
Siddhivinayak Apartment: 76% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 6 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Suyash Co Operative Housing Society Ltd | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar Amit Sawalakhe |
| Engineer | Mr Nikhil Wable |
| Chartered Accountant | CA P G Agarwal and Co |
| Partner | Role in project |
|---|---|
| M/S SIDDHIDATA BUILDCON | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Jul 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jun 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jun 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed53
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 6 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SIDDHIDATA BUILDCON_compressed.pdf | 6 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Siddhidata (1).pdf | 6 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Data Siddhivinayak Apartment.pdf | 6 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 01.pdf | 18 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 18 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Data Siddhivinayak Apartment.pdf | 18 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Siddhidata Infra_compressed.pdf | 18 Jul 2024 |
| Layout approvalFile: Siddhivinayak Apartment Final Plan 01.pdf | 25 Jun 2024 |
| Building plan approvalFile: Siddhivinayak Apartment 02Final Plan.pdf | 25 Jun 2024 |
| Copy of Layout Approval (in case of layout)File: Siddhivinayak Apartment Final Plan 01.pdf | 25 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Siddhivinayak Apartment 02Final Plan.pdf | 25 Jun 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Siddhivinayak Apartment CC.pdf | 25 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: sOLD UNSOLD SIDDHIVINAYAK.pdf | 24 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Siddhivinayak.pdf | 22 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Siddhivinayak.pdf | 22 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Siddhivinayak_compressed.pdf | 22 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Siddhivinayak Apartment.pdf | 25 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Siddhivinayak Apartment.pdf | 25 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Data Siddhivinayak Apartment.pdf | 25 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 25 Jan 2024 |
| Layout approvalFile: Sidhidata buildcon 1 map_compressed.pdf | 9 Jan 2024 |
| Building plan approvalFile: Sidhidata buildcon 2 map_compressed.pdf | 9 Jan 2024 |
| Copy of Layout Approval (in case of layout)File: Sidhidata buildcon 1 map_compressed.pdf | 9 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Sidhidata buildcon 2 map_compressed.pdf | 9 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- Siddhivinayak (2).pdf | 18 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Siddhivinayak_compressed.pdf | 16 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Siddhivinayak_compressed.pdf | 16 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold- Siddhivinayak.pdf | 16 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Siddhidata Buildcon_compressed.pdf | 16 Oct 2023 |
| Building plan approvalFile: 2 pg_compressed.pdf | 6 Jul 2023 |
| Layout approvalFile: 1 pg_compressed.pdf | 6 Jul 2023 |
| PAN CardFile: 1 PAN Card (3).pdf | 6 Jul 2023 |
| Copy of the legal title reportFile: Format A.pdf | 6 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance letter.pdf | 6 Jul 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance letter.pdf | 6 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: 1 pg_compressed.pdf | 6 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 2 pg_compressed.pdf | 6 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: SKM-C454e23052912460_compressed.pdf | 6 Jul 2023 |
| Declaration about Commencement CertificateFile: Format D-.pdf | 6 Jul 2023 |
| Declaration in FORM BFile: Form B.pdf | 6 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 6 Jul 2023 |
| CERSAI detailsFile: Cersai Report.pdf | 6 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Revised Form 3.pdf | 6 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Aanexure A.pdf | 6 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (1).pdf | 6 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A- Aditya shinde.pdf | 6 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 6 Jul 2023 |
| Proforma of Agreement for saleFile: RERA AGREEMENT TO SALE DRAFT.pdf | 6 Jul 2023 |
| Proforma of Allotment letterFile: Model form of AL.pdf | 6 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format 1- Bank.pdf | 6 Jul 2023 |
| Deviation Report with respect to Allotment letterFile: deviation of Allotment letter.pdf | 6 Jul 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation of Agreement to sale.pdf | 6 Jul 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 53 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Siddhivinayak Apartment on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chinchwad13,700+ in Pune
THE CENTRAL PARK PHASE -I
R RETAIL VENTURES PRIVATE LIMITED
THE CENTRAL PARK PHASE - II
R RETAIL VENTURES PRIVATE LIMITED
SHUBH VEDA Tower E F G and Block 8
UPSQUARE VENTURES LLP
EMPIRE SQUARE PHASE III
EMPIRE PROPERTIES
THE CENTRAL PARK PHASE - III
R RETAIL VENTURES PRIVATE LIMITED
The Central Park Phase- IV Tower D3
R Retail Ventures Private Limited
Builder: M/S SIDDHIDATA BUILDCON
M/S SIDDHIDATA BUILDCON has 2 registrations on MahaRERA, including IYANA RESIDENCY and Siddhivinayak Apartment. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Siddhivinayak Apartment shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Siddhivinayak Apartment is delayed beyond 31 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Siddhivinayak Apartment?
The registered promoter entity is M/S SIDDHIDATA BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Siddhivinayak Apartment?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Siddhivinayak Apartment?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Siddhivinayak Apartment?
The professionals named in the filing: Architect: Ar Amit Sawalakhe; Engineer: Mr Nikhil Wable; Chartered Accountant: CA P G Agarwal and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Siddhivinayak Apartment?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback