SHUBH VEDA Tower E F G and Block 8

By UPSQUARE VENTURES LLP

RG-MH-32541 · RERA P52100080358 · Last updated on MahaRERA portal: 6 May 2026

Source: official MahaRERA filing

Red flags

  • Rs 20.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
0 of 44Construction stages doneacross 4 buildings; furthest along: Excavation, 0%
434 of 595Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 122 documents Report an error

SHUBH VEDA Tower E F G and Block 8 is a Others project by UPSQUARE VENTURES LLP in Pune, Maharashtra, registered with MahaRERA as P52100080358 on 26 May 2025. Possession is promised by 31 Dec 2030. 161 of the 595 units on this registration are recorded sold or booked, and 0 of 44 construction stages are filed complete.

At a glance

Project

  • NameSHUBH VEDA Tower E F G and Block 8
  • TypeOthers
  • Location
    • Akurdi Street
    • Akurdi
    • Mawal
    • Pune
    • 411019
  • Pincode411019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100080358
  • ReraGenie IDRG-MH-32541

Builder

  • NameUPSQUARE VENTURES LLP
  • Entity typeOthers
  • GSTIN27AATFR7375Q1ZV
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations3 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredMay 2025PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 May 2025
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings4 building records
  • Documents filed122 files

Current status

27%161 of 595 units booked
5.2%Work done, per cost certificate

Figures as on 6 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower ENA40362600260
Tower FNA40361330133
Tower GNA38301720172
Block 8NA4303030

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 0%.

Tower E0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower F0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower G0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Block 80%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed756

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots756
Closed/Covered756
BuildingClosed/CoveredTotal
Tower E270270
Tower F269269
Tower G187187
Block 83030

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area15,154 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOUSING FINANCE LIMITED
Secured amountRs 20.00 crore
CERSAI search filedYes
Declared on18 Jul 2025

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI95335.86
Proposed, not sanctioned95,336 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., SDC Plot No.2, Sector No.29, Ravet, Tal.Haveli, Dist.Pune, Maharashtra.412101
Estimated costRs 587.10 cr
Cost incurredRs 30.50 cr
Work done5.19%
BuildingWingEstimatedIncurred
-NARs 247.88 crRs 12.88 cr
Tower ENARs 128.93 crRs 6.70 cr
Tower FNARs 111.82 crRs 5.81 cr
Tower GNARs 94.01 crRs 4.88 cr
Block 8NARs 4.46 crRs 23.17 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAkash Appasaheb Bongarde
ArchitectSANKALP DESINERS
EngineerSankalp Designers
EngineerAkash Appasaheb Bongarde
EngineerMubin Mehmood Shaikh
Chartered AccountantPatel & Sharma
PartnerRole in project
UPSQUARE VENTURES LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Apr 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 May 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed122

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 - TOWER EFG and B8 - Q4.pdf6 May 2026
Withdrawal Update Form 2File: FORM 2 - TOWER EFG and B8 - Q4.pdf6 May 2026
Withdrawal Update Form 3File: FORM 3 - TOWER EFG and B8 - Q4.pdf6 May 2026
Withdrawal Update Form 1File: Form1 Tower EFG Block 8- Dec 25.pdf31 Jan 2026
Withdrawal Update Form 2File: Form2 Tower EFG Block 8- Dec 25.pdf31 Jan 2026
Withdrawal Update Form 3File: Form3 Tower EFG Block 8- Dec 25.pdf31 Jan 2026
Layout approvalFile: 00 Layout Approval - Highlighted.pdf9 Dec 2025
Layout approvalFile: 01 Basement 1(Parking) Floor Plan.pdf5 Dec 2025
Layout approvalFile: 02 Basement 2 & 3( parking) Floor Plan.pdf5 Dec 2025
Layout approvalFile: 03 Ground (parking)Floor Plan.pdf5 Dec 2025
Layout approvalFile: 04 Podium 1 (parking) Floor Plan.pdf5 Dec 2025
Layout approvalFile: 05 Podium 2 (Parking) Floor Plan.pdf5 Dec 2025
Layout approvalFile: 06 Podium 3 (Parking) Floor Plan.pdf5 Dec 2025
Layout approvalFile: 07 Podium 4 (parking) Floor Plan.pdf5 Dec 2025
Layout approvalFile: 08 Podium 5 (parking) Floor Plan.pdf5 Dec 2025
Building plan approvalFile: 44 Tower E - Podium 2 & 3 Floor.pdf5 Dec 2025
Building plan approvalFile: 45 Tower E - P4, P5 & 1st,5th,10th,15th,20th,24th & 29th Floor.pdf5 Dec 2025
Building plan approvalFile: 46 Tower E - Other Floor Plan Upto 31st Floor.pdf5 Dec 2025
Building plan approvalFile: 47 Tower E - Elevation section AA.pdf5 Dec 2025
Building plan approvalFile: 48 Tower E - Elevation section BB.pdf5 Dec 2025
Building plan approvalFile: 49 Tower E - Elevation E.pdf5 Dec 2025
Building plan approvalFile: 50 Tower F - Building - Ground & podium1.pdf5 Dec 2025
Building plan approvalFile: 51 Tower F - Podium 2,3 & 4.pdf5 Dec 2025
Building plan approvalFile: 52 Tower F - Podium 5 & 1st,5th,10th,15th,20th,24th & 29th Floor.pdf5 Dec 2025
Building plan approvalFile: 53 Tower F - Other Floor Plan Upto 31st Floor & terrace.pdf5 Dec 2025
Building plan approvalFile: 54 Tower F - Elevation AA.pdf5 Dec 2025
Building plan approvalFile: 55 Tower F - Elevation BB.pdf5 Dec 2025
Building plan approvalFile: 56 Tower F - Elevation.pdf5 Dec 2025
Building plan approvalFile: 57 Tower G - Building , Ground & podium 1.pdf5 Dec 2025
Building plan approvalFile: 58 Tower G - Podium 2,3, 4 & 5.pdf5 Dec 2025
Building plan approvalFile: 59 Tower G - Floor Plans.pdf5 Dec 2025
Building plan approvalFile: 60 Tower G - 14th & Terrace Floor.pdf5 Dec 2025
Building plan approvalFile: 61 Tower G - Elevation.pdf5 Dec 2025
Building plan approvalFile: 62 Tower G - Elevation.pdf5 Dec 2025
Building plan approvalFile: 63 Tower G - Elevation.pdf5 Dec 2025
Building plan approvalFile: 28 Block 8 - Ground mezz 1st 2nd Floor Plan Elevation.pdf5 Dec 2025
Withdrawal Update Form 1File: Form 1 EFG u0026 8 Sept 25.pdf29 Nov 2025
Withdrawal Update Form 2File: Form 2 Tower E, F, G and Block 8- Sept 25.pdf29 Nov 2025
Withdrawal Update Form 3File: Form-3 EFG u0026 8 Sept 25.pdf29 Nov 2025
Withdrawal Update Form 1File: FORM 1 - TOWER E,F,G, BL 8.pdf18 Jul 2025
Withdrawal Update Form 2File: FORM 2 - TOWER EFG u0026 B8.pdf18 Jul 2025
Withdrawal Update Form 3File: FORM 3 - TOWER EFG u0026 B8- Uploaded.pdf18 Jul 2025
Other - LegalFile: 11 UPSQUARE CONVEYANCE DEED-26-09-2023_11zon.pdf20 May 2025
Other - TechnicalFile: CLARIFICATION - LAND AREA FOR TOWER E F G AND BLOCK 8.pdf20 May 2025
Other - TechnicalFile: CC verification mail -SS (1).pdf12 May 2025
Layout approvalFile: 01 layout_rotated-compressed.pdf3 May 2025
Building plan approvalFile: E Gf P1 P4.pdf3 May 2025
Building plan approvalFile: 43 E P2 P3 P5.pdf3 May 2025
Building plan approvalFile: 44 E 1 to18.pdf3 May 2025
Building plan approvalFile: 45 E 14.pdf3 May 2025
Building plan approvalFile: 46 E.pdf3 May 2025
Building plan approvalFile: 47 E.pdf3 May 2025
Building plan approvalFile: 48 E.pdf3 May 2025
Building plan approvalFile: 49 F.pdf3 May 2025
Building plan approvalFile: 50 F.pdf3 May 2025
Building plan approvalFile: 51 F.pdf3 May 2025
Building plan approvalFile: 52 F.pdf3 May 2025
Building plan approvalFile: 53 F.pdf3 May 2025
Building plan approvalFile: 54 F.pdf3 May 2025
Building plan approvalFile: 55 G.pdf3 May 2025
Building plan approvalFile: 56 G.pdf3 May 2025
Building plan approvalFile: 57 G.pdf3 May 2025
Building plan approvalFile: 58 G.pdf3 May 2025
Building plan approvalFile: 30 Block 08 Maz GF 1 2 edited.pdf3 May 2025
Details of encumbrances concerned to FinanceFile: Encumbrance concerned to finance.pdf3 May 2025
Details of encumbrances concerned to FinanceFile: Encumbrance concerned to Legal.pdf3 May 2025
Copy of Layout Approval (in case of layout)File: 01 layout_rotated-compressed.pdf3 May 2025
Declaration in FORM BFile: FORM_B.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECT CERTIFICATE.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA CERTIFICATE.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ENGG CERTIFICATE.pdf3 May 2025
Building Plan Approval / NA Order for plotted developmentFile: 52 F.pdf3 May 2025
Building Plan Approval / NA Order for plotted developmentFile: 47 E.pdf3 May 2025
Building Plan Approval / NA Order for plotted developmentFile: 53 F.pdf3 May 2025
Building Plan Approval / NA Order for plotted developmentFile: 54 F.pdf3 May 2025
Building Plan Approval / NA Order for plotted developmentFile: 55 G.pdf3 May 2025
Building Plan Approval / NA Order for plotted developmentFile: 56 G.pdf3 May 2025
Building Plan Approval / NA Order for plotted developmentFile: 57 G.pdf3 May 2025
Building Plan Approval / NA Order for plotted developmentFile: 58 G.pdf3 May 2025
Building Plan Approval / NA Order for plotted developmentFile: 30 Block 08 Maz GF 1 2 edited.pdf3 May 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Shubh Veda Block 1 2 3 4 5CS No 4663 4664P 4665P Taluka Mawal Village Akurdi Pune 411019142OngoingApr 2028Apr 2028

How this compares with Pune

27%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHUBH VEDA Tower E F G and Block 8 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Akurdi13,700+ in Pune

2 kmSHUBH VEDA Tower E F G aCompleted 25Lapsed / revoked 8Other 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 48 registered projects within 2 km.

Builder: UPSQUARE VENTURES LLP

UPSQUARE VENTURES LLP has 4 registrations on MahaRERA, including Shubh Veda Block 1,2,3,4,5 and SHUBH VEDA Tower E F G and Block 8. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SHUBH VEDA Tower E F G and Block 8 is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHUBH VEDA Tower E F G and Block 8?

The registered promoter entity is UPSQUARE VENTURES LLP, an others as per the filing. Its GSTIN 27AATFR7375Q1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHUBH VEDA Tower E F G and Block 8?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHUBH VEDA Tower E F G and Block 8?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHUBH VEDA Tower E F G and Block 8?

The professionals named in the filing: Architect: Akash Appasaheb Bongarde; Architect: SANKALP DESINERS; Engineer: Sankalp Designers; Engineer: Akash Appasaheb Bongarde; Engineer: Mubin Mehmood Shaikh; Chartered Accountant: Patel & Sharma. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHUBH VEDA Tower E F G and Block 8?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHUBH VEDA Tower E F G and Block 8. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHUBH VEDA Tower E F G and Block 8 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.