Home / Browse projects / Aurangabad, Maharashtra / SHUBHLABH RESIDENCY
SHUBHLABH RESIDENCY
RG-MH-15946 · RERA P51500049767 · Last updated on MahaRERA portal: 24 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 9 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHUBHLABH RESIDENCY is a Residential / Group Housing project by Bhaishree Realtors LLP in Aurangabad, Maharashtra, registered with MahaRERA as P51500049767 on 24 Feb 2023. Possession was promised by 31 Jan 2026 and is now 9 months past that date.
At a glance
Project
- NameSHUBHLABH RESIDENCY
- TypeResidential / Group Housing
- Location
- Vijay Nagar Road
- Garkheda
- Aurangabad (M Corp.)
- Aurangabad
- 431005
- Pincode431005
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500049767
- ReraGenie IDRG-MH-15946
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on24 Feb 2023
- Promised completion31 Jan 2026
- Revised completionNone
- Buildings2 building records
- Documents filed103 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| APARTMENT BUILDING A | NA | 9 | 0 | 0 | 0 | 0 |
| ROWHOUSE BUILDING B | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
13 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 80%.
APARTMENT BUILDING A62%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
ROWHOUSE BUILDING B71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed8
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| APARTMENT BUILDING A | 1 | 0 | 1 |
| ROWHOUSE BUILDING B | 1 | 6 | 7 |
Land and ownership16
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Kalpana Satish Patel | Aurangabad (M Corp.) | Aurangabad |
| Kavita Narendra Patel | Aurangabad (M Corp.) | Aurangabad |
| Ajeeta Gaurang Mody | - | Hyderabad |
| Anurita Ameet Patel | Aurangabad (M Corp.) | Aurangabad |
| Sejal Ameet Patel | Aurangabad (M Corp.) | Aurangabad |
| Rajula Satish Patel | Aurangabad (M Corp.) | Aurangabad |
| Panabai Uttamchand Runwal | Aurangabad (M Corp.) | Aurangabad |
| Santosh Uttamchand Runwal | Aurangabad (M Corp.) | Aurangabad |
| SANDIP UTTAMCHAND RUNWAL | Aurangabad (M Corp.) | Aurangabad |
| SAKHIBAI KAMALKUMAR JAIN | Aurangabad (M Corp.) | Aurangabad |
| POPATLAL UMEDCHAND JAIN | Aurangabad (M Corp.) | Aurangabad |
| LEELABAI MADANLAL JAIN | Aurangabad (M Corp.) | Aurangabad |
| VIKRAM MADANLAL JAIN | Aurangabad (M Corp.) | Aurangabad |
| SANDEEP MADANLAL JAIN | Aurangabad (M Corp.) | Aurangabad |
| SHAKUNTALA MANSUKH JAIN | Aurangabad (M Corp.) | Aurangabad |
| HARSH MANSUKH JAIN | Aurangabad (M Corp.) | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAURABH MIRKUTE MIRKUTE |
| Engineer | PRAMOD MOTE |
| Chartered Accountant | AKSHAY G TALREJA FOR SAGAR KAWNA & CO |
| Chartered Accountant | SATYANARAYAN MANTRI |
| Partner | Role in project |
|---|---|
| Bhaishree Realtors LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Feb 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Feb 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Feb 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed103
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 3File: 03 SHUBHLABH RESIDENCY Q3 FY 25-26 DEC 25.pdf | 24 Apr 2026 |
| Form 1File: 03 Architect Certificate SL R Q-3 FY 2025-26.pdf | 24 Apr 2026 |
| Form 2File: 03) Q-3 ENGG CERTIFICATE DEC-25.pdf | 24 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: 11 DISCLOSURE UNSOLD SOLD DEC-25 .pdf | 24 Apr 2026 |
| Form 1File: 02 Architect Certificate SL R Q-2 FY 2024-25.pdf | 12 Jan 2026 |
| Form 2File: 07 ENGG CERTIFICATE SEP-24.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 06 DISCLOSURE UNSOLD SOLD SEP-24 .pdf | 12 Jan 2026 |
| Form 3File: 08 SHUBHLABH RESIDENCY Q2 FY 24-25 SEP-24.pdf | 12 Jan 2026 |
| Form 1File: 03 Architect Certificate SL R Q-3 FY 2024-25.pdf | 12 Jan 2026 |
| Form 2File: 08 ENGG CERTIFICATE DEC-24.pdf | 12 Jan 2026 |
| Form 3File: 09 SHUBHLABH RESIDENCY Q3 FY 24-25 DEC 24.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 07 DISCLOSURE UNSOLD SOLD DEC-24 .pdf | 12 Jan 2026 |
| Form 1File: 04 Architect Certificate SL R Q-4 FY 2024-25.pdf | 12 Jan 2026 |
| Form 2File: 09 ENGG CERTIFICATE MARCH-25.pdf | 12 Jan 2026 |
| Form 3File: 10 SHUBHLABH RESIDENCY Q4 FY 24-25 MARCH 25.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 08 DISCLOSURE UNSOLD SOLD MAR-25 .pdf | 12 Jan 2026 |
| Form 1File: 01 Architect Certificate SL R Q-1 FY 2025-26.pdf | 12 Jan 2026 |
| Form 2File: 01) Q-1 ENGG CERTIFICATE JUNE-25.pdf | 12 Jan 2026 |
| Form 3File: 01 SHUBHLABH RESIDENCY Q1 FY 25-26 JUNE- 25.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 09 DISCLOSURE UNSOLD SOLD JUNE-25 .pdf | 12 Jan 2026 |
| Form 2File: 01 ENGG CERTIFICATE MAR-23.pdf | 12 Jan 2026 |
| Form 3File: 01 CA Certificate SL R Q-4 FY 2022-23.pdf | 12 Jan 2026 |
| Form 1File: 01 ENGG CERTIFICATE MAR-23.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 0 DISCLOSURE UNSOLD SOLD MAR-23 - Copy.pdf | 12 Jan 2026 |
| Form 1File: 03 SHUBHLABH RESIDENCY Q1 FY 23-24 JUNE-23.pdf | 10 Jan 2026 |
| Form 2File: 02 ENGG CERTIFICATE JUN-23.pdf | 10 Jan 2026 |
| Form 3File: 03 SHUBHLABH RESIDENCY Q1 FY 23-24 JUNE-23.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 01 DISCLOSURE UNSOLD SOLD JUNE-23 .pdf | 10 Jan 2026 |
| Form 1File: 02 Architect Certificate SL R Q-2 FY 2023-24 .pdf | 10 Jan 2026 |
| Form 2File: 03 ENGG CERTIFICATE SEP-23.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 02 DISCLOSURE UNSOLD SOLD SEP-23 - Copy.pdf | 10 Jan 2026 |
| Form 3File: 04 SHUBHLABH RESIDENCY Q2 FY 23-24Sept 23.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 03 DISCLOSURE UNSOLD SOLD DEC-23 .pdf | 10 Jan 2026 |
| Form 1File: 03 Architect Certificate SL R Q-3 FY 2023-24.pdf | 10 Jan 2026 |
| Form 2File: 04 ENGG CERTIFICATE DEC-23.pdf | 10 Jan 2026 |
| Form 3File: 05 SHUBHLABH RESIDENCY Q3 FY 23-24 DEC 23.pdf | 10 Jan 2026 |
| Form 1File: 04 Architect Certificate SL R Q-4 FY 2023-24.pdf | 10 Jan 2026 |
| Form 2File: 05 ENGG CERTIFICATE MAR-24.pdf | 10 Jan 2026 |
| Form 3File: 06 SHUBHLABH RESIDENCY Q4 FY 23-24 MAR 24.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 04 DISCLOSURE UNSOLD SOLD MAR-24 .pdf | 10 Jan 2026 |
| Form 1File: 01 Architect Certificate SL R Q-1 FY 2024-25.pdf | 10 Jan 2026 |
| Form 2File: 06 ENGG CERTIFICATE JUN-24.pdf | 10 Jan 2026 |
| Form 3File: 07 SHUBHLABH RESIDENCY Q1 FY 24-25 JUNE-24.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 05 DISCLOSURE UNSOLD SOLD APR-24 - Copy.pdf | 10 Jan 2026 |
| Form 1File: 02 Architect Certificate SL R Q-2 FY 2025-26.pdf | 23 Dec 2025 |
| Form 2File: 02) Q-2 ENGG CERTIFICATE SEPT-25.pdf | 23 Dec 2025 |
| Form 3File: 02 SHUBHLABH RESIDENCY Q2 FY 25-26 SEPT 25.pdf | 23 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE UNSOLD SOLD SEP-25.pdf | 23 Dec 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 SHUBHLABH RESIDENCY Q4 FY 24-25 MARCH 25.pdf | 23 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 08 Architect Certificate SL R Q-3 FY 2024-25.pdf | 17 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 08 ENGG CERTIFICATE DEC-24.pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 09 SHUBHLABH RESIDENCY Q3 FY 24-25 DEC 24.pdf | 10 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 07 Architect Certificate SL R Q-2 FY 2024-25.pdf | 8 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 07 SHUBHLABH RESIDENCY Q1 FY 24-25 JUNE 24.pdf | 8 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 07 SHUBHLABH RESIDENCY Q1 FY 24-25 JUNE-24.pdf | 8 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 07 ENGG CERTIFICATE SEP-24.pdf | 7 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 07 ENGG CERTIFICATE SEP-24.pdf | 7 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5_2324_BhaishreeRealtorsLLP.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 06 Architect Certificate SL R Q-1 FY 2024-25 (2).pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 06 Architect Certificate SL R Q-1 FY 2024-25.pdf | 28 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 05 Architect Certificate SL R Q-4 FY 2023-24.pdf | 3 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05 ENGG CERTIFICATE MAR-24.pdf | 3 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 06 BRL Shubhlabh Residency Q4 FY 23-24 MAR 24.pdf | 1 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 04 Architect Certificate SL R Q-3 FY 2023-24.pdf | 24 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 04 ENGG CERTIFICATE DEC-23.pdf | 24 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F-1_Q3_23-24.pdf | 18 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate SL H Q-4 FY 2022-23_compressed.pdf | 4 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate SL H Q-1 FY 2023-24_compressed.pdf | 4 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate SL H Q-2 FY 2023-24_compressed.pdf | 4 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SCAN F-2 MAR-23_compressed.pdf | 27 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SCAN F-2 JUN-23.pdf | 27 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SCAN F-2 SEPT-23.pdf | 27 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BRL Shubhlabh Residency Sept 23 COMP.pdf | 25 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shubh Labh Residency Form -5 2022-23.pdf | 12 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SL R Q4 22-23.pdf | 28 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SL R Q1 23-24.pdf | 28 Aug 2023 |
| Declaration about Commencement CertificateFile: dcc Bhaishree_0001.pdf | 18 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Form A Bhaishree_0001.pdf | 18 Feb 2023 |
| Other - TechnicalFile: Declaration Bhishree_0001.pdf | 18 Feb 2023 |
| Other - LegalFile: FORM B.pdf | 11 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 103 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHUBHLABH RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Garkheda1,400+ in Aurangabad
Filed coordinates, straight-line distance. 116 registered projects within 2 km.
One World Phase I
SIMAR PRIDE VENTURES LLP
The Solitairee Phase I
Dizzi Land Farms Private Limited
Neo Orbit
Piyush Infratech Pvt.Ltd.
180 and 51 Greens
A.M.PATEL INFRA PVT LTD
MILLENNIUM BUSINESS CENTER
MILLENNIUMPRO NEST LLP
The Solitairee Phase II
Dizzi Land Farms Private Limited
See every Aurangabad project, with the district possession charts
Builder: Bhaishree Realtors LLP
Bhaishree Realtors LLP has 2 registrations on MahaRERA, including SHUBHLABH RESIDENCY and Shubhlabh Heritage. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What does it mean that SHUBHLABH RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHUBHLABH RESIDENCY is delayed beyond 31 Jan 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHUBHLABH RESIDENCY?
The registered promoter entity is Bhaishree Realtors LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHUBHLABH RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHUBHLABH RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHUBHLABH RESIDENCY?
The professionals named in the filing: Architect: SAURABH MIRKUTE MIRKUTE; Engineer: PRAMOD MOTE; Chartered Accountant: AKSHAY G TALREJA FOR SAGAR KAWNA & CO; Chartered Accountant: SATYANARAYAN MANTRI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHUBHLABH RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback