Home / Browse projects / Aurangabad, Maharashtra / SHUBHLABH RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

SHUBHLABH RESIDENCY

By Bhaishree Realtors LLP

RG-MH-15946 · RERA P51500049767 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 9 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Jan 2026Possession promised9 months past this date
13 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 80%
0Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

SHUBHLABH RESIDENCY is a Residential / Group Housing project by Bhaishree Realtors LLP in Aurangabad, Maharashtra, registered with MahaRERA as P51500049767 on 24 Feb 2023. Possession was promised by 31 Jan 2026 and is now 9 months past that date.

At a glance

Project

  • NameSHUBHLABH RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Vijay Nagar Road
    • Garkheda
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431005
  • Pincode431005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500049767
  • ReraGenie IDRG-MH-15946

Builder

  • NameBhaishree Realtors LLP
  • Entity typePartnership
  • PartnersNarendra Marotirao Surkutwar, Makarand Dwarkanath Deshpande on behalf of bhaishree ventures llp
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

9 months past promisethis monthRegisteredFeb 2023PromisedJan 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Feb 2023
  • Promised completion31 Jan 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed103 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
APARTMENT BUILDING ANA90000
ROWHOUSE BUILDING BNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 80%.

APARTMENT BUILDING A62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROWHOUSE BUILDING B71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Closed/Covered2
Open Space6
BuildingClosed/CoveredOpen SpaceTotal
APARTMENT BUILDING A101
ROWHOUSE BUILDING B167

Land and ownership16

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,106 sq m
Land owned byThe promoter, with other names on the file
Named landowners16
LandownerVillageDistrict
Kalpana Satish PatelAurangabad (M Corp.)Aurangabad
Kavita Narendra PatelAurangabad (M Corp.)Aurangabad
Ajeeta Gaurang Mody-Hyderabad
Anurita Ameet PatelAurangabad (M Corp.)Aurangabad
Sejal Ameet PatelAurangabad (M Corp.)Aurangabad
Rajula Satish PatelAurangabad (M Corp.)Aurangabad
Panabai Uttamchand RunwalAurangabad (M Corp.)Aurangabad
Santosh Uttamchand RunwalAurangabad (M Corp.)Aurangabad
SANDIP UTTAMCHAND RUNWALAurangabad (M Corp.)Aurangabad
SAKHIBAI KAMALKUMAR JAINAurangabad (M Corp.)Aurangabad
POPATLAL UMEDCHAND JAINAurangabad (M Corp.)Aurangabad
LEELABAI MADANLAL JAINAurangabad (M Corp.)Aurangabad
VIKRAM MADANLAL JAINAurangabad (M Corp.)Aurangabad
SANDEEP MADANLAL JAINAurangabad (M Corp.)Aurangabad
SHAKUNTALA MANSUKH JAINAurangabad (M Corp.)Aurangabad
HARSH MANSUKH JAINAurangabad (M Corp.)Aurangabad

Approvals and building plan

Permissible FSI6105.87
Proposed, not sanctioned6,106 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNear PROZONE Mall Chikalthana Aurangabad

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAURABH MIRKUTE MIRKUTE
EngineerPRAMOD MOTE
Chartered AccountantAKSHAY G TALREJA FOR SAGAR KAWNA & CO
Chartered AccountantSATYANARAYAN MANTRI
PartnerRole in project
Bhaishree Realtors LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 3File: 03 SHUBHLABH RESIDENCY Q3 FY 25-26 DEC 25.pdf24 Apr 2026
Form 1File: 03 Architect Certificate SL R Q-3 FY 2025-26.pdf24 Apr 2026
Form 2File: 03) Q-3 ENGG CERTIFICATE DEC-25.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: 11 DISCLOSURE UNSOLD SOLD DEC-25 .pdf24 Apr 2026
Form 1File: 02 Architect Certificate SL R Q-2 FY 2024-25.pdf12 Jan 2026
Form 2File: 07 ENGG CERTIFICATE SEP-24.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: 06 DISCLOSURE UNSOLD SOLD SEP-24 .pdf12 Jan 2026
Form 3File: 08 SHUBHLABH RESIDENCY Q2 FY 24-25 SEP-24.pdf12 Jan 2026
Form 1File: 03 Architect Certificate SL R Q-3 FY 2024-25.pdf12 Jan 2026
Form 2File: 08 ENGG CERTIFICATE DEC-24.pdf12 Jan 2026
Form 3File: 09 SHUBHLABH RESIDENCY Q3 FY 24-25 DEC 24.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: 07 DISCLOSURE UNSOLD SOLD DEC-24 .pdf12 Jan 2026
Form 1File: 04 Architect Certificate SL R Q-4 FY 2024-25.pdf12 Jan 2026
Form 2File: 09 ENGG CERTIFICATE MARCH-25.pdf12 Jan 2026
Form 3File: 10 SHUBHLABH RESIDENCY Q4 FY 24-25 MARCH 25.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: 08 DISCLOSURE UNSOLD SOLD MAR-25 .pdf12 Jan 2026
Form 1File: 01 Architect Certificate SL R Q-1 FY 2025-26.pdf12 Jan 2026
Form 2File: 01) Q-1 ENGG CERTIFICATE JUNE-25.pdf12 Jan 2026
Form 3File: 01 SHUBHLABH RESIDENCY Q1 FY 25-26 JUNE- 25.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: 09 DISCLOSURE UNSOLD SOLD JUNE-25 .pdf12 Jan 2026
Form 2File: 01 ENGG CERTIFICATE MAR-23.pdf12 Jan 2026
Form 3File: 01 CA Certificate SL R Q-4 FY 2022-23.pdf12 Jan 2026
Form 1File: 01 ENGG CERTIFICATE MAR-23.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: 0 DISCLOSURE UNSOLD SOLD MAR-23 - Copy.pdf12 Jan 2026
Form 1File: 03 SHUBHLABH RESIDENCY Q1 FY 23-24 JUNE-23.pdf10 Jan 2026
Form 2File: 02 ENGG CERTIFICATE JUN-23.pdf10 Jan 2026
Form 3File: 03 SHUBHLABH RESIDENCY Q1 FY 23-24 JUNE-23.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 01 DISCLOSURE UNSOLD SOLD JUNE-23 .pdf10 Jan 2026
Form 1File: 02 Architect Certificate SL R Q-2 FY 2023-24 .pdf10 Jan 2026
Form 2File: 03 ENGG CERTIFICATE SEP-23.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 02 DISCLOSURE UNSOLD SOLD SEP-23 - Copy.pdf10 Jan 2026
Form 3File: 04 SHUBHLABH RESIDENCY Q2 FY 23-24Sept 23.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 03 DISCLOSURE UNSOLD SOLD DEC-23 .pdf10 Jan 2026
Form 1File: 03 Architect Certificate SL R Q-3 FY 2023-24.pdf10 Jan 2026
Form 2File: 04 ENGG CERTIFICATE DEC-23.pdf10 Jan 2026
Form 3File: 05 SHUBHLABH RESIDENCY Q3 FY 23-24 DEC 23.pdf10 Jan 2026
Form 1File: 04 Architect Certificate SL R Q-4 FY 2023-24.pdf10 Jan 2026
Form 2File: 05 ENGG CERTIFICATE MAR-24.pdf10 Jan 2026
Form 3File: 06 SHUBHLABH RESIDENCY Q4 FY 23-24 MAR 24.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 04 DISCLOSURE UNSOLD SOLD MAR-24 .pdf10 Jan 2026
Form 1File: 01 Architect Certificate SL R Q-1 FY 2024-25.pdf10 Jan 2026
Form 2File: 06 ENGG CERTIFICATE JUN-24.pdf10 Jan 2026
Form 3File: 07 SHUBHLABH RESIDENCY Q1 FY 24-25 JUNE-24.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 05 DISCLOSURE UNSOLD SOLD APR-24 - Copy.pdf10 Jan 2026
Form 1File: 02 Architect Certificate SL R Q-2 FY 2025-26.pdf23 Dec 2025
Form 2File: 02) Q-2 ENGG CERTIFICATE SEPT-25.pdf23 Dec 2025
Form 3File: 02 SHUBHLABH RESIDENCY Q2 FY 25-26 SEPT 25.pdf23 Dec 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE UNSOLD SOLD SEP-25.pdf23 Dec 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 SHUBHLABH RESIDENCY Q4 FY 24-25 MARCH 25.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 08 Architect Certificate SL R Q-3 FY 2024-25.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 08 ENGG CERTIFICATE DEC-24.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 09 SHUBHLABH RESIDENCY Q3 FY 24-25 DEC 24.pdf10 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 07 Architect Certificate SL R Q-2 FY 2024-25.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 07 SHUBHLABH RESIDENCY Q1 FY 24-25 JUNE 24.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 07 SHUBHLABH RESIDENCY Q1 FY 24-25 JUNE-24.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 07 ENGG CERTIFICATE SEP-24.pdf7 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 07 ENGG CERTIFICATE SEP-24.pdf7 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5_2324_BhaishreeRealtorsLLP.pdf7 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 06 Architect Certificate SL R Q-1 FY 2024-25 (2).pdf29 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 06 Architect Certificate SL R Q-1 FY 2024-25.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 05 Architect Certificate SL R Q-4 FY 2023-24.pdf3 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05 ENGG CERTIFICATE MAR-24.pdf3 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 06 BRL Shubhlabh Residency Q4 FY 23-24 MAR 24.pdf1 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 04 Architect Certificate SL R Q-3 FY 2023-24.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 04 ENGG CERTIFICATE DEC-23.pdf24 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F-1_Q3_23-24.pdf18 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate SL H Q-4 FY 2022-23_compressed.pdf4 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate SL H Q-1 FY 2023-24_compressed.pdf4 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate SL H Q-2 FY 2023-24_compressed.pdf4 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SCAN F-2 MAR-23_compressed.pdf27 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SCAN F-2 JUN-23.pdf27 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SCAN F-2 SEPT-23.pdf27 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BRL Shubhlabh Residency Sept 23 COMP.pdf25 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shubh Labh Residency Form -5 2022-23.pdf12 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SL R Q4 22-23.pdf28 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SL R Q1 23-24.pdf28 Aug 2023
Declaration about Commencement CertificateFile: dcc Bhaishree_0001.pdf18 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Form A Bhaishree_0001.pdf18 Feb 2023
Other - TechnicalFile: Declaration Bhishree_0001.pdf18 Feb 2023
Other - LegalFile: FORM B.pdf11 Feb 2023

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep SHUBHLABH RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Garkheda1,400+ in Aurangabad

2 kmSHUBHLABH RESIDENCYCompleted 44Lapsed / revoked 33Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 116 registered projects within 2 km.

Builder: Bhaishree Realtors LLP

Bhaishree Realtors LLP has 2 registrations on MahaRERA, including SHUBHLABH RESIDENCY and Shubhlabh Heritage. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that SHUBHLABH RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHUBHLABH RESIDENCY is delayed beyond 31 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHUBHLABH RESIDENCY?

The registered promoter entity is Bhaishree Realtors LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHUBHLABH RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHUBHLABH RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHUBHLABH RESIDENCY?

The professionals named in the filing: Architect: SAURABH MIRKUTE MIRKUTE; Engineer: PRAMOD MOTE; Chartered Accountant: AKSHAY G TALREJA FOR SAGAR KAWNA & CO; Chartered Accountant: SATYANARAYAN MANTRI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHUBHLABH RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHUBHLABH RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHUBHLABH RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.