Home / Browse projects / Aurangabad, Maharashtra / One World Phase I

Registered Litigation declared Others project

One World Phase I

By SIMAR PRIDE VENTURES LLP

RG-MH-15991 · RERA P51500050146 · Last updated on MahaRERA portal: 12 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 1 complaint at MahaRERA
  • Rs 120.00 crore secured on the land, in favour of State Bank of India

Clear

  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 10 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
16 of 55Construction stages doneacross 5 buildings; furthest along: Sanitary Fittings within the flats /..., 90%
283 of 700Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 233 documents Report an error

One World Phase I is a Others project by SIMAR PRIDE VENTURES LLP in Aurangabad, Maharashtra, registered with MahaRERA as P51500050146 on 21 Mar 2023. Possession is promised by 31 Dec 2028. 417 of the 700 units on this registration are recorded sold or booked, and 16 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameOne World Phase I
  • TypeOthers
  • Location
    • Peer Bazar Road
    • PratapNagar Shahnoorwadi
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431005
  • Pincode431005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500050146
  • ReraGenie IDRG-MH-15991

Builder

  • NameSIMAR PRIDE VENTURES LLP
  • Entity typePartnership
  • PartnersNITIN VENUPRASAD BAGADIYA, RAJENDRA SING DHARAM SINGH RAJPAL
  • Other registrations9 more →
  • Completed8 of 10
  • Declared earlier projects10 →

Key dates

this monthRegisteredMar 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Mar 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings5 building records
  • Documents filed233 files

Current status

60%417 of 700 units booked
66.5%Work done, per cost certificate

Figures as on 12 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building A1-A2NA23211600160
Building B1NA23211180118
Building C1-C2NA23211600160
Building E1 E2 E3 E4NA440133133
MHADANA17161290129

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 12 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

Building A1-A230%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building B133%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building C1-C234%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building E1 E2 E3 E468%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
MHADA70%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 12 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes45%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes40%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceYes40%
Open ParkingNoNot applicable

Parking filed483

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots483
Closed/Covered483
BuildingClosed/CoveredTotal
Building A1-A2160160
Building B18484
Building C1-C2164164
Building E1 E2 E3 E42828
MHADA4747

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area16,470 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofState Bank of India
Secured amountRs 120.00 crore
CERSAI search filedYes
Declared on27 Feb 2026
LandownerVillageDistrict
Tarvindarsingh Dhillon and companyAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityChatrapati Sambhajinagar Mahanagarpalika
Permissible FSI75438.97
Proposed, not sanctioned73,439 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchChikalthana Aurangabad
Estimated costRs 187.28 cr
Cost incurredRs 124.60 cr
Work done66.53%
BuildingWingEstimatedIncurred
Building B1NARs 66.54 crRs 29.83 cr
Building A1-A2NARs 47.12 crRs 27.40 cr
Building C1-C2NARs 32.02 crRs 28.56 cr
Building E1 E2 E3 E4NARs 20.83 crRs 19.25 cr
MHADANARs 16.01 crRs 15.99 cr
-NARs 4.75 crRs 3.56 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAKW Associates
EngineerCore Consultant
EngineerMilind Wadekar
EngineerDattatraya Ranjit Aurade
Chartered AccountantRajesh Agrawal and co
Chartered AccountantNarendra Navandar and co
Chartered AccountantCA Sachin Lathi
PartnerRole in project
SIMAR PRIDE VENTURES LLP-

Litigation declared2

CaseCourtStatus
RCS NO 810/2012/2012CIVIL JUDGE SENIOR DIVISION AURANGABADPending
RCS No 810/2012/2012Civil Judge Senior Division Chhatrapati SambhajinagarOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC003000000040123shyam gopal saincherSimar Pride Ventures LLP10/05/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jun 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jun 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed233

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 233 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: CC-13-2-26.pdf12 Jun 2026
Building plan approvalFile: 1-59 main sheet gr.pdf12 Jun 2026
Building plan approvalFile: 2-59 main sheet_Upper Gr.pdf12 Jun 2026
Building plan approvalFile: 3-59 Firat_fl.pdf12 Jun 2026
Building plan approvalFile: 4-59_A1-A2-P1_P2_1st_fl.pdf12 Jun 2026
Building plan approvalFile: 5-59_A1-A2_2nd_to_20_fl.pdf12 Jun 2026
Building plan approvalFile: 6-59_A1-A2-21_Terrace_Area.pdf12 Jun 2026
Building plan approvalFile: 7-59_A1_Area table_Ele.pdf12 Jun 2026
Building plan approvalFile: 8-59_A2_Area table_Ele.pdf12 Jun 2026
Building plan approvalFile: 9-59_A1_A2_Section.pdf12 Jun 2026
Building plan approvalFile: 18-59_B1_B2-P1_P2_fL.pdf12 Jun 2026
Building plan approvalFile: 19-59_B1_B2_2nd_to_20_fl.pdf12 Jun 2026
Building plan approvalFile: 20-22-59_B1_B2_21_fl_Terrace.pdf12 Jun 2026
Building plan approvalFile: 23-25-59_B1_B2_C1-C2.pdf12 Jun 2026
Building plan approvalFile: 25-27-59_C1_C2.pdf12 Jun 2026
Building plan approvalFile: 28-59_C1_C2_Sec_Ele.pdf12 Jun 2026
Building plan approvalFile: 38-41-59.pdf12 Jun 2026
Building plan approvalFile: 42-45-59_E1_E4.pdf12 Jun 2026
Building plan approvalFile: 46-49-59-E1_E3.pdf12 Jun 2026
Building plan approvalFile: 50-53-59_F_Mhada.pdf12 Jun 2026
Building plan approvalFile: 54-58-59_F_Mhada.pdf12 Jun 2026
Building plan approvalFile: 59-59_Gurudrawa_teble_Block.pdf12 Jun 2026
Withdrawal Update Form 1File: Form 1 Oneworld Phase 1 Mar 26.pdf11 Jun 2026
Withdrawal Update Form 2File: From-2-Engineers Certificate-One world Phase-1-Mar26.pdf11 Jun 2026
Withdrawal Update Form 3File: Form-3 One World Phase-1_0001.pdf11 Jun 2026
Form 1File: SPVLLP Architect Certificate-One World Phase I Dec 25.pdf11 Mar 2026
Form 2File: ONE WORLD ENGINEERS CERTIFICATE OCT TO DEC-2025.pdf11 Mar 2026
Form 3File: Form no 3 Simar_0001.pdf11 Mar 2026
Disclosure of Sold and Booked InventoryFile: corrigandum One world-Dec25.pdf11 Mar 2026
OthersFile: Form - 2A - Engineers Certificate (Quality Assurance)-One World-Dec25.pdf11 Mar 2026
Form 1File: SPVLLP Architect Certificate-One World Phase I Dec 24.pdf27 Feb 2026
Form 2File: ONE WORLD ENGINEERS CERTIFICATE OCT TO DEC-2024.pdf27 Feb 2026
Form 3File: Form-3 Simar Pride Venture_ Dt-31-12-2024.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: corrigandum One world-Dec24.pdf27 Feb 2026
OthersFile: Form 2A.pdf27 Feb 2026
Form 1File: Form 1.pdf27 Feb 2026
Form 2File: Form 2.pdf27 Feb 2026
Form 3File: Form-3 Simar Pride Venture Dt-31-03-2024.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disc.pdf27 Feb 2026
OthersFile: Form 2A.pdf27 Feb 2026
Form 1File: Form 1.pdf27 Feb 2026
Form 2File: Form 2.pdf27 Feb 2026
Form 3File: Form-3 Simar Pride Venture_Dt-30-06-2024.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disc.pdf27 Feb 2026
OthersFile: Form 2A.pdf27 Feb 2026
Form 1File: Form 1.pdf27 Feb 2026
Form 2File: Form 2.pdf27 Feb 2026
Form 3File: Form 3.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disc.pdf27 Feb 2026
OthersFile: Form 2A.pdf27 Feb 2026
Form 1File: Form 1.pdf27 Feb 2026
Form 2File: Form 2.pdf27 Feb 2026
Form 3File: Form 3.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disc.pdf27 Feb 2026
OthersFile: Form 2A.pdf27 Feb 2026
Form 1File: Form 1.pdf27 Feb 2026
Form 2File: Form 2.pdf27 Feb 2026
Form 3File: Form 3.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disc.pdf27 Feb 2026
OthersFile: Form 2A.pdf27 Feb 2026
Form 1File: Form 1.pdf27 Feb 2026
Form 2File: Form 2.pdf27 Feb 2026
Form 3File: Form 3.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disc.pdf27 Feb 2026
OthersFile: Form 2A.pdf27 Feb 2026
Form 1File: Form 1.pdf27 Feb 2026
Form 2File: Form 2.pdf27 Feb 2026
Form 3File: Form-3 Simar Pride Venture_Dt-30-09-2024.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disc.pdf27 Feb 2026
OthersFile: Form 2A.pdf27 Feb 2026
Form 1File: SPVLLP Architect Certificate-One World Phase I Marc 25.pdf27 Feb 2026
Form 2File: ONE WORLD ENGINEERS CERTIFICATE JAN TO MAR -2025.pdf27 Feb 2026
Form 3File: Form-3 Simar Pride Venture_ Dt-31-03-2025.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: corrigandum One world-Mar25.pdf27 Feb 2026
OthersFile: Form - 2A - Engineers Certificate (Quality Assurance)-One World- Marc24.pdf27 Feb 2026
Form 1File: SPVLLP Architect Certificate-One World Phase I June 25.pdf27 Feb 2026
Form 2File: ONE WORLD ENGINEERS CERTIFICATE APR TO JUNE-2025.pdf27 Feb 2026
Form 3File: Form -3 One World Phase-30-6-25.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: corrigandum One world-Jun25.pdf27 Feb 2026
OthersFile: Form - 2A - Engineers Certificate (Quality Assurance)-One World- JUN25.pdf27 Feb 2026

Promoter's earlier projects10

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

10 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
MY WORLD PLOT NO 2 BUILDING D1 TO D6P51500015862CHIKALTHANA, Aurangabad-Mar 2018CompletedDec 2026Jan 2023
MY WORLD BUILDING B1-B2-B3P51500015772CHIKALTHANA, Aurangabad-Mar 2018CompletedDec 2024Jan 2023
My World Building B 4-5-6Gut No 708 Chikalthana108-CompletedDec 2023Jul 2022
My World Building B 7-8-9Gut No 708 Chikalthana108-CompletedMar 2023Oct 2021
My World Building A4Gut No 708 Chikalthana36-CompletedMar 2023Oct 2021
My World Building A3Gut No 708 Chikalthana36-CompletedMar 2023Oct 2021
My World Building A1-A2Gut No 708 Chikalthana88-CompletedMar 2023Oct 2021
MANJEET PRIDE GLORYGUT NO 136P DEOLAI ROAD BEED BYPASS AURANGABAD74-CompletedJul 2017Jul 2017
manjeet prideplot no 361 316A 317 317A mahanagar1 cidco waluj aurangabad112-CompletedJul 2016Jun 2016
MANJEET PRIDE PRIMOGUT NO 81 P BEED BYPASS ROAD AURANGABAD70-CompletedMar 2015Mar 2015

How this compares with Aurangabad

60%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep One World Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PratapNagar Shahnoorwadi1,400+ in Aurangabad

2 kmOne World Phase ICompleted 31Lapsed / revoked 20Other 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 96 registered projects within 2 km.

Builder: SIMAR PRIDE VENTURES LLP

SIMAR PRIDE VENTURES LLP has 10 registrations on MahaRERA, including MY WORLD BUILDING A3 and MY WORLD BUILDING B1-B2-B3. Its filings disclose 10 earlier MahaRERA projects: declares 10 of 10 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if One World Phase I is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of One World Phase I?

The registered promoter entity is SIMAR PRIDE VENTURES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in One World Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against One World Phase I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for One World Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at One World Phase I?

The professionals named in the filing: Architect: AKW Associates; Engineer: Core Consultant; Engineer: Milind Wadekar; Engineer: Dattatraya Ranjit Aurade; Chartered Accountant: Rajesh Agrawal and co; Chartered Accountant: Narendra Navandar and co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in One World Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About One World Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save One World Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.