Home / Browse projects / Aurangabad, Maharashtra / One World Phase I
One World Phase I
RG-MH-15991 · RERA P51500050146 · Last updated on MahaRERA portal: 12 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- 1 complaint at MahaRERA
- Rs 120.00 crore secured on the land, in favour of State Bank of India
Clear
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 10 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
One World Phase I is a Others project by SIMAR PRIDE VENTURES LLP in Aurangabad, Maharashtra, registered with MahaRERA as P51500050146 on 21 Mar 2023. Possession is promised by 31 Dec 2028. 417 of the 700 units on this registration are recorded sold or booked, and 16 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameOne World Phase I
- TypeOthers
- Location
- Peer Bazar Road
- PratapNagar Shahnoorwadi
- Aurangabad (M Corp.)
- Aurangabad
- 431005
- Pincode431005
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500050146
- ReraGenie IDRG-MH-15991
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on21 Mar 2023
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings5 building records
- Documents filed233 files
Current status
Figures as on 12 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A1-A2 | NA | 23 | 21 | 160 | 0 | 160 |
| Building B1 | NA | 23 | 21 | 118 | 0 | 118 |
| Building C1-C2 | NA | 23 | 21 | 160 | 0 | 160 |
| Building E1 E2 E3 E4 | NA | 4 | 4 | 0 | 133 | 133 |
| MHADA | NA | 17 | 16 | 129 | 0 | 129 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 12 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.
Building A1-A230%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 40% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 35% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building B133%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building C1-C234%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 45% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building E1 E2 E3 E468%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
MHADA70%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 12 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 45% |
| Water Supply | Yes | 75% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 40% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 40% |
| Electrical meter room, sub-station, receiving station | Yes | 20% |
| Aggregate area of recreational Open Space | Yes | 40% |
| Open Parking | No | Not applicable |
Parking filed483
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Building A1-A2 | 160 | 160 |
| Building B1 | 84 | 84 |
| Building C1-C2 | 164 | 164 |
| Building E1 E2 E3 E4 | 28 | 28 |
| MHADA | 47 | 47 |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Tarvindarsingh Dhillon and company | Aurangabad (M Corp.) | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building B1 | NA | Rs 66.54 cr | Rs 29.83 cr |
| Building A1-A2 | NA | Rs 47.12 cr | Rs 27.40 cr |
| Building C1-C2 | NA | Rs 32.02 cr | Rs 28.56 cr |
| Building E1 E2 E3 E4 | NA | Rs 20.83 cr | Rs 19.25 cr |
| MHADA | NA | Rs 16.01 cr | Rs 15.99 cr |
| - | NA | Rs 4.75 cr | Rs 3.56 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AKW Associates |
| Engineer | Core Consultant |
| Engineer | Milind Wadekar |
| Engineer | Dattatraya Ranjit Aurade |
| Chartered Accountant | Rajesh Agrawal and co |
| Chartered Accountant | Narendra Navandar and co |
| Chartered Accountant | CA Sachin Lathi |
| Partner | Role in project |
|---|---|
| SIMAR PRIDE VENTURES LLP | - |
Litigation declared2
| Case | Court | Status |
|---|---|---|
| RCS NO 810/2012/2012 | CIVIL JUDGE SENIOR DIVISION AURANGABAD | Pending |
| RCS No 810/2012/2012 | Civil Judge Senior Division Chhatrapati Sambhajinagar | Ongoing |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC003000000040123 | shyam gopal saincher | Simar Pride Ventures LLP | 10/05/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Mar 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Jun 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Jun 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed233
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 233 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Commencement certificateFile: CC-13-2-26.pdf | 12 Jun 2026 |
| Building plan approvalFile: 1-59 main sheet gr.pdf | 12 Jun 2026 |
| Building plan approvalFile: 2-59 main sheet_Upper Gr.pdf | 12 Jun 2026 |
| Building plan approvalFile: 3-59 Firat_fl.pdf | 12 Jun 2026 |
| Building plan approvalFile: 4-59_A1-A2-P1_P2_1st_fl.pdf | 12 Jun 2026 |
| Building plan approvalFile: 5-59_A1-A2_2nd_to_20_fl.pdf | 12 Jun 2026 |
| Building plan approvalFile: 6-59_A1-A2-21_Terrace_Area.pdf | 12 Jun 2026 |
| Building plan approvalFile: 7-59_A1_Area table_Ele.pdf | 12 Jun 2026 |
| Building plan approvalFile: 8-59_A2_Area table_Ele.pdf | 12 Jun 2026 |
| Building plan approvalFile: 9-59_A1_A2_Section.pdf | 12 Jun 2026 |
| Building plan approvalFile: 18-59_B1_B2-P1_P2_fL.pdf | 12 Jun 2026 |
| Building plan approvalFile: 19-59_B1_B2_2nd_to_20_fl.pdf | 12 Jun 2026 |
| Building plan approvalFile: 20-22-59_B1_B2_21_fl_Terrace.pdf | 12 Jun 2026 |
| Building plan approvalFile: 23-25-59_B1_B2_C1-C2.pdf | 12 Jun 2026 |
| Building plan approvalFile: 25-27-59_C1_C2.pdf | 12 Jun 2026 |
| Building plan approvalFile: 28-59_C1_C2_Sec_Ele.pdf | 12 Jun 2026 |
| Building plan approvalFile: 38-41-59.pdf | 12 Jun 2026 |
| Building plan approvalFile: 42-45-59_E1_E4.pdf | 12 Jun 2026 |
| Building plan approvalFile: 46-49-59-E1_E3.pdf | 12 Jun 2026 |
| Building plan approvalFile: 50-53-59_F_Mhada.pdf | 12 Jun 2026 |
| Building plan approvalFile: 54-58-59_F_Mhada.pdf | 12 Jun 2026 |
| Building plan approvalFile: 59-59_Gurudrawa_teble_Block.pdf | 12 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Oneworld Phase 1 Mar 26.pdf | 11 Jun 2026 |
| Withdrawal Update Form 2File: From-2-Engineers Certificate-One world Phase-1-Mar26.pdf | 11 Jun 2026 |
| Withdrawal Update Form 3File: Form-3 One World Phase-1_0001.pdf | 11 Jun 2026 |
| Form 1File: SPVLLP Architect Certificate-One World Phase I Dec 25.pdf | 11 Mar 2026 |
| Form 2File: ONE WORLD ENGINEERS CERTIFICATE OCT TO DEC-2025.pdf | 11 Mar 2026 |
| Form 3File: Form no 3 Simar_0001.pdf | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: corrigandum One world-Dec25.pdf | 11 Mar 2026 |
| OthersFile: Form - 2A - Engineers Certificate (Quality Assurance)-One World-Dec25.pdf | 11 Mar 2026 |
| Form 1File: SPVLLP Architect Certificate-One World Phase I Dec 24.pdf | 27 Feb 2026 |
| Form 2File: ONE WORLD ENGINEERS CERTIFICATE OCT TO DEC-2024.pdf | 27 Feb 2026 |
| Form 3File: Form-3 Simar Pride Venture_ Dt-31-12-2024.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: corrigandum One world-Dec24.pdf | 27 Feb 2026 |
| OthersFile: Form 2A.pdf | 27 Feb 2026 |
| Form 1File: Form 1.pdf | 27 Feb 2026 |
| Form 2File: Form 2.pdf | 27 Feb 2026 |
| Form 3File: Form-3 Simar Pride Venture Dt-31-03-2024.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Disc.pdf | 27 Feb 2026 |
| OthersFile: Form 2A.pdf | 27 Feb 2026 |
| Form 1File: Form 1.pdf | 27 Feb 2026 |
| Form 2File: Form 2.pdf | 27 Feb 2026 |
| Form 3File: Form-3 Simar Pride Venture_Dt-30-06-2024.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Disc.pdf | 27 Feb 2026 |
| OthersFile: Form 2A.pdf | 27 Feb 2026 |
| Form 1File: Form 1.pdf | 27 Feb 2026 |
| Form 2File: Form 2.pdf | 27 Feb 2026 |
| Form 3File: Form 3.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Disc.pdf | 27 Feb 2026 |
| OthersFile: Form 2A.pdf | 27 Feb 2026 |
| Form 1File: Form 1.pdf | 27 Feb 2026 |
| Form 2File: Form 2.pdf | 27 Feb 2026 |
| Form 3File: Form 3.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Disc.pdf | 27 Feb 2026 |
| OthersFile: Form 2A.pdf | 27 Feb 2026 |
| Form 1File: Form 1.pdf | 27 Feb 2026 |
| Form 2File: Form 2.pdf | 27 Feb 2026 |
| Form 3File: Form 3.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Disc.pdf | 27 Feb 2026 |
| OthersFile: Form 2A.pdf | 27 Feb 2026 |
| Form 1File: Form 1.pdf | 27 Feb 2026 |
| Form 2File: Form 2.pdf | 27 Feb 2026 |
| Form 3File: Form 3.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Disc.pdf | 27 Feb 2026 |
| OthersFile: Form 2A.pdf | 27 Feb 2026 |
| Form 1File: Form 1.pdf | 27 Feb 2026 |
| Form 2File: Form 2.pdf | 27 Feb 2026 |
| Form 3File: Form-3 Simar Pride Venture_Dt-30-09-2024.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Disc.pdf | 27 Feb 2026 |
| OthersFile: Form 2A.pdf | 27 Feb 2026 |
| Form 1File: SPVLLP Architect Certificate-One World Phase I Marc 25.pdf | 27 Feb 2026 |
| Form 2File: ONE WORLD ENGINEERS CERTIFICATE JAN TO MAR -2025.pdf | 27 Feb 2026 |
| Form 3File: Form-3 Simar Pride Venture_ Dt-31-03-2025.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: corrigandum One world-Mar25.pdf | 27 Feb 2026 |
| OthersFile: Form - 2A - Engineers Certificate (Quality Assurance)-One World- Marc24.pdf | 27 Feb 2026 |
| Form 1File: SPVLLP Architect Certificate-One World Phase I June 25.pdf | 27 Feb 2026 |
| Form 2File: ONE WORLD ENGINEERS CERTIFICATE APR TO JUNE-2025.pdf | 27 Feb 2026 |
| Form 3File: Form -3 One World Phase-30-6-25.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: corrigandum One world-Jun25.pdf | 27 Feb 2026 |
| OthersFile: Form - 2A - Engineers Certificate (Quality Assurance)-One World- JUN25.pdf | 27 Feb 2026 |
Promoter's earlier projects10
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| MY WORLD PLOT NO 2 BUILDING D1 TO D6P51500015862 | CHIKALTHANA, Aurangabad | - | Mar 2018 | Completed | Dec 2026 | Jan 2023 |
| MY WORLD BUILDING B1-B2-B3P51500015772 | CHIKALTHANA, Aurangabad | - | Mar 2018 | Completed | Dec 2024 | Jan 2023 |
| My World Building B 4-5-6 | Gut No 708 Chikalthana | 108 | - | Completed | Dec 2023 | Jul 2022 |
| My World Building B 7-8-9 | Gut No 708 Chikalthana | 108 | - | Completed | Mar 2023 | Oct 2021 |
| My World Building A4 | Gut No 708 Chikalthana | 36 | - | Completed | Mar 2023 | Oct 2021 |
| My World Building A3 | Gut No 708 Chikalthana | 36 | - | Completed | Mar 2023 | Oct 2021 |
| My World Building A1-A2 | Gut No 708 Chikalthana | 88 | - | Completed | Mar 2023 | Oct 2021 |
| MANJEET PRIDE GLORY | GUT NO 136P DEOLAI ROAD BEED BYPASS AURANGABAD | 74 | - | Completed | Jul 2017 | Jul 2017 |
| manjeet pride | plot no 361 316A 317 317A mahanagar1 cidco waluj aurangabad | 112 | - | Completed | Jul 2016 | Jun 2016 |
| MANJEET PRIDE PRIMO | GUT NO 81 P BEED BYPASS ROAD AURANGABAD | 70 | - | Completed | Mar 2015 | Mar 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 9 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 233 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep One World Phase I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PratapNagar Shahnoorwadi1,400+ in Aurangabad
Filed coordinates, straight-line distance. 96 registered projects within 2 km.
The Solitairee Phase I
Dizzi Land Farms Private Limited
Neo Orbit
Piyush Infratech Pvt.Ltd.
180 and 51 Greens
A.M.PATEL INFRA PVT LTD
MILLENNIUM BUSINESS CENTER
MILLENNIUMPRO NEST LLP
The Solitairee Phase II
Dizzi Land Farms Private Limited
Infinity Business Park
ABOLI ADVISORS LLP
See every Aurangabad project, with the district possession charts
Builder: SIMAR PRIDE VENTURES LLP
SIMAR PRIDE VENTURES LLP has 10 registrations on MahaRERA, including MY WORLD BUILDING A3 and MY WORLD BUILDING B1-B2-B3. Its filings disclose 10 earlier MahaRERA projects: declares 10 of 10 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if One World Phase I is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of One World Phase I?
The registered promoter entity is SIMAR PRIDE VENTURES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in One World Phase I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against One World Phase I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for One World Phase I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at One World Phase I?
The professionals named in the filing: Architect: AKW Associates; Engineer: Core Consultant; Engineer: Milind Wadekar; Engineer: Dattatraya Ranjit Aurade; Chartered Accountant: Rajesh Agrawal and co; Chartered Accountant: Narendra Navandar and co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in One World Phase I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.