Home / Browse projects / Aurangabad, Maharashtra / Shrihari Nakshatra

Registration lapsed No litigation declared Residential / Group Housing project

Shrihari Nakshatra

By Marathwada Builders & Developers

RG-MH-00773 · RERA P51500002659 · Last updated on MahaRERA portal: 6 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 80%
0Complaints at MahaRERAon this registration
Jump to the 144 documents Report an error

Shrihari Nakshatra is a Residential / Group Housing project by Marathwada Builders & Developers in Aurangabad, Maharashtra, registered with MahaRERA as P51500002659 on 2 Aug 2017. Possession was promised by 29 Jun 2024 and is now 28 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameShrihari Nakshatra
  • TypeResidential / Group Housing
  • Location
    • Nakshatrawadi to Paithan Road
    • Nakshatrawadi
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431002
  • Pincode431002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500002659
  • ReraGenie IDRG-MH-00773

Builder

  • NameMarathwada Builders & Developers
  • Entity typePartnership
  • PartnerPratik Pramod Khairnar

Key dates

28 months past promisethis monthRegisteredAug 2017First promiseJun 2023Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Aug 2017
  • Promised completion29 Jun 2024
  • Revised completionRevised to 29 Jun 2024 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed144 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BuildingNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.

A Building: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities17

As on 6 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
Power Back upYes100%
LiftYes100%

Parking filed209

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots209
Closed/Covered88
Open Space121

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,762 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9465.47
Proposed, not sanctioned2,930 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGurunath Sankul, Kalda Corner, Chetna Nagar, Aurangabad- 431001

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRajaram Jadhav
EngineerAkshay Rodge
Chartered AccountantShrikant P Thorat & Co
PartnerRole in project
Marathwada Builders & Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500016789Jun 2023 → Jun 2024

Reason as filed by the promoterDear Sir/Madam, I am writing to formally request an extension for the completion date of the Shrihari Nakshatra project, as per the guidelines and regulations set by MahaRERA. The original completion date was set for 30th June 2023, and we are seeking an extension until 29th June 2024. The reason for the delay in the project's completion is as follows: Due to slow bookings, there has been a delay in the progress of the project. However, I would like to mention that we have already completed the construction of the 5-storey building, and the entire structure is ready. Additionally, some common

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Nov 2024

Documents filed144

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 144 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_6_24.pdf6 Dec 2024
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_9_24.pdf6 Dec 2024
Certificates of CA (Form 5)File: Form5_CA_certificate_SHN_31_3_24.pdf6 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold_Booked_Inventory_SHN_March24.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold_Booked_Inventory_SHN_June24.pdf30 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_SHN_19_11_24.pdf25 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_30_9_24.pdf24 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4_SHN_21_11_24.pdf24 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_31_3_24.pdf20 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_30_6_24.pdf20 Nov 2024
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_31_3_24.pdf20 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_30_9_24.pdf20 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_31_3_24.pdf4 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_30_6_24.pdf4 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Oc Inward SHN_10_6_24.pdf4 Jul 2024
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_9_23.pdf12 Apr 2024
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_31_12_23.pdf12 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_30_9_23.pdf15 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_31_12_23.pdf15 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_30_9_23.pdf15 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_31_12_23.pdf15 Feb 2024
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_31_3_23.pdf22 Nov 2023
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_6_23.pdf22 Nov 2023
Certificates of CA (Form 5)File: Form5_CA_certificate_SHN_31_3_23.pdf22 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_30_6_23.pdf6 Sep 2023
Disclosure of sold/ booked inventoryFile: Sold_Booked_Inventory_SHN_June23.pdf6 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A_SHN Eng Cert 2020.pdf29 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2A_SHN Eng Cert 2021.pdf29 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form2A_SHN Eng Cert 2022.pdf29 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A_SHN Eng Cert 2023.pdf29 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_31_3_23.pdf14 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_31_3_23.pdf1 Jun 2023
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_31_12_22.pdf1 Jun 2023
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_9_22.pdf1 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold_Booked_Inventory_SHN_March23.pdf24 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_30_9_22.pdf17 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_31_12_22.pdf17 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_31_12_22.pdf17 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_30_9_22.pdf17 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_30_9_22.pdf17 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_31_12_22.pdf17 May 2023
Disclosure of sold/ booked inventoryFile: Sold_Booked_Inventory_SHN_Sept22.pdf16 Feb 2023
Disclosure of sold/ booked inventoryFile: Sold_Booked_Inventory_SHN_Dec22.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5_CA_certificate_SHN_31_3_21.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5_CA_certificate_SHN_31_3_22.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5_CA_certificate_SHN_31_3_18.pdf8 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5_CA_certificate_SHN_31_3_19.pdf8 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form5_CA_certificate_SHN_31_3_20.pdf8 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5_CA_certificate_SHN_31_3_21.pdf8 Feb 2023
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_6_22.pdf22 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_30_6_22.pdf18 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_30_6_22.pdf18 Sep 2022
Certificates of CA (Form 3)File: Form2_Engg's_Certificate_SHN_31_3_22.pdf18 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2_Engg's_Certificate_SHN_30_6_22.pdf1 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold_Booked_Inventory_SHN_June22.pdf1 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_31_3_22.pdf4 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_31_3_22.pdf4 Jul 2022
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_31_12_21.pdf6 Jun 2022
Disclosure of sold/ booked inventoryFile: Sold_Booked_Inventory_SHN_March22.pdf21 Apr 2022
Disclosure of sold/ booked inventoryFile: Sold_Booked_Inventory_SHN_Dec21.pdf5 Feb 2022
Layout approvalFile: Drawing_Layout_SHN_New_29_10_21.pdf2 Feb 2022
Building plan approvalFile: Drawing_A_Building_SHN_New_29_10_21.pdf2 Feb 2022
Copy of Layout Approval (in case of layout)File: Drawing_Layout_SHN_New_29_10_21.pdf2 Feb 2022
Building Plan Approval (IOD)File: Drawing_A_Building_SHN_New_29_10_21.pdf2 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: CC_SHN_29_10_21.pdf2 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_31_12_21.pdf2 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg's_Certificate_SHN_31_12_21.pdf2 Feb 2022
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_9_21.pdf27 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_30_9_21.pdf14 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold_Booked_Inventory_SHN_Sept21.pdf13 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg_Certificate_SHN_30_6_21.pdf11 Oct 2021
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_6_21.pdf31 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold-Booked Inventory_SHN_Aug-21.pdf26 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_SHN_30_6_21.pdf12 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engg_Certificate_SHN_30_6_21.pdf12 Aug 2021
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_6_20.pdf28 Jun 2021
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_9_20.pdf28 Jun 2021
Certificates of CA (Form 3)File: Form5_CA_certificate_SHN_31_12_20.pdf28 Jun 2021
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_31_3_21.pdf28 Jun 2021
Certificates of CA (Form 3)File: Form3_CA_certificate_SHN_30_6_20.pdf13 Jun 2021

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 12 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Shrihari Nakshatra on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nakshatrawadi1,400+ in Aurangabad

2 kmShrihari NakshatraCompleted 4Lapsed / revoked 1Other 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: Marathwada Builders & Developers

Marathwada Builders & Developers has 1 registration on MahaRERA, including Shrihari Nakshatra. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that Shrihari Nakshatra shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shrihari Nakshatra is delayed beyond 29 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shrihari Nakshatra?

The registered promoter entity is Marathwada Builders & Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shrihari Nakshatra?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shrihari Nakshatra?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shrihari Nakshatra?

The professionals named in the filing: Architect: Rajaram Jadhav; Engineer: Akshay Rodge; Chartered Accountant: Shrikant P Thorat & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shrihari Nakshatra?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shrihari Nakshatra. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shrihari Nakshatra to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.