SHRI GOVINDAM HEIGHTS

By SHREE VYANKATESHA INFRA

RG-MH-36593 · RERA P51500034840 · Last updated on MahaRERA portal: 14 May 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 12 months from the original
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 98%
137 of 238Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

SHRI GOVINDAM HEIGHTS is a Others project by SHREE VYANKATESHA INFRA in Aurangabad, Maharashtra, registered with MahaRERA as P51500034840 on 28 Apr 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 101 of the 238 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSHRI GOVINDAM HEIGHTS
  • TypeOthers
  • Location
    • DEVLAI
    • SATARA DEVLAI
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431002
  • Pincode431002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500034840
  • ReraGenie IDRG-MH-36593

Builder

  • NameSHREE VYANKATESHA INFRA
  • Entity typePartnership
  • PartnersSAYED TANVIRABANU KAUSAR, KIRAN NARAYANRAO PATIL, KANTA MAHADEV KADAM, PALLAVI SWAPNIL JAHAGIRDAR, SUHAS MANGESHRAO TENDULKAR

Key dates

this monthRegisteredApr 2022First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Apr 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed76 files

Current status

42%101 of 238 units booked
98.0%Work done, per cost certificate

Figures as on 14 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHRI GOVINDAM HEIGHTSNA10819246238

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 98%.

SHRI GOVINDAM HEIGHTS: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%

Progress on shared amenities15

As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes95%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes97%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed78

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots78
Closed/Covered78

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,294 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityAurangabad Municipal Corporation, Aurangabad
Permissible FSI19493.23
Proposed, not sanctioned9,767 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHAHGANJ AURANGABAD
Estimated costRs 30.85 cr
Cost incurredRs 30.23 cr
Work done98.0%
BuildingWingEstimatedIncurred
SHRI GOVINDAM HEIGHTSNARs 29.38 crRs 28.79 cr
-NARs 1.47 crRs 1.44 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCHANDRASHEKHAR AND ASSOCIATES
EngineerCHNADRASHEKHAR AND ASSOCIATES
EngineerER AKASH RATHOD
Chartered AccountantANUPAM VYAWAHARE AND CO
Chartered AccountantBKPS AND ASSOCAITES
PartnerRole in project
SHREE VYANKATESHA INFRA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA15042620641Mar 2026 → Mar 2027

Reason as filed by the promoterAn application for project extension has been submitted for SHRI GOVINDAM HEIGHT S ' (MahaRERA Reg. No: P51500034840) under Section 7(3) of the RERA Act. The project construction stands fully completed in strict compliance with the sanctioned plans and Commencement Certificate, with all statutory setbacks and margins duly adhered to. The Promoter applied for Occupancy Certificate on 18/09/2025; however, the same is pending with the Municipal Corporation. The delay has arisen solely due to subsequent provisions introduced in the revised Development Plan, including 18 mtrs DP road widening, whic

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12604604Shyamal Akshay GambhirSHREE VYANKATESHA INFRA22/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Apr 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architects Certificate - Form 1.pdf14 May 2026
Withdrawal Update Form 2File: Engineers Certificate - Form 2.pdf14 May 2026
Withdrawal Update Form 3File: Form-3.pdf14 May 2026
Form 2A (FY 2022-2023)File: 1 Form-2A 22-23.pdf15 Apr 2026
Form 2A (FY 2023-2024)File: 2 Form-2A 23-24.pdf15 Apr 2026
Form 2A (FY 2025-2026)File: 5 Form-2A 25-26.pdf15 Apr 2026
Form 1File: Form-1 Dec 25.pdf13 Apr 2026
Form 2File: Form-2 Dec 25.pdf13 Apr 2026
Form 3File: Form-3 Dec 25.pdf13 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold Dec 25.pdf13 Apr 2026
Form 2A (FY 2024-2025)File: Form-2A (FY24 25).pdf6 Apr 2026
Form 1File: Form-1 March 25.pdf4 Apr 2026
Form 2File: Form-2 March 25.pdf4 Apr 2026
Form 3File: Form-3 March 25.pdf4 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold March 25.pdf4 Apr 2026
Form 1File: Form-1 June 25.pdf4 Apr 2026
Form 2File: Form-2 June 25.pdf4 Apr 2026
Form 3File: Form-3 June 25.pdf4 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold June 25.pdf4 Apr 2026
Form 1File: Form-1 Sep 25.pdf4 Apr 2026
Form 2File: Form-2 Sep 25.pdf4 Apr 2026
Form 3File: Form-3 Sep 25.pdf4 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold Sep 25.pdf4 Apr 2026
Form 5 (FY 2022-2023)File: Form-5 22-23.pdf2 Apr 2026
Form 5 (FY 2023-2024)File: Form-5 23-24.pdf2 Apr 2026
Form 5 (FY 2024-2025)File: Form-5 24-25.pdf2 Apr 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Form-1 Dec 22.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Form-1 March 23.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Form-1 June 23.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Form-1 Sep 23.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Form-1 Dec 23.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 Form-1 March 24.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Form-1 June 24.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 Form-1 Sep 24.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 Form-1 Dec 24.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form-1 June 22.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 Form-3 Dec 23.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 Form-3 Dec 24.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 Form-3 Sep 24.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 Form-3 Jun 24.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 Form-3 Mar 24.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Form-3 Sep 23.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Form-3 Jun 23.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form-3 Mar 23.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Form-3 Dec 22.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Form-3 Jun 22.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Form-2 June 22.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form-2 Dec 22.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Form-2 March 23.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Form-2 June 23.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Form-2 Sep 23.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Form-2 Dec 23.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 Form-2 March 24.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 Form-2 June 24.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 Form-2 Sep 24.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 Form-2 Dec 24.pdf20 Feb 2025
Copy of the legal title reportFile: UTTAM M DESHPANDE_compressed.pdf6 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 organized-1-6_compressed.pdf20 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 organized-7-13_compressed.pdf20 Apr 2022
Copy of the legal title reportFile: LEGAL TITLE REPORT_compressed.pdf12 Apr 2022
Layout approvalFile: SANCTION PLAN 1-8_compressed.pdf21 Mar 2022
Building plan approvalFile: SANTION PLAN 4-8_compressed.pdf21 Mar 2022
Building plan approvalFile: SANCTION PLAN 8-8_compressed.pdf21 Mar 2022
Building plan approvalFile: SANTION PLAN 4-8_compressed.pdf21 Mar 2022
PAN CardFile: PAN.pdf21 Mar 2022
Details of encumbrancesFile: Venkatesha Infra Letterhead.pdf21 Mar 2022
Copy of Layout Approval (in case of layout)File: SANCTION PLAN 1-8_compressed.pdf21 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: SANTION PLAN 4-8_compressed.pdf21 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN 8-8_compressed.pdf21 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: SANTION PLAN 4-8_compressed.pdf21 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: COMM CERT_compressed.pdf21 Mar 2022
Declaration about Commencement CertificateFile: Venkatesha Infra Format D.pdf21 Mar 2022
Declaration in FORM BFile: Venkatesha Infra Form B_compressed.pdf21 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_200232970625_For_Asset_Based_Search_21_03_2022_17_43_38_402.pdf21 Mar 2022
Proforma of Allotment letterFile: Proforma of Allotment Letter.pdf21 Mar 2022
Proforma of Allotment letterFile: Proforma of the allotment letter and agreement for sale.pdf21 Mar 2022

How this compares with Aurangabad

42%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 12 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep SHRI GOVINDAM HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SATARA DEVLAI1,400+ in Aurangabad

2 kmSHRI GOVINDAM HEIGHTSCompleted 11Lapsed / revoked 10Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 33 registered projects within 2 km.

Builder: SHREE VYANKATESHA INFRA

SHREE VYANKATESHA INFRA has 1 registration on MahaRERA, including SHRI GOVINDAM HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if SHRI GOVINDAM HEIGHTS is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRI GOVINDAM HEIGHTS?

The registered promoter entity is SHREE VYANKATESHA INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRI GOVINDAM HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHRI GOVINDAM HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHRI GOVINDAM HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRI GOVINDAM HEIGHTS?

The professionals named in the filing: Architect: CHANDRASHEKHAR AND ASSOCIATES; Engineer: CHNADRASHEKHAR AND ASSOCIATES; Engineer: ER AKASH RATHOD; Chartered Accountant: ANUPAM VYAWAHARE AND CO; Chartered Accountant: BKPS AND ASSOCAITES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRI GOVINDAM HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRI GOVINDAM HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRI GOVINDAM HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.