SHRI SWAMI SAMARTH RESIDENCY
By M/S SHRI SWAMI SAMARTH BUILDERS AND DEVELOPERS
RG-MH-27618 · RERA P52100034055 · Last updated on MahaRERA portal: 22 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 33 months, 4 of them under MahaRERA's automatic 4-month extension
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHRI SWAMI SAMARTH RESIDENCY is a Residential / Group Housing project by M/S SHRI SWAMI SAMARTH BUILDERS AND DEVELOPERS in DIGHI, 411015, registered with MahaRERA as P52100034055 on 17 Mar 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 33 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 46 of the 47 units on this registration are recorded sold or booked, and 17 of 22 construction stages are filed complete.
At a glance
Project
- NameSHRI SWAMI SAMARTH RESIDENCY
- TypeResidential / Group Housing
- Location
- DIGHI
- 411015
- Pincode411015
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100034055
- ReraGenie IDRG-MH-27618
Builder
- NameM/S SHRI SWAMI SAMARTH BUILDERS AND DEVELOPERS
- Entity typePartnership
- GSTIN27ADZFS7120DIZQ
- PartnersGANESH BALASAHEB GHULE, PARMESHWAR BHIMRAO HANGE, NANASAHEB GENBA MORE, CHANDRAKANT NIGAPPA KEDAR, SURESH NARAYAN BARGE, SAURABH SUDAM POLE, NILESH SIDDHARTH BHOSALE
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on17 Mar 2022
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2024)
- Buildings2 building records
- Documents filed170 files
Current status
Figures as on 22 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A BUILDING | NA | 7 | 6 | 24 | 0 | 24 |
| B BUILDING | NA | 7 | 6 | 23 | 0 | 23 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 22 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
A BUILDING73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B BUILDING82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 22 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed16
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A BUILDING | NA | Rs 4.72 cr | Rs 4.72 cr |
| B BUILDING | NA | Rs 4.03 cr | Rs 4.03 cr |
| - | NA | Rs 81.20 lakh | Rs 33.16 lakh |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | A SQUARE |
| Engineer | MR AMAR JADHAV |
| Engineer | Rohinee Badgujar |
| Engineer | Rahul Kapse & Associates |
| Chartered Accountant | GAUTAM D SHARMA AND ASSOCIATES |
| Chartered Accountant | Pravin Pise |
| Chartered Accountant | VAIBHAV S BHISE |
| Partner | Role in project |
|---|---|
| M/S SHRI SWAMI SAMARTH BUILDERS AND DEVELOPERS | - |
Extensions4
A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.
Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.
Reason as filed by the promoterDue to financial Issue We are not unable to start our construction on site
Reason as filed by the promotera) Time taken in Slum TDR loading and procedural compliances with the concerned Departments. b) There is a limited access to the project land. The materials are unloaded away from the site and through local small transport, materials are taken to project site. Therefore, it took time to lower the water level while excavation and for footing and filling of Murum. The photograph of entry and exit to project land is attached herewith. c) The area is which project is to be constructed and completed is entirely a residential area, therefore there were limitations in time of construction work on dai
Reason as filed by the promoterThe project is complete, but certain corrections and modifications are required to be made in the application before proceeding with the completion update. In view of the same, we request MahaRERA to kindly grant an extension of the completion date to enable us to complete the necessary corrections and thereafter submit the completion update/application. We request you to kindly grant an extension in the project completion date till 31/12/2026. We hope and trust that the above justification/explanation shall be found in order by this Hon'ble Authority, and that this Hon'ble Authority is reques
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed170
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 170 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Arch Certificate June 2025.pdf | 22 Sep 2026 |
| Withdrawal Update Form 1File: Arch Certificate June 2025.pdf | 22 Sep 2026 |
| Withdrawal Update Form 1File: Arch Certificate June 2025.pdf | 22 Sep 2026 |
| Withdrawal Update Form 1File: Arch Certificate June 2025.pdf | 22 Sep 2026 |
| Withdrawal Update Form 1File: Arch Certificate June 2025.pdf | 22 Sep 2026 |
| Withdrawal Update Form 2File: Engineer Certificate June 2025.pdf | 22 Sep 2026 |
| Withdrawal Update Form 2File: Engineer Certificate June 2025.pdf | 22 Sep 2026 |
| Withdrawal Update Form 2File: Engineer Certificate June 2025.pdf | 22 Sep 2026 |
| Withdrawal Update Form 2File: Engineer Certificate June 2025.pdf | 22 Sep 2026 |
| Withdrawal Update Form 2File: Engineer Certificate June 2025.pdf | 22 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificate June 2025-Final.pdf | 22 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificate June 2025-Final.pdf | 22 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificate June 2025-Final.pdf | 22 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificate June 2025-Final.pdf | 22 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificate June 2025-Final.pdf | 22 Sep 2026 |
| Form 5 (FY 2024-2025)File: Audit Report 2024-25.pdf | 21 Sep 2026 |
| Form 5 (FY 2025-2026)File: RERA audit report 25-26.pdf | 21 Sep 2026 |
| Form 1File: AR-Sep 24.pdf | 7 Sep 2026 |
| Form 1File: AR-Dec 24.pdf | 7 Sep 2026 |
| Form 1File: AR-March 25.pdf | 7 Sep 2026 |
| Form 2File: Engineer Certificate Sep 24.pdf | 7 Sep 2026 |
| Form 2File: Engineer Certificate Dec 24.pdf | 7 Sep 2026 |
| Form 2File: Engineer Certificate March 25.pdf | 7 Sep 2026 |
| Form 3File: CA-Sep 24.pdf | 7 Sep 2026 |
| Form 3File: CA-Dec 24.pdf | 7 Sep 2026 |
| Form 3File: CA-March 25.pdf | 7 Sep 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-Sep 24.pdf | 7 Sep 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-Dec 24.pdf | 7 Sep 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-March 25.pdf | 7 Sep 2026 |
| Form 1File: AR-June 22.pdf | 18 Aug 2026 |
| Form 2File: ER-June 22.pdf | 18 Aug 2026 |
| Form 3File: CA - June 22.pdf | 18 Aug 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-June 22.pdf | 18 Aug 2026 |
| Form 1File: AR-March 22.pdf | 29 Jul 2026 |
| Form 1File: AR-Sep 22.pdf | 29 Jul 2026 |
| Form 1File: AR-Dec 22.pdf | 29 Jul 2026 |
| Form 1File: AR-March 23.pdf | 29 Jul 2026 |
| Form 1File: AR-Sep 23.pdf | 29 Jul 2026 |
| Form 1File: AR-Dec 23.pdf | 29 Jul 2026 |
| Form 1File: AR-March 24.pdf | 29 Jul 2026 |
| Form 1File: AR-June 24.pdf | 29 Jul 2026 |
| Form 2File: ER-March 22.pdf | 29 Jul 2026 |
| Form 2File: ER-Sep 22.pdf | 29 Jul 2026 |
| Form 2File: ER-Dec 22.pdf | 29 Jul 2026 |
| Form 2File: ER-March 23.pdf | 29 Jul 2026 |
| Form 2File: ER-Sep 23.pdf | 29 Jul 2026 |
| Form 2File: ER-Dec 23().pdf | 29 Jul 2026 |
| Form 2File: ER-March 24.pdf | 29 Jul 2026 |
| Form 2File: ER-June 24.pdf | 29 Jul 2026 |
| Form 3File: CA-March 22.pdf | 29 Jul 2026 |
| Form 3File: CA-Sep 22.pdf | 29 Jul 2026 |
| Form 3File: CA-Dec 22.pdf | 29 Jul 2026 |
| Form 3File: CA-March 23.pdf | 29 Jul 2026 |
| Form 3File: CA-Sep 23.pdf | 29 Jul 2026 |
| Form 3File: CA-Dec 23.pdf | 29 Jul 2026 |
| Form 3File: CA-March 24.pdf | 29 Jul 2026 |
| Form 3File: CA-June 24.pdf | 29 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-March 22.pdf | 29 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-Sep 22.pdf | 29 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-Dec 22.pdf | 29 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-March 23.pdf | 29 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure-23.pdf | 29 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-Dec 23.pdf | 29 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-March 24.pdf | 29 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Dis-June 24.pdf | 29 Jul 2026 |
| Form 2A (FY 2021-2022)File: Form 2A - March 2022.pdf | 29 Jul 2026 |
| Form 2A (FY 2022-2023)File: Form 2A - March2023.pdf | 29 Jul 2026 |
| Form 2A (FY 2023-2024)File: Form 2A - March 2024.pdf | 29 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form 2A - March 2025.pdf | 29 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A - March 2026.pdf | 29 Jul 2026 |
| Form 5 (FY 2021-2022)File: RA-2021-22.pdf | 29 Jul 2026 |
| Form 5 (FY 2022-2023)File: RA-2022-23.pdf | 29 Jul 2026 |
| Form 5 (FY 2023-2024)File: RA 2023-24.pdf | 29 Jul 2026 |
| Declaration in FORM BFile: Pune Swami Samarth Form B.pdf | 29 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold (Sep-2024).pdf | 27 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold (Dec-2024).pdf | 27 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold ( Mar-2025).pdf | 27 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Certificate - 2023.pdf | 27 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer Certificate - 2024-25.pdf | 26 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate (March-2025) (2).pdf | 13 Mar 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 170 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHRI SWAMI SAMARTH RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DIGHI
Filed coordinates, straight-line distance. 48 registered projects within 2 km.
Kohinoor Viva Pixel- Phase II
RISING ASSOCIATES
VIVACITY
REALCON LANDMARKS LLP
TRIAA VASANTAM CITY CENTER PHASE 1
Triaa Realtors LLP
QUE 101 PHASE I
ANNR Unique Realty LLP
NYATI ERA I
NYATI CONSTRUCTION PRIVATE LIMITED
ONE ARETHA PHASE 1
Triaa Landmarks LLP
Builder: M/S SHRI SWAMI SAMARTH BUILDERS AND DEVELOPERS
M/S SHRI SWAMI SAMARTH BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including SHRI SWAMI SAMARTH RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What are my rights if SHRI SWAMI SAMARTH RESIDENCY is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHRI SWAMI SAMARTH RESIDENCY?
The registered promoter entity is M/S SHRI SWAMI SAMARTH BUILDERS AND DEVELOPERS, a partnership as per the filing. Its GSTIN 27ADZFS7120DIZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHRI SWAMI SAMARTH RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHRI SWAMI SAMARTH RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHRI SWAMI SAMARTH RESIDENCY?
The professionals named in the filing: Architect: A SQUARE; Engineer: MR AMAR JADHAV; Engineer: Rohinee Badgujar; Engineer: Rahul Kapse & Associates; Chartered Accountant: GAUTAM D SHARMA AND ASSOCIATES; Chartered Accountant: Pravin Pise. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHRI SWAMI SAMARTH RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback