ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / Shri Ramrao Residency Rowhouse Phase 1

Registration lapsed No litigation declared Residential / Group Housing project

Shri Ramrao Residency Rowhouse Phase 1

By Balasaheb Sambhaji Dighe

RG-MH-08371 · RERA P51500019224 · Last updated on MahaRERA portal: 24 Nov 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
54 of 66Construction stages doneacross 6 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 108 documents Report an error

Shri Ramrao Residency Rowhouse Phase 1 is a Residential / Group Housing project by Balasaheb Sambhaji Dighe in Aurangabad, Maharashtra, registered with MahaRERA as P51500019224 on 14 Jan 2019. Possession was promised by 29 Dec 2023 and is now 34 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameShri Ramrao Residency Rowhouse Phase 1
  • TypeResidential / Group Housing
  • Location
    • Tuljapur
    • Aurangabad
    • 431001
  • Pincode431001
  • RERA no.P51500019224
  • ReraGenie IDRG-MH-08371

Builder

  • NameBalasaheb Sambhaji Dighe
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

34 months past promisethis monthRegisteredJan 2019First promiseDec 2022Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Jan 2019
  • Promised completion29 Dec 2023
  • Revised completionRevised to 29 Dec 2023 (originally 30 Dec 2022)
  • Buildings6 building records
  • Documents filed108 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A Type Rowhouse 1 to 7NA40000
A Type Rowhouse 8 to 14NA40000
A Type Rowhouse 15 to 19NA40000
A Type Rowhouse 20 to 27NA40000
B Type Rowhouse 1 to 6NA20000
B Type Rowhouse 7 to 12NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 24 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

54 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Podiums (if any), at 0%.

A Type Rowhouse 1 to 782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A Type Rowhouse 8 to 1482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A Type Rowhouse 15 to 1982%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A Type Rowhouse 20 to 2782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B Type Rowhouse 1 to 682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B Type Rowhouse 7 to 1282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,846 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Ranjana Rajendra KuberTuljapurAurangabad
Asha Sanjay KuberTuljapurAurangabad
Sumanbai Ramrao DahihandeTuljapurAurangabad

Approvals and building plan

Permissible FSI3407.19
Proposed, not sanctioned3,407 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAdalat Road Aurangabad

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSantosh M Chavan
EngineerPrasad Aphale
PartnerRole in project
Balasaheb Sambhaji Dighe-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500013621Dec 2022 → Dec 2023

Reason as filed by the promoterThe Registered project is having row house structures which is almost completed in all respect, only occupancy certificate from respective authority not received. Hence, we are applying for Extension by one year. We undertake to submit occupancy certificate within the applied extension time i.e. 364 days from existing completion date. Hence, we apply for extension of time limit by 364 days and the proposed completion date will be 29-12-2023.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jan 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jan 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jan 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed108

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 1 Dec 22.pdf24 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 1 31-3-23.pdf24 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 1 30-6-23.pdf24 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 1 30-9-23.pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 1 Dec 22.pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 1 31-3-23.pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 1 30-6-23.pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 1 30-9-23.pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sup cert phase 1 dec 22.pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sup cert phase 1 31-3-23.pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sup cert phase 1 30-6-23.pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sup cert phase 1 30-9-23.pdf24 Nov 2023
Disclosure of sold/ booked inventoryFile: sold - booked Inventory Dec 22.pdf24 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold-booked Inventory Phase 1 31-3-23 (1).pdf24 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold-booked Inventory Phase 1 30-6-23.pdf24 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold-booked Inventory Phase 1 30-9-23.pdf24 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Dighe Sir_0001.pdf16 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure sept 21.pdf13 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure Dec21.pdf13 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure March 22.pdf13 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosures June22.pdf13 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure Sept 22.pdf13 Jan 2023
Certificates of CA (Form 3)File: CA certificate June 21 Ph 1.pdf13 Jan 2023
Certificates of CA (Form 3)File: CA certificate Sep 21 Ph 1 (1).pdf13 Jan 2023
Certificates of CA (Form 3)File: CA certificate Dec 21 Ph 1.pdf13 Jan 2023
Certificates of CA (Form 3)File: CA certificate March 22 Ph 1.pdf13 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5 2019-20.pdf13 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5 2020-21.pdf13 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5 2021-22.pdf13 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch certificate sept 21 phase 1.pdf26 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: phase 1 Dec 21.pdf26 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 22 Phase 1.pdf26 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: June 22 Phase1.pdf26 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sept 22 phase 1.pdf26 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert Sep 21 Ph1.pdf3 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New eng cert Dec 21 Ph 1.pdf3 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Eng cert march 22 Ph 1.pdf3 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Eng cert march 22 Ph 1.pdf3 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Eng cert June 22 Ph 1.pdf3 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Eng cert SEP 22 Ph 1.pdf3 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Sup Crt sep 21 ph 1.pdf3 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: New sup cert Dec 21 Ph 1.pdf3 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: New sup cert march 22 Ph 1.pdf3 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: New sup cert June 22 Ph 1.pdf3 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: New sup cert SEP 22 Ph 1.pdf3 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 1 Dec 20.pdf14 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 1 March 21.pdf14 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 1 june 21.pdf14 Apr 2022
Certificates of CA (Form 3)File: FORM_3_PHASE_I_31_12_2020.pdf14 Apr 2022
Certificates of CA (Form 3)File: FORM_3_PHASE_I_31_3_2021.pdf14 Apr 2022
Declaration about Commencement CertificateFile: Declaration about CC PHASE 1.pdf18 Aug 2021
Disclosure of sold/ booked inventoryFile: PHASE 1.pdf18 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase -1 Dec 20.pdf15 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 1 - March 21.pdf15 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase -1 June 21.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sup cert phase -1 Dec20 (1).pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SupCertphase 1- March 21.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Supcert phase -1 June 21.pdf15 Aug 2021
Certificates of CA (Form 3)File: FORM_3_PHASE_I_MARCH_2020.pdf26 May 2021
Certificates of CA (Form 3)File: FORM_3_PHASE_I_JUNE_2020.pdf26 May 2021
Certificates of CA (Form 3)File: FORM_3_PHASE_I_SEPT_2020.pdf26 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 1 March 2020.pdf24 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 1 june 20.pdf24 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 1 sep20.pdf24 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 1 march 20.pdf24 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 1 june 20.pdf24 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 1 sep 20.pdf24 Mar 2021
Form 2AFile: sup cert phase 1 march 20.pdf24 Mar 2021
Form 2AFile: sup cert phase 1 june 20.pdf24 Mar 2021
Form 2AFile: sup cert phase 1 sep20.pdf24 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch certificate phase 1 Oct-Dec 2019.pdf17 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate phase 1 Oct-Dec 2019.pdf17 Jul 2020
Form 2AFile: supervisor certificate phase 1 Oct-Dec 2019.pdf17 Jul 2020
Certificates of CA (Form 3)File: FORM-3 DEC-19 PHASE-1.pdf17 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate Phase-1.pdf7 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - Phase-1.pdf7 Jan 2020
Form 2AFile: Form 2A phase-1.pdf7 Jan 2020
Certificates of CA (Form 3)File: FORM-3-PHASE 1_JUNE-19.pdf7 Jan 2020
Certificates of CA (Form 3)File: FORM-3-PHASE 1-SEPT-19.pdf7 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 -PHASE 1.pdf30 Nov 2019

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 12 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Shri Ramrao Residency Rowhouse Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tuljapur1,400+ in Aurangabad

Builder: Balasaheb Sambhaji Dighe

Balasaheb Sambhaji Dighe has 2 registrations on MahaRERA, including Shri Ramrao Residency Rowhouse Phase 1 and Shri Ramrao Residency Apartment Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that Shri Ramrao Residency Rowhouse Phase 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shri Ramrao Residency Rowhouse Phase 1 is delayed beyond 29 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shri Ramrao Residency Rowhouse Phase 1?

The registered promoter entity is Balasaheb Sambhaji Dighe, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shri Ramrao Residency Rowhouse Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shri Ramrao Residency Rowhouse Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shri Ramrao Residency Rowhouse Phase 1?

The professionals named in the filing: Architect: Santosh M Chavan; Engineer: Prasad Aphale. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shri Ramrao Residency Rowhouse Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shri Ramrao Residency Rowhouse Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shri Ramrao Residency Rowhouse Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.