Home / Browse projects / Aurangabad, Maharashtra / Shri Ramrao Residency Apartment Phase 2

Registered No litigation declared Residential / Group Housing project

Shri Ramrao Residency Apartment Phase 2

By Balasaheb Sambhaji Dighe

RG-MH-08372 · RERA P51500019379 · Last updated on MahaRERA portal: 23 Sep 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 60 months
  • 2 extensions taken
  • Rs 3.00 crore secured on the land, in favour of Ambajogai Peoples Co op Bank ltd
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 60 months from the original
8 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 80%
36 of 48Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 136 documents Report an error

Shri Ramrao Residency Apartment Phase 2 is a Residential / Group Housing project by Balasaheb Sambhaji Dighe in Aurangabad, Maharashtra, registered with MahaRERA as P51500019379 on 23 Jan 2019. Possession is promised by 31 Dec 2027. The completion date has moved by 60 months from the original filing. 12 of the 48 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete.

At a glance

Project

  • NameShri Ramrao Residency Apartment Phase 2
  • TypeResidential / Group Housing
  • Location
    • Tuljapur
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500019379
  • ReraGenie IDRG-MH-08372

Builder

  • NameBalasaheb Sambhaji Dighe
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJan 2019First promiseDec 2022Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Jan 2019
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed136 files

Current status

25%12 of 48 units booked
75.0%Work done, per cost certificate

Figures as on 23 Sep 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C1-C2 BuildingNA6432032
D BuildingNA6416016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 80%.

C1-C2 Building55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
D Building55%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 23 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes65%
Water SupplyYes55%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes55%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes20%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes60%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes10%

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Closed/Covered40
BuildingClosed/CoveredTotal
C1-C2 Building3232
D Building88

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,264 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofAmbajogai Peoples Co op Bank ltd
Secured amountRs 3.00 crore
CERSAI search filedYes
Declared on30 Jun 2025
LandownerVillageDistrict
Ranjana Rajendra KuberTuljapurAurangabad
Asha Sanjay KuberTuljapurAurangabad
Sumanbai Ramrao DahihandeTuljapurAurangabad

Approvals and building plan

Sanctioning authorityCIDCO Aurangabad
Permissible FSI2892.03
Proposed, not sanctioned2,892 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAdalat Road Aurangabad
Estimated costRs 5.48 cr
Cost incurredRs 4.11 cr
Work done75.0%
BuildingWingEstimatedIncurred
C1-C2 BuildingNARs 5.48 crRs 4.11 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSantosh M Chavan
EngineerPrasad Aphale
Chartered AccountantNilesh Salunke
PartnerRole in project
Balasaheb Sambhaji Dighe-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500013417Dec 2022 → Jun 2025

Reason as filed by the promoterThe construction of the project got delayed on account pandemic situation across country due to COVID-19. The construction work at site was completely stopped due to non-availability of labour. So we have not taken any booking for same project. Hence, we request you to allow us extension by 30 months from date 30/12/2022.

EA30062501872Dec 2022 → Dec 2027

Reason as filed by the promoterThe project has been delayed due to a proposed change in the sanctioned plan. We anticipate that this change will lead to an increase in the potential FSI, which will ultimately benefit the overall project. Despite this delay, we remain fully committed to completing the project within the proposed timeline. We also assure all our existing customers that there will be no change or alteration in the amenities or facilities already committed to them.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jan 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jan 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jan 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed136

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 136 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 1 FORM-1 MAR 23.pdf23 Sep 2025
Form 2File: 2 FORM-2 MAR 23.pdf23 Sep 2025
Form 3File: Form-3 Declaration March 23.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD MAR 23.pdf23 Sep 2025
Form 1File: 1 FORM-1 JUN 23.pdf23 Sep 2025
Form 2File: 2 FORM-2 JUN 23.pdf23 Sep 2025
Form 3File: Form-3 Declaration June 23.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD JUN 23.pdf23 Sep 2025
Form 1File: 1 FORM-1 SEP 23.pdf23 Sep 2025
Form 2File: 2 FORM-2 SEP 23.pdf23 Sep 2025
Form 3File: Form-3 Declaration Sep 23.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD SEP 23.pdf23 Sep 2025
Form 1File: 1 FORM-1 DEC 23.pdf23 Sep 2025
Form 2File: 2 FORM-2 DEC 23.pdf23 Sep 2025
Form 3File: Form-3 Declaration Dec 23.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD DEC 23.pdf23 Sep 2025
Form 1File: 1 FORM-1 MAR 24.pdf23 Sep 2025
Form 2File: 2 FORM-2 MAR 24.pdf23 Sep 2025
Form 3File: Form-3 Declaration March 24.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD MAR 24.pdf23 Sep 2025
Form 1File: 1 FORM-1 JUN 24.pdf23 Sep 2025
Form 2File: 2 FORM-2 JUN 24.pdf23 Sep 2025
Form 3File: Form-3 Declaration June 24.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD JUN 24.pdf23 Sep 2025
Form 1File: 1 FORM-1 SEP 24.pdf23 Sep 2025
Form 2File: 2 FORM-2 SEP 24.pdf23 Sep 2025
Form 3File: Form-3 Declaration Sep 24.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD SEP 24.pdf23 Sep 2025
Form 1File: Form-1 Dec 24.pdf23 Sep 2025
Form 2File: 2 FORM-2 DEC 24.pdf23 Sep 2025
Form 3File: Form-3 Declaration Dec 24.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD DEC 24.pdf23 Sep 2025
Form 1File: Form-1 March 25.pdf23 Sep 2025
Form 2File: 2 FORM-2 MAR 25.pdf23 Sep 2025
Form 3File: Form-3 Declaration March 25.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD MAR 25.pdf23 Sep 2025
Withdrawal Update Form 1File: Form-1 June 25.pdf23 Sep 2025
Withdrawal Update Form 2File: Form-2 June 25.pdf23 Sep 2025
Withdrawal Update Form 3File: Form- 3 CA 20-09-25.pdf23 Sep 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 2 dec 22.pdf24 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert Phase 2 31-3-23.pdf24 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 2 30-6-23 (1).pdf24 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 2 30-9-23.pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 2 Dec 22.pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 2 31-3-23.pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 2 30-6-23.pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert phase 2 30-9-23.pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sup cert phase 2 dec 22.pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Supervisor cert phase 2 31-3-23.pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sup cert phase 2 30-6-23.pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sup cert phase 2 30-9-23.pdf24 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM_5_FY_2019-20.pdf31 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM_5_FY_2020_21.pdf31 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual Report - Form - 5_0001.pdf31 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure - Date 30-09-2021_0001.pdf27 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure - Date 31-12-2021_0001.pdf27 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure - Date 31-03-2022_0001.pdf27 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure - Date 30-06-2022_0001.pdf27 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure - Date 30-09-2022_0001.pdf27 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cer phase 2 sept 21.pdf26 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 2 Dec 21.pdf26 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 22 Phase 2.pdf26 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: June 22 Phase 2.pdf26 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sept 22 Phase 2.pdf26 Dec 2022
Certificates of CA (Form 3)File: CA certificate June 21 Ph 2.pdf26 Dec 2022
Certificates of CA (Form 3)File: CA certificate Sep 21 Ph 2.pdf26 Dec 2022
Certificates of CA (Form 3)File: CA certificate Dec 21 Ph 2.pdf26 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert Sep 21 Ph 2.pdf3 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New eng cert Dec 21 Ph 2.pdf3 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Eng cert march 22 Ph 2.pdf3 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Eng cert June 22 Ph 2.pdf3 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Eng cert SEP 22 Ph 2.pdf3 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Sup cert Sep 21 Ph 2.pdf3 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: New sup cert Dec 21 Ph 2.pdf3 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: New Sup cert March 22 ph 2.pdf3 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: New sup cert June 22 Ph 2.pdf3 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: New sup cert SEP 22 Ph 2.pdf3 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 2 Dec 20.pdf14 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 2 March 21.pdf14 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert phase 2 June 21.pdf14 Apr 2022

How this compares with Aurangabad

25%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 60 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Shri Ramrao Residency Apartment Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tuljapur1,400+ in Aurangabad

2 kmShri Ramrao Residency ApCompleted 3Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: Balasaheb Sambhaji Dighe

Balasaheb Sambhaji Dighe has 2 registrations on MahaRERA, including Shri Ramrao Residency Rowhouse Phase 1 and Shri Ramrao Residency Apartment Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if Shri Ramrao Residency Apartment Phase 2 is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shri Ramrao Residency Apartment Phase 2?

The registered promoter entity is Balasaheb Sambhaji Dighe, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shri Ramrao Residency Apartment Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shri Ramrao Residency Apartment Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shri Ramrao Residency Apartment Phase 2?

The professionals named in the filing: Architect: Santosh M Chavan; Engineer: Prasad Aphale; Chartered Accountant: Nilesh Salunke. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shri Ramrao Residency Apartment Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shri Ramrao Residency Apartment Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shri Ramrao Residency Apartment Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.