Home / Browse projects / Mumbai City, Maharashtra / SHRI PRASANNA
SHRI PRASANNA
RG-MH-74500 · RERA P51900016881 · Last updated on MahaRERA portal: 6 Nov 2024
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
- 1 extension taken
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHRI PRASANNA is a Residential / Group Housing project by TENDULKAR & ASSOCIATES in Mumbai City, Maharashtra, registered with MahaRERA as P51900016881 on 20 Jun 2018. The registration is recorded completed; possession was promised by 1 Apr 2020. 1 complaint is on record with the regulator.
At a glance
Project
- NameSHRI PRASANNA
- TypeResidential / Group Housing
- Location
- BHAVANI SHANKARR ROAD
- DADAR WEST
- GNorth-400028
- Ward GNorth
- Mumbai City
- 400028
- Pincode400028
- RERA no.P51900016881
- ReraGenie IDRG-MH-74500
Builder
- NameTENDULKAR & ASSOCIATES
- Entity typePartnership
- PartnersSIDDHESH SUBHASH TENDULKAR, SUNANDA SUBHASH TENDULKAR
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on20 Jun 2018
- Promised completion1 Apr 2020
- Revised completionNone
- Buildings1 building record
- Documents filed58 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING B | NA | 16 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
WING B: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 6 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MUKTANAND & ASSOCIATES |
| Engineer | A D SHINTRE CONSULTANTS |
| Chartered Accountant | K P KAPADIA & CO |
| Partner | Role in project |
|---|---|
| TENDULKAR & ASSOCIATES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterCommencement certificate is obtained upto Top of 12th Part floor as per last approved amended plan dated 20.03.2019
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000195822 | Vijaykumar Narayan Deshpande | Tendulkar & Associates | 01/02/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Dec 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Mar 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 May 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 5 Nov 2024
Documents filed58
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate (1).pdf | 6 Nov 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate (1)_rotated (1).pdf | 6 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM -4 ANNEXURE-E (1).pdf | 5 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION --369 (1).pdf | 5 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5.pdf | 25 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FORM -4 ANNEXURE-E.pdf | 3 Sep 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION CERTIFICATE.pdf | 29 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf | 5 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CBG Certificate -TA.pdf | 5 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CBG Certificate -TA.pdf | 5 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arhitect Certificate March21 (1).pdf | 16 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 16082021.pdf | 16 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC upto 15th floor.pdf | 28 Aug 2020 |
| Layout approvalFile: 2232887Amendletter_signed (1).pdf | 26 Mar 2020 |
| Layout approvalFile: 1597275171-17-03-2020 03-13-19 Drawing 1.pdf | 26 Mar 2020 |
| Layout approvalFile: 1597275171-17-03-2020 03-13-19 Drawing 2.pdf | 26 Mar 2020 |
| Layout approvalFile: 1597275171-17-03-2020 03-13-19 Drawing 3.pdf | 26 Mar 2020 |
| Layout approvalFile: 1597275171-17-03-2020 03-13-19 Drawing 3.pdf | 26 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: 2232887Amendletter_signed (1).pdf | 26 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: 1597275171-17-03-2020 03-13-19 Drawing 1.pdf | 26 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: 1597275171-17-03-2020 03-13-19 Drawing 2.pdf | 26 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: 1597275171-17-03-2020 03-13-19 Drawing 3.pdf | 26 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: 1597275171-17-03-2020 03-13-19 Drawing 3.pdf | 26 Mar 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: 2246607_FurtherCC_signed.pdf | 26 Mar 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 18022020.pdf | 18 Feb 2020 |
| Certificates of CA (Form 3)File: Form 3 final 2020 NEW.pdf | 24 Jan 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 final.pdf | 24 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: 2218189_FurtherCC UPTO 12TH FL.pdf | 18 Jul 2019 |
| Form 2AFile: Tendulkar associates-Rera quarterly cert.pdf | 18 Jul 2019 |
| Proforma of Allotment letterFile: SHREE PRASANNA AGREEMENT FOR SALE.pdf | 22 Mar 2019 |
| Proforma of Allotment letterFile: Allotment letter RERA.pdf | 22 Mar 2019 |
| Copy of the legal title reportFile: 321 tital report New.pdf | 5 Dec 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 061118.pdf | 6 Nov 2018 |
| Certificates of CA (Form 3)File: RERA C A CERTIFICATE FORM 3.pdf | 6 Nov 2018 |
| Certificates of CA (Form 5)File: RERA FORM 5-ilovepdf-compressed.pdf | 6 Nov 2018 |
| Layout approvalFile: amended plans.pdf | 24 May 2018 |
| Layout approvalFile: EB_369_GN_AR_VOL_3_0070.pdf | 24 May 2018 |
| Building plan approvalFile: iod letter2.pdf | 24 May 2018 |
| Building plan approvalFile: iod plan.pdf | 24 May 2018 |
| Layout approvalFile: amended plans letter.pdf | 24 May 2018 |
| Layout approvalFile: amended plans.pdf | 24 May 2018 |
| Layout approvalFile: EB_369_GN_AR_VOL_3_0069.pdf | 24 May 2018 |
| Copy of the legal title reportFile: TITLE REPORT SHREE PRASANNA.pdf | 24 May 2018 |
| Details of encumbrancesFile: NO encumbrances.pdf | 24 May 2018 |
| Copy of Layout Approval (in case of layout)File: amended plans letter.pdf | 24 May 2018 |
| Copy of Layout Approval (in case of layout)File: amended plans.pdf | 24 May 2018 |
| Copy of Layout Approval (in case of layout)File: EB_369_GN_AR_VOL_3_0069.pdf | 24 May 2018 |
| Copy of Layout Approval (in case of layout)File: EB_369_GN_AR_VOL_3_0070.pdf | 24 May 2018 |
| Copy of Layout Approval (in case of layout)File: amended plans.pdf | 24 May 2018 |
| Building Plan Approval (IOD)File: iod letter2.pdf | 24 May 2018 |
| Building Plan Approval (IOD)File: iod plan.pdf | 24 May 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: c c full.pdf | 24 May 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 24 May 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A D SHINTRE.pdf | 24 May 2018 |
| Certificates of CA (Form 3)File: Form3.pdf | 24 May 2018 |
| Proforma of Allotment letterFile: letter of allotment2.pdf | 24 May 2018 |
| PAN CardFile: patnership pancard.pdf | 21 May 2018 |
| Declaration in FORM BFile: b form.pdf | 21 May 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 58 filed documents as one ZIP, foldered, with a manifest
Keep SHRI PRASANNA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DADAR WEST780+ in Mumbai City
Kohinoor Square Phase 1
Kohinoor CTNL Infrastructure Company Priva
Sigma Garnet
COLO COLOR PRIVATE LIMITED
PALETTE
SURAJ ESTATE DEVELOPERS LTD
Eon One
Firstlight Properties Private Limited
Ratan Address
Shri Nakoda Enterprises
Promesa West End
M/s. virtue Enterprises
See every Mumbai City project, with the district possession charts
Builder: TENDULKAR & ASSOCIATES
TENDULKAR & ASSOCIATES has 1 registration on MahaRERA, including SHRI PRASANNA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What are my rights if SHRI PRASANNA is delayed beyond 1 Apr 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHRI PRASANNA?
The registered promoter entity is TENDULKAR & ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHRI PRASANNA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHRI PRASANNA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SHRI PRASANNA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHRI PRASANNA?
The professionals named in the filing: Architect: MUKTANAND & ASSOCIATES; Engineer: A D SHINTRE CONSULTANTS; Chartered Accountant: K P KAPADIA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHRI PRASANNA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback