Completed No litigation declared Others project

SHREEVENKATESH PARK

By SWAMI CONSTRUCTIONS

RG-MH-13371 · RERA P51600025353 · Last updated on MahaRERA portal: 7 Nov 2024

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Sep 2023Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

SHREEVENKATESH PARK is a Others project by SWAMI CONSTRUCTIONS in Nashik, Maharashtra, registered with MahaRERA as P51600025353 on 30 Apr 2020. The registration is recorded completed; possession was promised by 30 Sep 2023.

At a glance

Project

  • NameSHREEVENKATESH PARK
  • TypeOthers
  • Location
    • B/H ASHOKA SCHOOL
    • NR. AYYAPPA TEMPLE
    • KHODE NAGAR
    • NASHIK
    • Nashik (M Corp.)
    • Nashik
    • 422011
  • Pincode422011
  • RERA no.P51600025353
  • ReraGenie IDRG-MH-13371

Builder

  • NameSWAMI CONSTRUCTIONS
  • Entity typeOthers
  • Named personSWAMI CONSTRUCTIONS
  • Other registrations6 more →
  • Completed6 of 7
  • Declared earlier projects6 →

Key dates

this monthRegisteredApr 2020PromisedSep 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on30 Apr 2020
  • Promised completion30 Sep 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREEVENKATESH PARKNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SHREEVENKATESH PARK: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 7 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed48

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots48
Closed/Covered42
Open Space6

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,894 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3633.37
Proposed, not sanctioned3,633 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch8-9 SUYOJIT SANKUL, TILAKADI RD CANADA CORNER NASHIK 422002

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUMESH BAGUL
EngineerSAGAR S SHAH
Chartered AccountantPRASHANT PATHAK & ASSOCIATES
PartnerRole in project
SWAMI CONSTRUCTIONS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600017662Sep 2023 → Mar 2024

Reason as filed by the promoterThe Project is completed in all respect from Promoter and the procedure is initiated for obtaining Building Completion Certificate from Competent/Planning Authority NMC Nashik, But the same is taking time to grant the BCC before 30/09/2023.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Mar 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Mar 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Apr 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Jan 2024

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 ShreeVenkatesh Park.PDF7 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE SHREEVENKATESH PARK_240112_161602.pdf12 Jan 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4- Architect Certificate.pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: venkatesh form 2.pdf3 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Venkatesh Form 3 - Reduce.pdf3 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.PDF20 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.PDF20 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf27 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ShreeVenkatesh Park.PDF21 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ShreeVenkatesh park.PDF21 Jul 2023
Disclosure of sold/ booked inventoryFile: SHREEVENKATESH PARK.PDF21 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SheeVenkatesh Park.PDF20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed - Venkatesh.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Venkatesh park.pdf19 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Venkatesh.PDF19 Apr 2023
Disclosure of sold/ booked inventoryFile: sold unsold ShreeVenkatesh.PDF19 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shree Venkatesh Park-CA Certificate.pdf28 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Venkatesh park.pdf17 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.PDF17 Jan 2023
Disclosure of sold/ booked inventoryFile: BOOKED INVENTORY.PDF17 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SHREE VENKATESH PARK.pdf20 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Shree Venkatesh.pdf30 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SHREE VENKATESHFINAL.pdf20 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Annexure D-CA Certificate Q4.pdf24 May 2022
Disclosure of sold/ booked inventoryFile: SHREEVENKATESH.PDF7 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SHREEVENKATESH.PDF7 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SHREEVENKATESH.PDF7 Jan 2022
Disclosure of sold/ booked inventoryFile: SHREEVENKATESH.PDF7 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shree Venkatesh.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 SHREE VENKATESH.pdf31 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SHREEVENKATESH PARK.PDF9 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SHREEVENKATESH PARK.PDF9 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shree Venkatesh FINAL.pdf7 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf15 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SHREEVENKATESH PARK.PDF13 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SHREEVENKATRSH APRIL.PDF13 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SHREEVENKATESH JULY.PDF13 Aug 2021
Disclosure of sold/ booked inventoryFile: shreevenkatesh.PDF16 Jul 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventor venkatesh.PDF19 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SHREEVENKATESH PARK.PDF10 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 with UDIN.pdf14 Jan 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5- Shree Venkatesh 2019-20.pdf10 Jan 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SHREEVENKATESH PARK.PDF10 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: N A Order.PDF24 Apr 2020
Commencement Certificates / NA Order for plotted developmentFile: Commercial NA Order.pdf24 Apr 2020
Layout approvalFile: lay out plan.pdf19 Mar 2020
Layout approvalFile: Lay Out letter.PDF19 Mar 2020
Building plan approvalFile: Building plan 1.pdf19 Mar 2020
Building plan approvalFile: Building plan 2.pdf19 Mar 2020
Copy of the legal title reportFile: TITALE CERTFICATE.pdf19 Mar 2020
Details of encumbrancesFile: SELF DECLARATION.PDF19 Mar 2020
Copy of Layout Approval (in case of layout)File: lay out plan.pdf19 Mar 2020
Copy of Layout Approval (in case of layout)File: Lay Out letter.PDF19 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Building plan 1.pdf19 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Building plan 2.pdf19 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf19 Mar 2020
Declaration in FORM BFile: FORM B Affidavit.pdf19 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cartificate.PDF19 Mar 2020
Proforma of Allotment letterFile: AGREEMENT DRAFT.pdf19 Mar 2020
PAN CardFile: Pan card.PDF18 Mar 2020

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise2 delivered late1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SHREENEELKANTH APARTMENTP51600045701RAJIV NAGAR, Nashik36Jun 2022OngoingMar 2025Not delivered
SHREEMAULI PARKAt OPP Potdar School Tapovan Road Uttara Nagar Nashik 1118-CompletedOct 2021Jun 2021
SHREENAVSHAKTI APARTMENTNavshakti Chowk opp Dr Homi Bhabha Garden Bhabha Nagar Nashik 42200216-CompletedSep 2021Late, Oct 2021
SHREEVISHWABH TIRUPATTI PETROL PUMP NR METRO MALL OPP. SAIBABA MANDIR RTO COLONY BOTHALE NAGAR NASHIK1-CompletedDec 2020Jul 2020
SHREESANKALP APARTMENTOOP LIC COLONY NR GURU GOVIND SINGH COLLEGE INDIRA NAGAR NASHIK-0940-CompletedMar 2015Late, Dec 2015

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREEVENKATESH PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NR. AYYAPPA TEMPLE, KHODE NAGAR ,NASHIK4,100+ in Nashik

Builder: SWAMI CONSTRUCTIONS

SWAMI CONSTRUCTIONS has 7 registrations on MahaRERA, including SHREEVISHWA and SHREENAVSHAKTI APARTMENT. Its filings disclose 6 earlier MahaRERA projects: declares 3 of 5 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SHREEVENKATESH PARK is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREEVENKATESH PARK?

The registered promoter entity is SWAMI CONSTRUCTIONS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREEVENKATESH PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREEVENKATESH PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREEVENKATESH PARK?

The professionals named in the filing: Architect: UMESH BAGUL; Engineer: SAGAR S SHAH; Chartered Accountant: PRASHANT PATHAK & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREEVENKATESH PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREEVENKATESH PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREEVENKATESH PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.