ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / Shree Vighnaharan Luxuria

Registered No litigation declared Residential / Group Housing project

Shree Vighnaharan Luxuria

By SHREE DATTALAXMI BUILDERS AND DEVELOPERS

RG-MH-54546 · RERA P51600049885 · Last updated on MahaRERA portal: 7 Mar 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Feb 2027Possession promisedno revision filed
4 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 70%
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

Shree Vighnaharan Luxuria is a Residential / Group Housing project by SHREE DATTALAXMI BUILDERS AND DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600049885 on 6 Mar 2023. Possession is promised by 21 Feb 2027.

At a glance

Project

  • NameShree Vighnaharan Luxuria
  • TypeResidential / Group Housing
  • Location
    • Ashoka Marg
    • Wadala Shiwar
    • Nashik
    • 422011
  • Pincode422011
  • RERA no.P51600049885
  • ReraGenie IDRG-MH-54546

Builder

  • NameSHREE DATTALAXMI BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersVIJAY BHASKARRAO BHATAMBAREKAR, Deepashri Jayant Bhatambrekar, ANAND SANJAY BHATAMBREKAR, SANJAY BHASKARRAO BHATAMBAREKAR

Key dates

this monthRegisteredMar 2023PromisedFeb 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Mar 2023
  • Promised completion21 Feb 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Apartment BNA70000
Apartment CNA70000
Apartment ANA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 70%.

Apartment B27%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Apartment C25%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Apartment A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed191

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots191
Closed/Covered191
BuildingClosed/CoveredTotal
Apartment B112112
Apartment C4040
Apartment A3939

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,800 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6462.19
Proposed, not sanctioned6,462 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJehan Circle, Gangapur Road

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay Mhalas
EngineerDeepak Kulkarni
Chartered AccountantHimesh J Patel
PartnerRole in project
SHREE DATTALAXMI BUILDERS AND DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 21 Feb 2027

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Bhatambarekar_-_form_5_2024.pdf7 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 QUARTER 1 - 2024.pdf22 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 QUARTER 2 - 2024.pdf22 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 QUARTER 2 - 2024_compressed.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1st qtr engineer cert.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2nd qtr engineer cert.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3rd qtr engineer cert.pdf22 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bhatambarekar - rera, form 3, q1.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bhatambarekar - rera, form 3, q2.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bhatambatrekar - rera - form 3, q3_compressed.pdf1 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FINAL.pdf10 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf3 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHREE VIGHNHARAN LUXURIA-Cert-3-signed.pdf3 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect_certificate.pdf3 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers_certificate.pdf3 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_RERA_CERTIFICATE.pdf3 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf20 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AYE ENGINEERS.pdf20 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA CERTIFICATE.pdf20 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf4 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AYE ENGINEERS.pdf4 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA CERTIFICATE.pdf4 Nov 2023
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBANCES FINANCIAL- PROJECT.pdf30 Jan 2023
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBANCES FINANCIAL- PROJECT.pdf30 Jan 2023
Declaration about Commencement CertificateFile: DETAILS COMMENCEMENT CERTIFICATE.pdf30 Jan 2023
CERSAI detailsFile: DETAILS OF cersai- PROJECT.pdf30 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PROJECT (1).pdf30 Jan 2023
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBANCES legal- apt b.pdf18 Jan 2023
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBANCES legal.pdf18 Jan 2023
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBANCES legal- apt b.pdf18 Jan 2023
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBANCES legal.pdf18 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Apartment C DECLARATION interest disc.pdf18 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Apartment B DECLARATION interest discl.pdf2 Jan 2023
Details of encumbrances concerned to FinanceFile: SDL Declaration of encumbrances Apartment B.pdf10 Dec 2022
Details of encumbrances concerned to FinanceFile: SDL Declaration of encumbrances Apartment C.pdf10 Dec 2022
Details of encumbrances concerned to LegalFile: SDL Declaration of encumbrances Apartment B.pdf10 Dec 2022
Details of encumbrances concerned to LegalFile: SDL Declaration of encumbrances Apartment C.pdf10 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SVL Bank Details.pdf24 Nov 2022
Deviation Report with respect to Allotment letterFile: SVL Apartment B DEVIATION PROFORMA.pdf24 Nov 2022
Deviation Report with respect to Allotment letterFile: SVL Apartment C DEVIATION PROFORMA.pdf24 Nov 2022
Deviation Report with respect to model copy of AgreementFile: Shree Vighnaharan Luxuria Agreement Deviation form.pdf24 Nov 2022
Building plan approvalFile: Shree Vighnaharan Luxuria Building Plan_compressed-1.pdf21 Nov 2022
Building plan approvalFile: Shree Vighnaharan Luxuria Building Plan_compressed-2.pdf21 Nov 2022
Building plan approvalFile: Shree Vighnaharan Luxuria Building Plan_compressed-3.pdf21 Nov 2022
Layout approvalFile: land layout.pdf21 Nov 2022
PAN CardFile: pan.pdf21 Nov 2022
Copy of the legal title reportFile: Shree Vighnaharan Luxuria Legal Title Report .pdf21 Nov 2022
Copy of Layout Approval (in case of layout)File: land layout.pdf21 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Shree Vighnaharan Luxuria Building Plan_compressed-1.pdf21 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Shree Vighnaharan Luxuria Building Plan_compressed-2.pdf21 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Shree Vighnaharan Luxuria Building Plan_compressed-3.pdf21 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: wadala 27 Commencement Certificate.pdf21 Nov 2022
Declaration in FORM BFile: FORM B APPT B_compressed.pdf21 Nov 2022
Declaration in FORM BFile: FORM B APPT C.pdf21 Nov 2022
Proforma of Allotment letterFile: SDL Allottment Letter Proforma Apartment B.pdf21 Nov 2022
Proforma of Allotment letterFile: SDL Allottment Letter Proforma Apartment C.pdf21 Nov 2022
Proforma of Agreement for saleFile: Proforma Agreement for Sale.pdf21 Nov 2022

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shree Vighnaharan Luxuria on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wadala Shiwar4,100+ in Nashik

Builder: SHREE DATTALAXMI BUILDERS AND DEVELOPERS

SHREE DATTALAXMI BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including Shree Vighnaharan Luxuria. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if Shree Vighnaharan Luxuria is delayed beyond 21 Feb 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shree Vighnaharan Luxuria?

The registered promoter entity is SHREE DATTALAXMI BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shree Vighnaharan Luxuria?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shree Vighnaharan Luxuria?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shree Vighnaharan Luxuria?

The professionals named in the filing: Architect: Sanjay Mhalas; Engineer: Deepak Kulkarni; Chartered Accountant: Himesh J Patel. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Vighnaharan Luxuria?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Vighnaharan Luxuria. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Vighnaharan Luxuria to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.