Shree Sai Hills Phase II
RG-MH-20261 · RERA P52100004895 · Last updated on MahaRERA portal: 16 Oct 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 4 complaints at MahaRERA
- Completion date moved by 54 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shree Sai Hills Phase II is a Residential / Group Housing project by Shree Sai Hills in Pune, Maharashtra, registered with MahaRERA as P52100004895 on 9 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 54 months from the original filing. 7 of the 144 units on this registration are recorded sold or booked, and 3 of 22 construction stages are filed complete. 4 complaints are on record with the regulator.
At a glance
Project
- NameShree Sai Hills Phase II
- TypeResidential / Group Housing
- Location
- Nagar Raod
- Kesnand
- Haveli
- Pune
- 412207
- Pincode412207
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100004895
- ReraGenie IDRG-MH-20261
Builder
- NameShree Sai Hills
- Entity typePartnership
- PartnerJayashree Mohan Gaikwad
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2021)
- Buildings2 building records
- Documents filed181 files
Current status
Figures as on 16 Oct 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D | NA | 12 | 12 | 96 | 0 | 96 |
| E | NA | 6 | 6 | 48 | 0 | 48 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 16 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 65%.
D37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 65% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 16 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed108
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| D | 29 | 25 | 54 |
| E | 29 | 25 | 54 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 30.08 cr | Rs 9.13 cr |
| D | NA | Rs 19.52 cr | Rs 8.33 cr |
| E | NA | Rs 9.76 cr | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Viinod Associates |
| Engineer | Sumit Shesherao Misale |
| Chartered Accountant | CA Amar & Company |
| Chartered Accountant | B.B. Awari & Co. |
| Partner | Role in project |
|---|---|
| Shree Sai Hills | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterOur project got delayed due to stoppage of work in lockdown of covid -19 pandemic, shortage of material and labour supply and price inflation and also due to correction in sanctioned layout plan and material non availability due to heavy rain. So we request you grant us relief in the form of extension of due date to complete the project by three year. Humbly request you to extend the completion date to 31/12/2025
Reason as filed by the promoterDue to covid 19 pendamic and lockdown, we were not able to get labour and material in time and this why we were not able to complete project within time.
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000064627 | Anosh Deodatta Gaikwad | Shree Sai Hills | 22/09/2020 |
| CC005000000064628 | Anugrah Gaikwad | Shree Sai Hills | 22/09/2020 |
| CC005000000064630 | Nagesh Lore | Shree Sai Hills | 22/09/2020 |
| CC12401125 | Parth Sampat Raykar | Shree Sai Hills | 14/12/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed181
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 181 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form1 Ar Certificate Sep17.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Sep-17.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Sep17.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sep17.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Dec17.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Dec-17.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Dec17.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec17.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Mar18.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Mar-18.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Mar18.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Mar18.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Jun18.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Jun-18.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Jun18.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Jun18.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Sep18.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Sep-18.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Sep18.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sep18.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Dec18.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Dec-18.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Dec18.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec18.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Mar19.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Mar-19.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Mar19.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Mar19.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Jun19.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Jun-19.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Jun19.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Jun19.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Sep19.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Sep-19.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Sep19.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sep19.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Dec19.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Dec-19.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Dec19.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec19.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Mar20.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Mar-20.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Mar20.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Mar20.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Jun20.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Jun-20.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Jun20.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Jun20.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sep20.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Sep20.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Sep-20.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Sep20.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Dec20.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Dec-20.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Dec20.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec20.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Mar21.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Mar-21.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Mar21.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Mar21.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Jun21.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Jun-21.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Jun21.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Jun21.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Sep21.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Sep-21.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Sep21.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sep21.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec21.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Dec21.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Dec-21.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Dec21.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Mar22.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Mar-22.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Mar22.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Mar22.pdf | 16 Oct 2025 |
| Form 1File: Form1 Ar Certificate Jun22.pdf | 16 Oct 2025 |
| Form 2File: ER Form 2 Jun-22.pdf | 16 Oct 2025 |
| Form 3File: Form 3 CA Certificate Jun22_compressed.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Jun22.pdf | 16 Oct 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 181 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Shree Sai Hills Phase II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kesnand13,700+ in Pune
Filed coordinates, straight-line distance. 42 registered projects within 2 km.
Yashwin Enchante Phase 2
Vilas Javdekar Infinitee Developers Pvt. L
Godrej Greens
DREAM WORLD LANDMARKS LLP
Yashwin Enchante Phase 1
Vilas Javdekar Infinitee Developers Pvt. L
Kohinoor Kaleido
Intofinity Promoters Private Limited
VIJAY VIHAR
COL. RPS RAWAT
FLAMANTE BY VTP LUXE PHASE 1
INTEGRATED BUSINESS ECOSYSTEM PRIVATE LIMI
Builder: Shree Sai Hills
Shree Sai Hills has 2 registrations on MahaRERA, including Shree Sai Hills Phase I and Shree Sai Hills Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Shree Sai Hills Phase II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Shree Sai Hills Phase II is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shree Sai Hills Phase II?
The registered promoter entity is Shree Sai Hills, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shree Sai Hills Phase II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Shree Sai Hills Phase II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Shree Sai Hills Phase II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shree Sai Hills Phase II?
The professionals named in the filing: Architect: Viinod Associates; Engineer: Sumit Shesherao Misale; Chartered Accountant: CA Amar & Company; Chartered Accountant: B.B. Awari & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shree Sai Hills Phase II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback