Home / Browse projects / Mumbai City, Maharashtra / Shree Sai Baba

Registration lapsed No litigation declared Others project

Shree Sai Baba

By Shree Saiganesh Constructions

RG-MH-57549 · RERA P51900015093 · Last updated on MahaRERA portal: 13 Apr 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 35 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 24 documents Report an error

Shree Sai Baba is a Others project by Shree Saiganesh Constructions in Mumbai City, Maharashtra, registered with MahaRERA as P51900015093 on 24 Jan 2018. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 35 months from the original filing.

At a glance

Project

  • NameShree Sai Baba
  • TypeOthers
  • Location
    • D.S. Babrekar Marg
    • Shivaji park
    • GNorth-400028
    • Ward GNorth
    • Mumbai City
    • 400028
  • Pincode400028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900015093
  • ReraGenie IDRG-MH-57549

Builder

  • NameShree Saiganesh Constructions
  • Entity typeOthers
  • Named personKaushik Narayan More
  • Declared earlier projects1 →

Key dates

22 months past promisethis monthRegisteredJan 2018First promiseJan 2022Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Jan 2018
  • Promised completion30 Dec 2024
  • Revised completionRevised to 30 Dec 2024 (originally 1 Jan 2022)
  • Buildings1 building record
  • Documents filed24 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
shree sai babaNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Apr 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

shree sai baba: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 13 Apr 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Staircase Lifts and Lift LobyYes0%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered12

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area185 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI855.0
Proposed, not sanctioned774 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGokhale Road, Dadar

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchvision Architects
EngineerKelkar Designs Pvt Ltd Madhura Manjrekar
PartnerRole in project
Shree Saiganesh Constructions-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900011745Jan 2022 → Dec 2024

Reason as filed by the promoterI/We the Promoters of the Project name Shree Sai Baba registered under project registration no P51900015093. We are thankful to the MahaRERA Authority for giving a one-year extension because of Covid 19 to our project which was valid till 1st January 2022. We request you to give an extension for our project for three years that is till 30th December 2024.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Dec 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Dec 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Dec 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed24

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: declaration 1 compressed.pdf13 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate 2019 - 2020.pdf13 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate 2021- 2022.pdf13 Apr 2022
Disclosure of sold/ booked inventoryFile: discloser of sold2 compressed.pdf13 Apr 2022
CERSAI detailsFile: CERSAI REPORT SAI BABA.pdf13 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 2019-20 Certficate.pdf13 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FY 2020-21Certificate.pdf13 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5.pdf14 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5.pdf14 Jan 2020
OtherFile: RERA Complience Letter.pdf29 Jul 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf21 Sep 2018
Certificates of CA (Form 3)File: Form-3 CA Certificate.pdf16 Jan 2018
Details of encumbrancesFile: RERA Encumbrances Letter.pdf9 Jan 2018
OtherFile: RERA PAN Letter.pdf9 Jan 2018
Declaration in FORM BFile: Form B RERA.pdf3 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engg Certificate.pdf3 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf2 Jan 2018
Layout approvalFile: Amended plan IOD.pdf28 Dec 2017
Copy of the legal title reportFile: Title Report.pdf28 Dec 2017
Copy of Layout Approval (in case of layout)File: Amended plan IOD.pdf28 Dec 2017
Proforma of Allotment letterFile: Letter for MAHARERA.pdf28 Dec 2017
Building plan approvalFile: Amended plan IOD.pdf23 Dec 2017
PAN CardFile: PAN Card.pdf23 Dec 2017
Building Plan Approval (IOD)File: Amended plan IOD.pdf23 Dec 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Saloni BuildingPlot No 816 TPS IV MAHIM DIVISION off Gokhale Road dadar mumbai 40002815CompletedApr 2013Apr 2013

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 35 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shree Sai Baba on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shivaji park780+ in Mumbai City

2 kmShree Sai BabaCompleted 88Lapsed / revoked 70Other 105Dot size: filed unitsN

Filed coordinates, straight-line distance. 263 registered projects within 2 km.

Builder: Shree Saiganesh Constructions

Shree Saiganesh Constructions has 1 registration on MahaRERA, including Shree Sai Baba. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that Shree Sai Baba shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shree Sai Baba is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shree Sai Baba?

The registered promoter entity is Shree Saiganesh Constructions, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shree Sai Baba?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shree Sai Baba?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shree Sai Baba?

The professionals named in the filing: Architect: Archvision Architects; Engineer: Kelkar Designs Pvt Ltd Madhura Manjrekar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Sai Baba?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Sai Baba. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Sai Baba to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.