Home / Browse projects / Thane, Maharashtra / Shree Ganraj Residency

Registered No litigation declared Others project

Shree Ganraj Residency

By OM SAI CONSTRUCTION

RG-MH-17567 · RERA P51700054872 · Last updated on MahaRERA portal: 9 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 75%
5 of 14Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

Shree Ganraj Residency is a Others project by OM SAI CONSTRUCTION in Thane, Maharashtra, registered with MahaRERA as P51700054872 on 15 Feb 2024. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 9 of the 14 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameShree Ganraj Residency
  • TypeOthers
  • Location
    • Badlapur
    • Village Kulgaon
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700054872
  • ReraGenie IDRG-MH-17567

Builder

  • NameOM SAI CONSTRUCTION
  • Entity typePartnership
  • PartnersKrupashankar Ramkishor Pal, Sanjeev Rajaram Pal, Reeta Krupashankar Pal
  • Other registrations14 more →
  • Completed3 of 15
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects13 →

Key dates

this monthRegisteredFeb 2024First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Feb 2024
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed58 files

Current status

64%9 of 14 units booked
69.1%Work done, per cost certificate

Figures as on 9 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shree Ganraj ResidencyNA4410414

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 75%.

Shree Ganraj Residency: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Open Space15

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area298 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Jul 2025

Approvals and building plan

Sanctioning authorityKulgaon Badlapur Municipal Council
Permissible FSI534.56
Proposed, not sanctioned535 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 1 2 3 and 4 Shelar House Ground Floor Pipeline Road Sanewadi Badlapur 421503
Estimated costRs 2.55 cr
Cost incurredRs 1.76 cr
Work done69.12%
BuildingWingEstimatedIncurred
Shree Ganraj ResidencyNARs 2.35 crRs 1.76 cr
-NARs 20.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArti V Jamgaonkar
EngineerDarshan A Kasture
Chartered AccountantJeetu A Ramrakhiyani
Chartered AccountantDaksha Jeetu Ramrakhiyani
PartnerRole in project
OM SAI CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30122519140Dec 2025 → Dec 2026

Reason as filed by the promoterThere were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate.pdf9 May 2026
Withdrawal Update Form 2File: Engineer Certificate.pdf9 May 2026
Withdrawal Update Form 3File: Form 3.pdf9 May 2026
Withdrawal Update Form 1File: Form 1_Shree Ganraj_Dec25.pdf11 Feb 2026
Withdrawal Update Form 2File: Form 2_Shree Ganraj_Dec25.pdf11 Feb 2026
Withdrawal Update Form 3File: Form-3 Shree Ganraj_Dec25.pdf11 Feb 2026
Form 2A (FY 2023-2024)File: Form 2A as on 31 March 2024.pdf11 Feb 2026
Form 2A (FY 2024-2025)File: Form 2A as on 31 March 2025.pdf11 Feb 2026
Form 5 (FY 2023-2024)File: Form-5.pdf7 Feb 2026
Withdrawal Update Form 1File: Arch Certificate of SGR Sept 25.pdf12 Dec 2025
Withdrawal Update Form 2File: Form 3 of Shree Ganraj.pdf12 Dec 2025
Withdrawal Update Form 3File: Form 3 of Ganraj.pdf12 Dec 2025
Form 5 (FY 2024-2025)File: Signed Form 5_OSC.pdf30 Sep 2025
Form 1File: Architect's Certificate of Shree Ganraj.pdf28 Jul 2025
Form 2File: Engineer's Certificate of shree Ganraj.pdf28 Jul 2025
Form 3File: Form 3 of shree ganraj.pdf28 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory Shree Ganraj Residency June 25.pdf28 Jul 2025
Form 1File: Arch Certi OSC SGR June 24.pdf21 May 2025
Form 2File: Eng Certi OSC SGR June 24.pdf21 May 2025
Form 3File: Form 3 OSC SGR June.pdf21 May 2025
Form 1File: Arch Certi OSC SGR Sept 24.pdf21 May 2025
Form 2File: Eng Certi OSC SGR Sept 24.pdf21 May 2025
Form 3File: Form 3 Certi OSC SGR Sept 24_compressed.pdf21 May 2025
Form 1File: Arch Certi OSC SGR Dec 24.pdf21 May 2025
Form 2File: Eng Certi OSC SGR Dec 24.pdf21 May 2025
Form 3File: Form 3 Certi OSC SGR Dec 24.pdf21 May 2025
Form 1File: Arch Certi OSC SGR Dec 24.pdf21 May 2025
Form 2File: Eng Certi OSC SGR Dec 24.pdf21 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certi OSC SGR June 24.pdf12 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certi OSC SGR Sept 24.pdf12 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certi OSC SGR Dec 24.pdf12 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 OSC SGR June.pdf12 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certi OSC SGR Sept 24_compressed.pdf12 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certi OSC SGR Dec 24 - converted.pdf12 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certi OSC SGR June 24.pdf12 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certi OSC SGR Sept 24.pdf12 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certi OSC SGR Jan 25.pdf12 May 2025
Other - TechnicalFile: Letter of CC on Confirmation mail_Om Sai.pdf9 Feb 2024
Proforma of Agreement for saleFile: Draft of Agreement of Sale.pdf3 Feb 2024
Layout approvalFile: Building Plan_Om Sai.pdf25 Jan 2024
Copy of Layout Approval (in case of layout)File: Building Plan_Om Sai.pdf25 Jan 2024
CERSAI detailsFile: CERSAI CERTIFICATE_Om Sai.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf25 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration About Separate bank account - OM SAI CONSTRUCTION.pdf25 Jan 2024
Other - LegalFile: Annexure A Declaration cum Undertaking_Om Sai.pdf25 Jan 2024
Copy of the legal title reportFile: Legal Title Report and Search Report_Om Sai.pdf23 Jan 2024
Building plan approvalFile: Building Plan_Om Sai.pdf22 Jan 2024
PAN CardFile: PAN Card of Partnership Firm.pdf22 Jan 2024
Details of encumbrances concerned to FinanceFile: No Emcumbrance Om sai.pdf22 Jan 2024
Details of encumbrances concerned to LegalFile: No Emcumbrance Om sai.pdf22 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plan_Om Sai.pdf22 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_Om Sai.pdf22 Jan 2024
Declaration about Commencement CertificateFile: Declaration of CC_Om Sai.pdf22 Jan 2024
Declaration in FORM BFile: Form B_ Om Sai.pdf22 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organasation.pdf22 Jan 2024
Proforma of Allotment letterFile: Allotment Letter_Om Sai.pdf22 Jan 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment Letter_Om sai.pdf22 Jan 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement_Om Sai.pdf22 Jan 2024

How this compares with Thane

64%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shree Ganraj Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Village Kulgaon7,600+ in Thane

2 kmShree Ganraj ResidencyCompleted 205Lapsed / revoked 77Other 123Dot size: filed unitsN

Filed coordinates, straight-line distance. 405 registered projects within 2 km.

Builder: OM SAI CONSTRUCTION

OM SAI CONSTRUCTION has 15 registrations on MahaRERA, including SAI SAMRUDDHI and SAI SUMIRAN APARTMENT. Its filings disclose 13 earlier MahaRERA projects: declares 10 of 13 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Shree Ganraj Residency is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shree Ganraj Residency?

The registered promoter entity is OM SAI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shree Ganraj Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shree Ganraj Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shree Ganraj Residency?

The professionals named in the filing: Architect: Arti V Jamgaonkar; Engineer: Darshan A Kasture; Chartered Accountant: Jeetu A Ramrakhiyani; Chartered Accountant: Daksha Jeetu Ramrakhiyani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Ganraj Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Ganraj Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Ganraj Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.