Home / Browse projects / Nashik, Maharashtra / SHREE GANESH BLISS
SHREE GANESH BLISS
RG-MH-87265 · RERA P51600015415 · Last updated on MahaRERA portal: 19 May 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 10 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREE GANESH BLISS is a Others project by PRAKASH RAMAN CHAUDHARI in Nashik, Maharashtra, registered with MahaRERA as P51600015415 on 23 Feb 2018. The registration is recorded completed; possession was promised by 17 Feb 2022.
At a glance
Project
- NameSHREE GANESH BLISS
- TypeOthers
- Location
- DREAM CITI - TAPOVAN LINK ROAD
- UTTARA NAGAR
- Nashik (M Corp.)
- Nashik
- 422011
- Pincode422011
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600015415
- ReraGenie IDRG-MH-87265
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on23 Feb 2018
- Promised completion17 Feb 2022
- Revised completionNone
- Buildings1 building record
- Documents filed39 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREE GANESH BLISS | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 19 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
SHREE GANESH BLISS: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 19 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed23
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SOHAM AES |
| Engineer | RAJENDRA B CHOPDA |
| Partner | Role in project |
|---|---|
| PRAKASH RAMAN CHAUDHARI | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Feb 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Feb 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Feb 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Feb 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 21 Jul 2021
Documents filed39
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate FY 17 18.pdf | 19 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate FY 18 19.pdf | 19 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate FY 19 20.pdf | 19 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Oct 20.pdf | 19 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer Certificate FY 17 18.pdf | 17 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer Certificate FY 18 19.pdf | 17 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer Certificate FY 19 20.pdf | 17 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Engineer Certificate Oct 20.pdf | 17 May 2023 |
| Certificates of CA (Form 3)File: CA Certificate_SG Bliss 17-18.pdf | 16 May 2023 |
| Certificates of CA (Form 3)File: CA Certificate_SG Bliss 18-19.pdf | 16 May 2023 |
| Certificates of CA (Form 3)File: CA Certificate_SG Bliss 19-20.pdf | 16 May 2023 |
| Certificates of CA (Form 3)File: A Certificate_SG Bliss 20-21 Till OC.pdf | 16 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Prakash Chaudhary (Form 5) 2018-19.pdf | 15 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Prakash Chaudhary (Form 5) 2019-20.pdf | 15 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Prakash Chaudhary (Form 5)2020-21.pdf | 15 May 2023 |
| Declaration about Commencement CertificateFile: Form D S G Bliss.pdf | 6 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold S G Bliss.pdf | 6 Feb 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: completition certificate.pdf | 21 Jul 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Shree Ganesh Bliss Apartment Declaration Index II.pdf | 13 Nov 2020 |
| Status of ConveyanceFile: Shree Ganesh Bliss Apartment Declaration Index II.pdf | 13 Nov 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: SG Bliss Form4 Completion Certificate.pdf | 10 Nov 2020 |
| Certificates of CA (Form 5)File: Shree Ganesh Bliss.pdf | 15 Oct 2018 |
| Building plan approvalFile: BP SG Bliss 1-2.pdf | 21 Feb 2018 |
| Building plan approvalFile: BP SG Bliss 2-2.pdf | 21 Feb 2018 |
| Layout approvalFile: Layout Plan.pdf | 21 Feb 2018 |
| PAN CardFile: PAN Card - PRC.pdf | 21 Feb 2018 |
| Copy of the legal title reportFile: Title Report.pdf | 21 Feb 2018 |
| Details of encumbrancesFile: Affidavit.pdf | 21 Feb 2018 |
| Copy of Layout Approval (in case of layout)File: Layout Plan.pdf | 21 Feb 2018 |
| Building Plan Approval (IOD)File: BP SG Bliss 1-2.pdf | 21 Feb 2018 |
| Building Plan Approval (IOD)File: BP SG Bliss 2-2.pdf | 21 Feb 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate SG Bliss.pdf | 21 Feb 2018 |
| Declaration in FORM BFile: Form B.pdf | 21 Feb 2018 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 21 Feb 2018 |
| Proforma of Allotment letterFile: Draft Allotment Letter.pdf | 21 Feb 2018 |
| Proforma of Allotment letterFile: Draft Agreement of sale.pdf | 21 Feb 2018 |
| OtherFile: 7 12 extract.pdf | 21 Feb 2018 |
| OtherFile: N A ORDER.pdf | 21 Feb 2018 |
| OtherFile: Layout order.pdf | 21 Feb 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 10 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 39 filed documents as one ZIP, foldered, with a manifest
Keep SHREE GANESH BLISS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near UTTARA NAGAR4,100+ in Nashik
Filed coordinates, straight-line distance. 144 registered projects within 2 km.
Anandvan Housing Complex
Ravi Mahajan Buildcon LLP
SHREEJI INFINIA
SHREEJI LIFE SPACE
Waterways
Sanklecha Construction Private Limited
Shreejis Gujral Arcade
SHREEJI LIFE SPACE
VRAJ METROPOLIS SOUTH
SHREE INFRA SPACE
ALEEF BREEZE APARTMENT
KHATIB BUILDERS AND DEVELOPERS
See every Nashik project, with the district possession charts
Builder: PRAKASH RAMAN CHAUDHARI
PRAKASH RAMAN CHAUDHARI has 11 registrations on MahaRERA, including SHREE GANESH IMPERIAL and GENESIS. Its filings disclose 9 earlier MahaRERA projects: declares 8 of 8 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if SHREE GANESH BLISS is delayed beyond 17 Feb 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREE GANESH BLISS?
The registered promoter entity is PRAKASH RAMAN CHAUDHARI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREE GANESH BLISS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREE GANESH BLISS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREE GANESH BLISS?
The professionals named in the filing: Architect: SOHAM AES; Engineer: RAJENDRA B CHOPDA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREE GANESH BLISS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback