Home / Browse projects / Mumbai Suburban, Maharashtra / SHRADDHA PRIVA
SHRADDHA PRIVA
By Shree Mangesh Constructions
RG-MH-37204 · RERA P51800048242 · Last updated on MahaRERA portal: 30 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 15 months
- 3 extensions taken
- Rs 45.00 crore secured on the land, in favour of Aditya Birla Finance Limited
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHRADDHA PRIVA is a Residential / Group Housing project by Shree Mangesh Constructions in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800048242 on 19 Dec 2022. Possession is promised by 30 Nov 2026. The completion date has moved by 15 months from the original filing. 59 of the 89 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameSHRADDHA PRIVA
- TypeResidential / Group Housing
- Location
- CTS NO 791 / 791/1
- MULUND WEST
- MULUND WEST
- Kurla
- Mumbai Suburban
- 400080
- Pincode400080
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800048242
- ReraGenie IDRG-MH-37204
Builder
- NameShree Mangesh Constructions
- Entity typePartnership
- PartnersSUDHIR BALU MEHTA, AJAY MADHUKAR NAYAK
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Dec 2022
- Promised completion30 Nov 2026
- Revised completionRevised to 30 Nov 2026 (originally 2 Aug 2025)
- Buildings1 building record
- Documents filed142 files
Current status
Figures as on 30 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHRADDHA PRIVA | NA | 22 | 21 | 71 | 18 | 89 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
SHRADDHA PRIVA: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed65
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership9
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Janki Raghunath Patil | Mulund | Mumbai Suburban |
| Arun Raghunath Patil | Mulund | Mumbai Suburban |
| Ashok Raghunath Patil | Mulund | Mumbai Suburban |
| Nandu Raghunath Patil | Mulund | Mumbai Suburban |
| Dilip Raghunath Patil | Mulund | Mumbai Suburban |
| Vinod Raghunath Patil | Mulund | Mumbai Suburban |
| Asha Narendra Patil | Mulund | Mumbai Suburban |
| Neeta Narendra Patil | Mulund | Mumbai Suburban |
| Shashikala K Keny | Mulund | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHRADDHA PRIVA | NA | Rs 38.00 cr | Rs 38.00 cr |
| - | NA | Rs 2.00 cr | Rs 85.70 lakh |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vijay Damodar Turbadkar |
| Engineer | S K Consultants & Engineers |
| Engineer | SHREE MANGESH CONSTRUCTIONS |
| Engineer | RAJENDRA BANKAR |
| Chartered Accountant | CA Rutuja Narsingh & Associates |
| Chartered Accountant | M s. Pratiksha Tulshyan & Associates |
| Chartered Accountant | N B Sayed & Associates |
| Partner | Role in project |
|---|---|
| Shree Mangesh Constructions | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 02-11-2025. to complete the project and fulfil all regulatory requirements.
Reason as filed by the promoterThe project is substantially completed, with all major construction activities finished. Only minor finishing works such as final touch-ups, common area detailing, testing/commissioning of services, and statutory compliances remain. The extension is sought solely to complete these residual works and to obtain the OC, ensuring full compliance with statutory requirements and delivering the project in a proper and compliant manner to allottees. The extension is requested to complete residual works and obtain the OC in compliance with statutory requirements.Hence we are requesting for an extension
Reason as filed by the promoterWe, Shree Mangesh Constructions, hereby declare the following with respect to the project Shraddha Priva bearing registration number P51800048242 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 27/01/2026 and we have also initiated the process for the possession as well. However, there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, total c
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Apr 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Apr 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Nov 2026
Documents filed142
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 142 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Shraddha Priva as on June 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - Shraddha Priva as on June 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - Shraddha Priva as on June 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: Form 1- Architect Certificate.pdf | 29 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 29 Jul 2026 |
| Withdrawal Update Form 3File: Form 3- CA Certificate.pdf | 29 Jul 2026 |
| Form 2A (FY 2023-2024)File: Form 2A_FY_2023-24.pdf | 13 Jul 2026 |
| Form 2A (FY 2022-2023)File: Form 2A_FY_2022-23.pdf | 13 Jul 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A- FY 24-25 SHRADDHA PRIVA.pdf | 18 Jun 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A- FY 25-26 SHRADDHA PRIVA.pdf | 18 Jun 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - Shraddha Priva for FY 2024-25.pdf | 5 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Shraddha Priva as on March 2026.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Shraddha Priva as on March 2026.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Shraddha Priva as on March 2026.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Shraddha Priva as on Dec 2025.pdf | 28 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 - Shraddha Priva as on Dec 2025.pdf | 28 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Shraddha Priva as on Dec 2025.pdf | 28 Jan 2026 |
| Withdrawal Update Form 1File: Form 1- Shraddha Priva as on Sep 2025.pdf | 15 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - Shraddha Priva as on Sep 2025.pdf | 15 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - Shraddha Priva as on Sep 2025.pdf | 15 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Shraddha Priva as on March 2025.pdf | 8 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 8 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shraddha Priva as on 31-03-2025.pdf | 20 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 14 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shraddha Priva as on March 2025.pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 20 Apr 2025 |
| Details of encumbrances concerned to FinanceFile: SMC.pdf | 8 Apr 2025 |
| Details of encumbrances concerned to LegalFile: SMC.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (Dec 2024).pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shraddha Priva as on Dec 2024_compressed.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shraddha Priva as on Dec 2024.pdf | 6 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29_removed.pdf | 6 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SHRADDHA PRIVA Sep 2024.pdf | 19 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shraddha Priva as on 30-09-2024.pdf | 19 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sept 2024.pdf | 19 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Shraddha Priva for FY 2023-24.pdf | 19 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29 - Sept 2024.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SHRADDHA PRIVA Sep 2024.pdf | 19 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sept 2024.pdf | 19 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shraddha Priva as on 30-09-2024.pdf | 19 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29 - Sept 2024.pdf | 19 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Shraddha Priva for FY 2023-24.pdf | 19 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shraddha Priva as on June 2024_11zon.pdf | 18 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shraddha Priva as on June 2024_11zon.pdf | 18 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Shraddha Priva for FY 2023-24.pdf | 29 Oct 2024 |
| Declaration about Commencement CertificateFile: FORMAT D.pdf | 23 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Janki niketan FCC 22102024.pdf | 22 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shraddha Priva as on 30-09-2024.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shraddha Priva as on 30-09-2024.pdf | 20 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SHRADDHA PRIVA Sep 2024.pdf | 16 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Shraddha Priva for FY 2023-24.pdf | 9 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCE ON PROJECT SMC (2) (1).pdf | 8 Oct 2024 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCE ON PROJECT SMC (2) (1).pdf | 8 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Shraddha Priva as on June 2024.pdf | 14 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shraddha Priva as on June 2024.pdf | 14 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 23-24.pdf | 14 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 22-23.pdf | 14 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29.pdf | 14 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shraddha Priva as on June 2024_11zon.pdf | 14 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022-23_organized.pdf | 14 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shraddha Priva as on June 2024.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shraddha Priva as on June 2024.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Shraddha Priva as on June 2024.pdf | 16 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shraddha Priva as on March 2024.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shraddha Priva as on March 2024.pdf | 20 Apr 2024 |
| Layout approvalFile: Janki Niketan Amended IOD 1.pdf | 4 Apr 2024 |
| Building plan approvalFile: Janki Niketan Amended IOD 2.pdf | 4 Apr 2024 |
| Building plan approvalFile: Janki Niketan Amended IOD 3.pdf | 4 Apr 2024 |
| Building plan approvalFile: Janki Niketan Amended IOD 4.pdf | 4 Apr 2024 |
| Building plan approvalFile: Janki Niketan Amended IOD 5.pdf | 4 Apr 2024 |
| Building plan approvalFile: Janki Niketan Amended IOD 6.pdf | 4 Apr 2024 |
| Copy of Layout Approval (in case of layout)File: Janki Niketan Amended IOD 1.pdf | 4 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Janki Niketan Amended IOD 2.pdf | 4 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Janki Niketan Amended IOD 3.pdf | 4 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Janki Niketan Amended IOD 4.pdf | 4 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Janki Niketan Amended IOD 5.pdf | 4 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Janki Niketan Amended IOD 6.pdf | 4 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: SHRADDHA PRIVA.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shraddha Priva as on Dec 2023.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shraddha Priva as on 31-12-2023.pdf | 20 Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 142 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHRADDHA PRIVA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MULUND WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 336 registered projects within 2 km.
Eternia Towers A to D
Oberoi Constructions Limited
Bellanza Phase 1 - Wing A, B, C at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Atmosphere O2
Atmosphere Realty Pvt Ltd
Bellanza Phase 2 - Wing D, E, F at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Forest Hills Ph 1 at The Prestige City
PRESTIGE MULUND REALTY PRIVATE LIMITED
Kalpataru Elitus
Arimas Real Estate Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: Shree Mangesh Constructions
Shree Mangesh Constructions has 1 registration on MahaRERA, including SHRADDHA PRIVA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if SHRADDHA PRIVA is delayed beyond 30 Nov 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHRADDHA PRIVA?
The registered promoter entity is Shree Mangesh Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHRADDHA PRIVA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHRADDHA PRIVA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHRADDHA PRIVA?
The professionals named in the filing: Architect: Vijay Damodar Turbadkar; Engineer: S K Consultants & Engineers; Engineer: SHREE MANGESH CONSTRUCTIONS; Engineer: RAJENDRA BANKAR; Chartered Accountant: CA Rutuja Narsingh & Associates; Chartered Accountant: M s. Pratiksha Tulshyan & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHRADDHA PRIVA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback