Home / Browse projects / Mumbai Suburban, Maharashtra / Shivam

Registration lapsed No litigation declared Residential / Group Housing project

Shivam

By Pooja Developers

RG-MH-10884 · RERA P51800008097 · Last updated on MahaRERA portal: 8 Oct 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 25 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 48 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2024Possession promised25 months past this date
17 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 97%
3 of 81Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

Shivam is a Residential / Group Housing project by Pooja Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008097 on 18 Aug 2017. Possession was promised by 30 Sep 2024 and is now 25 months past that date. The completion date has moved by 48 months from the original filing. 78 of the 81 units on this registration are recorded sold or booked, and 17 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameShivam
  • TypeResidential / Group Housing
  • Location
    • shiv sai lane
    • pimple saudagar
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008097
  • ReraGenie IDRG-MH-10884

Builder

  • NamePooja Developers
  • Entity typePartnership
  • GSTIN27AAIFP5595M1ZE
  • PartnersSachanand K Galani, Mohit S Galani, Sukhlal Kishinchand Galani, Tarun Tulsidas Rupela, Vikas Sadoromal Galani
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

25 months past promisethis monthRegisteredAug 2017First promiseSep 2020Revised toSep 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion30 Sep 2024
  • Revised completionRevised to 30 Sep 2024 (originally 30 Sep 2020)
  • Buildings2 building records
  • Documents filed88 files

Current status

96%78 of 81 units booked
100.0%Work done, per cost certificate

Figures as on 8 Oct 2024, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building FNA13038038
Building ENA13043043

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 97%.

Building F100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building E90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises94%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.53%

Progress on shared amenities15

As on 8 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingYes0%
Community BuildingsYes60%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed78

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots78
Closed/Covered78
BuildingClosed/CoveredTotal
Building F3939
Building E3939

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area12,400 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Sep 2024

Approvals and building plan

Permissible FSI7394.6
Proposed, not sanctioned5,764 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch285, Koregaon Park, Pune 411001
Estimated costRs 98.40 cr
Cost incurredRs 98.40 cr
Work done100.0%
BuildingWingEstimatedIncurred
Building FNARs 32.80 crRs 32.80 cr
Building ENARs 32.80 crRs 32.80 cr
-NARs 32.80 crRs 32.80 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLaxman Thite
ArchitectMilind Patil
EngineerStrudcom Consultants Pvt Ltd
EngineerJayant Indamdar
EngineerSachanand Galani
Chartered AccountantDHARINI NASWA
Chartered AccountantSANJAYKUMAR SHAH
PartnerRole in project
Pooja Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008765Sep 2020 → Sep 2021

Reason as filed by the promoterOur Ongoing Project Shivam consists of 2 Buildings E & F. We have obtained Completion Certificate for Building F on 21/02/2018. However, constriction work for Bldg E is pending for Environment Clearance Certificate. We have already applied for the said permission to concerned authorities. After getting Environment Clearance Certificate, we would require approximately one years’ time to complete the said Building E.

EXT51800011636Sep 2020 → Sep 2023

Reason as filed by the promoterOur Ongoing Project Shivam consists of 2 Buildings E & F consisting total 65 allottees (Tower F 38 and Tower E 27). We have obtained Completion Certificate for Building F on 21/02/2018 and 38 units have been handed over to respective allotees. However, constriction work for Tower E is pending for Environment Clearance Certificate. We have already received provisional permission by concerned authorities and submitted bank guarantee to them for the said process. We would require approximately one years’ time to complete the said Tower E consisting 43 units of which 27 are already allotted.

EXT51800017872Sep 2020 → Sep 2024

Reason as filed by the promoterF wing is completed and possession handed over in 2018 so F wing 38 units are deemed consent provided and E wing 31 units consent is obtained out of 38 sold units accounting for total 69 units consent out of 76 sold units. We have prepared for completion check list as per our Governing authority i.e. Pimpri Chinchwad Municipal Corporation, and it might take about 120 to 150 days for Pimpri Chinchwad Municipal Corporation to issue the completion certificate after due diligence, hence we request you to accept our extension plea to complete legal formalities.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000195258SANGEETA MUNDRAPOOJA DEVELOPERS16/12/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jul 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Oct 2024

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 Building E.pdf8 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate Building F - 21 Feb 2018.pdf8 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate Building E 2024.pdf8 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 Building E.pdf8 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate Building F - 21 Feb 2018.pdf8 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate Building E 2024.pdf8 Oct 2024
Form 5 (FY 2018-2019)File: Form 5 Mar2019.pdf16 Sep 2024
Form 5 (FY 2019-2020)16 Sep 2024
Form 5 (FY 2020-2021)16 Sep 2024
Form 5 (FY 2021-2022)16 Sep 2024
Form 5 (FY 2022-2023)16 Sep 2024
Form 5 (FY 2017-2018)File: Form 5 Mar2018.pdf14 Sep 2024
Disclosure of sold/ booked inventoryFile: RERA SOLD UNSOLD UNITS SEP 2023.pdf2 Nov 2023
Certificates of CA (Form 3)File: CA - FORM 3 - SEP 23 -- revised.pdf2 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA ARCHITECT - FORM 1 - Mar 2022.pdf28 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA ARCHITECT - FORM 1 - Dec 2022.pdf28 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA ARCHITECT - FORM 1 - Jun 2023.pdf28 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA ARCHITECT - FORM 1 - Sep 2023.pdf28 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificates (Form 2) Jun 2022.pdf27 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificates (Form 2) Dec 2022.pdf27 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificates (Form 2) Mar 2023.pdf27 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificates (Form 2) Jun 2023.pdf27 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificates (Form 2) Sep 2023.pdf27 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Rera Quality Assurance Certificate - 2023.pdf27 Oct 2023
CERSAI detailsFile: CERSAI 2023.pdf27 Oct 2023
CERSAI detailsFile: CERSAI Declaration 2023.pdf27 Oct 2023
Disclosure of sold/ booked inventoryFile: RERA SOLD UNSOLD UNITS SEP 2023.pdf27 Oct 2023
Certificates of CA (Form 3)File: Certificates of CA (Form 3) Mar 2022.pdf27 Oct 2023
Certificates of CA (Form 3)File: CA FORM 3 APR - JUN 22.pdf27 Oct 2023
Certificates of CA (Form 3)File: CA FORM 3 JUL - SEP 22.pdf27 Oct 2023
Certificates of CA (Form 3)File: CA FORM 3 OCT - DEC 22.pdf27 Oct 2023
Certificates of CA (Form 3)File: CA FORM 3 JAN - MAR 23.pdf27 Oct 2023
Certificates of CA (Form 3)File: CA FORM 3 APR - JUN 23.pdf27 Oct 2023
Certificates of CA (Form 3)File: CA FORM 3 JUL - SEP 23.pdf27 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Rera Quality Assurance Certificate - 2023.pdf26 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ANNUAL AUDIT - FORM 5 - FY 21-22.pdf26 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ANNUAL AUDIT - FORM 5 - FY 22-23.pdf26 Oct 2023
OtherFile: ECLSEIAA_193116_5488F8_SIA_MH_MIS_237889_2021_.pdf27 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: RERA Form 5 CA Annual Report Mar 2018.pdf13 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA Form 5 CA Annual Report Mar 2019.pdf13 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Form 5 CA Annual Report Mar 2020.pdf13 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Form 5 CA Annual Report Mar 2021.pdf13 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: RERA Quality Assurance Certificate 2020.pdf25 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RERA Quality Assurance Certificate 2021.pdf25 Apr 2022
Disclosure of sold/ booked inventoryFile: RERA Disclosure of Sold and Booked Units.pdf25 Apr 2022
Declaration about Commencement CertificateFile: RERA Declaration for Commencement.pdf21 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PD RERA Arc Crt 18-19 upload.pdf21 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PD RERA Arc Crt 19-20 upload.pdf21 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PD RERA Arc Crt 20-21 upload.pdf21 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_200235479925_For_Asset_Based_Search_20_04_2022_16_19_21_178.pdf21 Apr 2022
CERSAI detailsFile: RERA CERSAI Declaration Letter.pdf21 Apr 2022
CERSAI detailsFile: RERA CERSAI Declaration.pdf21 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPELETION CERTIFICATE BLDG C D F .pdf21 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 18-19 UPLOAD.pdf19 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 19-20 UPLOAD.pdf19 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 20-21 UPLOAD.pdf19 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 18-19.pdf19 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 19-20.pdf19 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 20-21.pdf19 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MAR 18 UPLOAD.pdf19 Apr 2022
Certificates of CA (Form 3)File: RERA CERTIFIACTE signed_compressed.pdf19 Apr 2022
Certificates of CA (Form 3)File: RERA 19-20.pdf19 Apr 2022
Certificates of CA (Form 3)File: RERA signed.pdf19 Apr 2022
Certificates of CA (Form 3)File: RERA 20-21.pdf19 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 SIGNED.pdf19 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf19 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf19 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf19 Apr 2022
Layout approvalFile: Revised Layout Plan.pdf6 Jul 2018
Copy of Layout Approval (in case of layout)File: Revised Layout Plan.pdf6 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CommencementFeb18.pdf6 Jul 2018
Certificates of CA (Form 3)File: Pooja F.pdf30 Jul 2017
Certificates of CA (Form 3)File: Pooja E.pdf30 Jul 2017
OtherFile: Completion ABCD.pdf29 Jul 2017
Proforma of Allotment letterFile: Rera_FP_for_Shivam_2017.pdf27 Jul 2017
Proforma of Allotment letterFile: FINAL_Allotment_letter.pdf27 Jul 2017
Layout approvalFile: Layout PLAN (SHIVAM).pdf25 Jul 2017
Building plan approvalFile: Layout PLAN (SHIVAM).pdf25 Jul 2017
PAN CardFile: Pooja PANCARD.pdf25 Jul 2017
Copy of the legal title reportFile: Search Report.pdf25 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHIVAM Bldg A B C DS No 185 Hissa No 4b 6a 5 part Pimple Saudagar PCMC Pune104CompletedMar 2009Mar 2009

How this compares with Mumbai Suburban

96%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shivam on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near pimple saudagar6,700+ in Mumbai Suburban

Builder: Pooja Developers

POOJA DEVELOPERS has 3 registrations on MahaRERA, including POOJA HEAVAN PARK and Shivam. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Shivam shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shivam is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shivam?

The registered promoter entity is Pooja Developers, a partnership as per the filing. Its GSTIN 27AAIFP5595M1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shivam?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Shivam?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Shivam?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shivam?

The professionals named in the filing: Architect: Laxman Thite; Architect: Milind Patil; Engineer: Strudcom Consultants Pvt Ltd; Engineer: Jayant Indamdar; Engineer: Sachanand Galani; Chartered Accountant: DHARINI NASWA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shivam?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shivam. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shivam to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.