Shiva Residency
RG-MH-53536 · RERA P52100035062 · Last updated on MahaRERA portal: 27 May 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 7 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shiva Residency is a Residential / Group Housing project by DEEPALI SHIVAJI RAJGURAV in Near Yamai Mandir Dighi, 411015, registered with MahaRERA as P52100035062 on 4 May 2022. The registration is recorded completed; possession was promised by 30 May 2025. The completion date has moved by 7 months from the original filing.
At a glance
Project
- NameShiva Residency
- TypeResidential / Group Housing
- Location
- Lane No 1 Sai Park
- Near Yamai Mandir Dighi
- 411015
- Pincode411015
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100035062
- ReraGenie IDRG-MH-53536
Builder
- NameDEEPALI SHIVAJI RAJGURAV
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on4 May 2022
- Promised completion30 May 2025
- Revised completionRevised to 30 May 2025 (originally 31 Oct 2024)
- Buildings1 building record
- Documents filed55 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHIVA RESIDENCY | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 80%.
SHIVA RESIDENCY: 89% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 27 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| DEEPALI SHIVAJI RAJGURAV | Talegaon Dabhade (M Cl) | Pune |
| Balkrishna Ramchandra Gurav | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shubham Bhalerao |
| Engineer | Ajinkya Malkar |
| Chartered Accountant | R G Joshi and Co |
| Partner | Role in project |
|---|---|
| DEEPALI SHIVAJI RAJGURAV | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe would like to provide detailed reasons and clarification regarding the delay in the project and the necessity for an extension. Reason for Delay: The delay is primarily due to a shortage of funds, which temporarily impacted the progress of the project. Pending Work: The only remaining tasks are the installation of the lift and completion certificate (CC) processing. Work Completed: 95% of the project has been successfully completed. Balance Work: 5% of the project remains to be completed. The remaining work is planned to be completed within the proposed extension period, with the revised de
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Apr 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Apr 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 21 May 2025
Documents filed55
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 3File: Form - 3 Q4-2024 shivay.pdf | 27 May 2025 |
| Occupational CertificateFile: Occupancy Certificate.PDF | 26 May 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4.pdf | 21 May 2025 |
| Other - TechnicalFile: PCMC MAIL ROHAN SIR.pdf | 18 May 2025 |
| Occupational CertificateFile: Form 4.pdf | 14 May 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: completion certificate.pdf | 24 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: complition dighi SHIVA RESIDENCY.pdf | 16 Jan 2025 |
| Declaration in FORM BFile: 0001.pdf | 25 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 ARCT 1 Q 1 23-24 OK-scan.pdf | 25 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 ARCT 1 Q2 23-24 OK-scan.pdf | 25 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 April to June 24 SHIVA.pdf | 25 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Jul 24 sep 24 SHIVA.pdf | 25 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Start to dec 23 SHIVA.pdf | 25 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 (Start to Dec 2023)_compressed.pdf | 25 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 jan-march 24 SHIVA.pdf | 25 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2 FORM 2 SHIVA JULY TO SEP.pdf | 25 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 1 FORM 2 SHIVA APRIL TO JUNE.pdf | 25 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD BOOK Q 3.pdf | 25 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGG Annexure C form 2A 23 24-1-scan (1).pdf | 25 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 ca SHIVA.pdf | 25 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificates q1 APRIL - JUNE 22.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificates q2 JULY - SEPTEMBER 22.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificates q3 OCTOBER - DECEMBER 22.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificates q4 JANUARY - MARCH 23.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificates q1 APRIL - JUNE 23.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificates q2 JULY - SEPTEMBER 23.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificates q3 OCTOBER - DECEMBER 23.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificates q4 JANUARY - MARCH 24.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer Certificates q2 JULY - SEPTEMBER 23.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer Certificates q4 JANUARY - MARCH 24.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer Certificates q3 OCTOBER - DECEMBER 23.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer Certificates q1 APRIL - JUNE 23.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer Certificates q4 JANUARY - MARCH -23.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer Certificates q3 OCTOBER - DECEMBER 22.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer Certificates q2 JULY-SEPTEMBER 22.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer Certificates Q1 APRIL - JUNE 22.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate_1.pdf | 23 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality cert engg rera form 2a 2023_1.pdf | 23 Mar 2024 |
| Proforma of Allotment letterFile: Allotment sheet.pdf | 6 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiva Estate_Form 3_New (1).pdf | 30 Apr 2022 |
| Layout approvalFile: BLUEPRINT.pdf | 18 Apr 2022 |
| Building plan approvalFile: BLUEPRINT.pdf | 18 Apr 2022 |
| PAN CardFile: DEEPALI PAN.pdf | 18 Apr 2022 |
| Copy of the legal title reportFile: Title Search Report.pdf | 18 Apr 2022 |
| Details of encumbrancesFile: Shiva Estates_Declaration of NoEncumbrances.pdf | 18 Apr 2022 |
| Copy of Layout Approval (in case of layout)File: BLUEPRINT.pdf | 18 Apr 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BLUEPRINT.pdf | 18 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Letter.pdf | 18 Apr 2022 |
| Declaration about Commencement CertificateFile: Shiva Estates_Form D.pdf | 18 Apr 2022 |
| Declaration in FORM BFile: Shiva Estates_Form B.pdf | 18 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect cert.pdf | 18 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf | 18 Apr 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200235271040_For_Asset_Based_Search_17_04_2022_19_39_38_966.pdf | 18 Apr 2022 |
| Proforma of Allotment letterFile: Shiva Estates_Allotment Letter.pdf | 18 Apr 2022 |
| Proforma of Allotment letterFile: AGREEMENT TO SALE SAMPLE FORMAT.pdf | 18 Apr 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 55 filed documents as one ZIP, foldered, with a manifest
Keep Shiva Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Yamai Mandir Dighi
Filed coordinates, straight-line distance. 47 registered projects within 2 km.
Kohinoor Viva Pixel- Phase II
RISING ASSOCIATES
VIVACITY
REALCON LANDMARKS LLP
TRIAA VASANTAM CITY CENTER PHASE 1
Triaa Realtors LLP
QUE 101 PHASE I
ANNR Unique Realty LLP
NYATI ERA I
NYATI CONSTRUCTION PRIVATE LIMITED
ONE ARETHA PHASE 1
Triaa Landmarks LLP
Builder: DEEPALI SHIVAJI RAJGURAV
DEEPALI SHIVAJI RAJGURAV has 1 registration on MahaRERA, including Shiva Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What are my rights if Shiva Residency is delayed beyond 30 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shiva Residency?
The registered promoter entity is DEEPALI SHIVAJI RAJGURAV, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shiva Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Shiva Residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shiva Residency?
The professionals named in the filing: Architect: Shubham Bhalerao; Engineer: Ajinkya Malkar; Chartered Accountant: R G Joshi and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shiva Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback