Home / Browse projects / Nashik, Maharashtra / SHIV SANJIVANI LANDMARK
SHIV SANJIVANI LANDMARK
By SHIV SANJIVANI BUILDERS and DEVELOPERS
RG-MH-15604 · RERA P51600045790 · Last updated on MahaRERA portal: 5 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 6 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHIV SANJIVANI LANDMARK is a Others project by SHIV SANJIVANI BUILDERS and DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600045790 on 9 Jun 2022. Possession was promised by 30 Apr 2026 and is now 6 months past that date.
At a glance
Project
- NameSHIV SANJIVANI LANDMARK
- TypeOthers
- Location
- TRIMBAK ROAD
- MAUJE SATPUR SHIWAR
- Nashik (M Corp.)
- Nashik
- 422013
- Pincode422013
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600045790
- ReraGenie IDRG-MH-15604
Builder
- NameSHIV SANJIVANI BUILDERS and DEVELOPERS
- Entity typePartnership
- PartnerGOKUL SUBHASH AHER
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Jun 2022
- Promised completion30 Apr 2026
- Revised completionNone
- Buildings1 building record
- Documents filed71 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHIV SANJIVANI LANDMARK | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 5 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
SHIV SANJIVANI LANDMARK: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 5 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| LIFT | Yes | 100% |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAVI AMRUTKAR |
| Engineer | RAVI AMRUTKAR |
| Engineer | B P BHAVSAR |
| Chartered Accountant | MILIND MODAK and CO |
| Partner | Role in project |
|---|---|
| SHIV SANJIVANI BUILDERS and DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 5 May 2025
Documents filed71
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1 10_01_2023.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1 09_10_2022.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1_Q10_10_01_2025.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1_Q9_10_10_2024.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1_Q8_12_07_2024.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1_Q7_13_04_2024.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark form 1_Q6_10_01_2024.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1_Q5_11_10_2023.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1_Q4_11_07_2023.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1_Q3_09_04_2023.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1_Q2_10_01_2023.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Sanjivani Landmark Form 1_Q1_09_10_2022.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3_Q2_OND_22 31_12_2022.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3_Q10_OND_24 31_12_2024.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3_Q9_JAS_24 30_09_2024.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3_Q8_AMJ_24 30_06_2024.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3_Q7_JFM_24 31_03_2024.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3_Q6_OND_23 31_12_23.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3_Q5_JAS_23 30_09_2023.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3_Q4_AMJ_23 30_06_2023.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3_Q3_JFM_23 31_03_23.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3_Q1_JAS_22 30_09_2022.pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv Sanjivani Landmark Form 2_Q3_11_04_2023.pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv Sanjivani Landmark Form 2_Q9_14_10_2024.pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv Sanjivani Landmark Form 2_Q8_14_07_2024.pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv Sanjivani Landmark Form 2_Q7_15_04_2024.pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv Sanjivani Landmark Form 2_Q6_13_01_2024.pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv Sanjivani Landmark Form 2_Q4_15_07_2023.pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv Sanjivani Landmark Form 2_Q2_15_01_2023.pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv Sanjivani Landmark Form 2 _Q1_12_10_2022.pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv Sanjivani Landmark Form 2_Q5_15_10_2023.pdf | 5 May 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Shiv Sanjivani Landmark Form 4 10_01_2025.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: Shiv Sanjivani Landmark Disclosure Q7_05_01_2024.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: Shiv Sanjivani Landmark Disclosure Q11_11_01_2025.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: Shiv Sanjivani Landmark Disclosure Q9_25_07_2024.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: Shiv Sanjivani Landmark Disclosure Q8_15_04_2024.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: Shiv Sanjivani Landmark Disclosure Q6_15_10_2023.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: Shiv Sanjivani Landmark Disclosure Q5_09_07_2023.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: Shiv Sanjivani Landmark Disclosure Q4_16_04_2023.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: Shiv Sanjivani Landmark Disclosure Q3_06_01_2023.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: Shiv Sanjivani Landmark Disclosure Q2_26_10_2022.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: Shiv Sanjivani Landmark Disclosure Q1_26_04_2022.pdf | 5 May 2025 |
| Other - TechnicalFile: Shiv Sanjivani Landmark Form 4 10_01_2025.pdf | 5 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Shiv Sanjivani Landmark Form 5_FY1 2022-23.pdf | 5 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shiv Sanjivani Landmark Form 5_FY1 2022-23.pdf | 5 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Shiv Sanjivani Landmark Form 5_FY2 2023-24.pdf | 5 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Shiv Sanjivani Landmark Form 5_FY3 2024-25.pdf | 5 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shiv Sanjivani Landmark Form 5_FY2 2023-24.pdf | 5 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shiv Sanjivani Landmark Form 5_FY3 2024-25.pdf | 5 May 2025 |
| Status of ConveyanceFile: Shiv Sanjivani Landmark Declairation of Apt P to 12.pdf | 20 Jan 2025 |
| Status of ConveyanceFile: Shiv Sanjivani Landmark Declairation of Apt 13 to 27.pdf | 20 Jan 2025 |
| Status of ConveyanceFile: Shiv Sanjivani Landmark Declairation of Apt 28 to 42.pdf | 20 Jan 2025 |
| Status of ConveyanceFile: Shiv Sanjivani Landmark Declairation of Apt 43 to 56 end.pdf | 20 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Shiv Sanjivani Landmark Completion Certificate 28102024.pdf | 20 Jan 2025 |
| Layout approvalFile: Shiv Sanjivani Landmark Layout 18052022.pdf | 26 May 2022 |
| Building plan approvalFile: Shiv Sanjivani Landmark IOD 1.pdf | 26 May 2022 |
| Building plan approvalFile: Shiv Sanjivani Landmark IOD 2.pdf | 26 May 2022 |
| PAN CardFile: Shiv Sanjivani Builders and Developers Firm PAN Card 14052022.pdf | 26 May 2022 |
| Copy of the legal title reportFile: Shiv Sanjivani Landmark Receipt N Format A 14052022.pdf | 26 May 2022 |
| Copy of the legal title reportFile: Shiv Sanjivani Landmark Receipt N Title Report 14052022.pdf | 26 May 2022 |
| Details of encumbrancesFile: Shiv Sanjivani Landmark Self Declairation 14052022.pdf | 26 May 2022 |
| Copy of Layout Approval (in case of layout)File: Shiv Sanjivani Landmark Layout 18052022.pdf | 26 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Shiv Sanjivani Landmark IOD 1.pdf | 26 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Shiv Sanjivani Landmark IOD 2.pdf | 26 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Shiv Sanjivani Landmark Commencement Certificate 18052022.pdf | 26 May 2022 |
| Declaration about Commencement CertificateFile: Shiv Sanjivani Landmark Format D 14052022.pdf | 26 May 2022 |
| Declaration in FORM BFile: Shiv Sanjivani Landmark Form B 14052022.pdf | 26 May 2022 |
| CERSAI detailsFile: Shiv Sanjivani Landmark cersai_search_report_200237564616_for_asset_based_search_18_05_202 | 26 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shiv Sanjivani Landmark Form 3 19052022.pdf | 26 May 2022 |
| Proforma of Allotment letterFile: Shiv Sanjivani Landmark Allottment Letter 14052022.pdf | 26 May 2022 |
| Proforma of Allotment letterFile: Shiv Sanjivani Landmark Agreement To Sale Draft 14052022.pdf | 26 May 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 71 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SHIV SANJIVANI LANDMARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MAUJE SATPUR SHIWAR4,100+ in Nashik
Filed coordinates, straight-line distance. 55 registered projects within 2 km.
Samraat AmOzon
M/S Shweta Infrastructure & Housing (I) Pv
ELYSIAN
ROONGTA HOMES LLP
HAPPY LIFE AT APNA GHAR PHASE III
M/S Shweta Infrastructure & Housing (I) Pv
SKY53
SKY53
ROONGTA ROSEWOOD APARTMENT
SHREE TIRUMALA BUILDCON
ROONGTA EMINENCE APARTMENT
SHREE TIRUMALA BUILDCON
See every Nashik project, with the district possession charts
Builder: SHIV SANJIVANI BUILDERS and DEVELOPERS
SHIV SANJIVANI BUILDERS and DEVELOPERS has 1 registration on MahaRERA, including SHIV SANJIVANI LANDMARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What does it mean that SHIV SANJIVANI LANDMARK shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHIV SANJIVANI LANDMARK is delayed beyond 30 Apr 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHIV SANJIVANI LANDMARK?
The registered promoter entity is SHIV SANJIVANI BUILDERS and DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHIV SANJIVANI LANDMARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHIV SANJIVANI LANDMARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHIV SANJIVANI LANDMARK?
The professionals named in the filing: Architect: RAVI AMRUTKAR; Engineer: RAVI AMRUTKAR; Engineer: B P BHAVSAR; Chartered Accountant: MILIND MODAK and CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHIV SANJIVANI LANDMARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.