Home / Browse projects / Pune, Maharashtra / SHIV PARK
SHIV PARK
RG-MH-36481 · RERA P52100015980 · Last updated on MahaRERA portal: 18 Nov 2024
Source: official MahaRERA filing
Red flags
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHIV PARK is a Residential / Group Housing project by TRIMURTI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100015980 on 10 Apr 2018. The registration is recorded completed; possession was promised by 29 Sep 2022. The completion date has moved by 6 months from the original filing.
At a glance
Project
- NameSHIV PARK
- TypeResidential / Group Housing
- Location
- NAGAR PUNE ROAD
- RADHESHWARI HOUSING CO-OPERATIVE SOCIETY
- WAGHOLI
- Haveli
- Pune
- 412207
- Pincode412207
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100015980
- ReraGenie IDRG-MH-36481
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on10 Apr 2018
- Promised completion29 Sep 2022
- Revised completionRevised to 29 Sep 2022 (originally 30 Mar 2022)
- Buildings1 building record
- Documents filed70 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHIV PARK | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
SHIV PARK: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities17
As on 18 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
| UPS Backup | Yes | 100% |
| Lift | Yes | 100% |
Parking filed10
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| TRIMURTI DEVELOPERS | Pune (M Corp.) | Pune |
| VINOD INDERLAL JESSANI | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GIRISH KARANDE |
| Engineer | Mr G A BHILARE |
| Partner | Role in project |
|---|---|
| TRIMURTI DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have revised the Plan and additional FSI of 314.50 sqm have been got Sanctioned the copy of which is attatched in Documents list of the said Project.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jun 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Mar 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 5 Aug 2024
Documents filed70
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: fORM 4.pdf | 18 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: fORM 4.pdf | 18 Nov 2024 |
| Proforma of Agreement for saleFile: Model form of Agreement as per RERA.pdf | 16 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 by Maharera.pdf | 16 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 by Maharera.pdf | 16 Nov 2024 |
| Proforma of Agreement for saleFile: Model form of Agreement as per RERA.pdf | 16 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: fORM 4.pdf | 11 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC -1 Shivpark_compressed.pdf | 5 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 26 Aug 2023 |
| Status of ConveyanceFile: Conveyance.pdf | 26 Aug 2023 |
| Declaration about Commencement CertificateFile: Declrn Commencement-.pdf | 24 Jul 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: CHS Certificate.pdf | 19 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A--upto March 2023.pdf | 30 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf | 30 Jun 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC -1 Shivpark.pdf | 30 Jun 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC For 2 Flats.pdf | 30 Jun 2023 |
| Other - TechnicalFile: Consent of Allottees.pdf | 30 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 13 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 13 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf | 13 May 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 13 May 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 13 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5.pdf | 13 May 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC for 46 flats.pdf | 13 May 2023 |
| Other - TechnicalFile: Declaration as per Cir 32.pdf | 13 May 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 10 May 2023 |
| Declaration about Commencement CertificateFile: dclaration of Commencement.pdf | 16 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance 2019-20.pdf | 16 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 16 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FormV2017-18.PDF | 16 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FormV2018-19.PDF | 16 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FormV2019-20.PDF | 16 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FormV2020-21.PDF | 16 Aug 2021 |
| OtherFile: As per Circular 28.pdf | 16 Aug 2021 |
| OtherFile: property card.pdf | 16 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 2.pdf | 19 Jul 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enggr Certificate.pdf | 19 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate 2.pdf | 19 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Discosure of Inventory.pdf | 16 Jul 2021 |
| Certificates of CA (Form 3)File: CA Certificate revised.pdf | 16 Jul 2021 |
| Copy of the legal title reportFile: title report Revised.pdf | 14 Jun 2021 |
| Building plan approvalFile: Revised Sanction Plan sheet 1.pdf | 16 Dec 2020 |
| Building plan approvalFile: Revised Sanction Plan sheet 2.pdf | 16 Dec 2020 |
| Building plan approvalFile: Revised Sanction Plan sheet 3.pdf | 16 Dec 2020 |
| Building Plan Approval (IOD)File: Revised Sanction Plan sheet 1.pdf | 16 Dec 2020 |
| Building Plan Approval (IOD)File: Revised Sanction Plan sheet 2.pdf | 16 Dec 2020 |
| Building Plan Approval (IOD)File: Revised Sanction Plan sheet 3.pdf | 16 Dec 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate.pdf | 16 Dec 2020 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 28 Mar 2018 |
| Declaration in FORM BFile: CO-Promoter Schedule B.pdf | 17 Mar 2018 |
| Proforma of Allotment letterFile: Agreement to Sale.pdf | 14 Mar 2018 |
| Details of encumbrancesFile: No Encumbrance Certificate.pdf | 10 Mar 2018 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 10 Mar 2018 |
| Layout approvalFile: Layout Plan-2.pdf | 9 Mar 2018 |
| Building plan approvalFile: Plan 1.pdf | 9 Mar 2018 |
| Building plan approvalFile: Plan 2.pdf | 9 Mar 2018 |
| Building plan approvalFile: Plan 3.pdf | 9 Mar 2018 |
| Layout approvalFile: layout plan.pdf | 9 Mar 2018 |
| Copy of the legal title reportFile: Title report.pdf | 9 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: layout plan.pdf | 9 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: Layout Plan-2.pdf | 9 Mar 2018 |
| Building Plan Approval (IOD)File: Plan 1.pdf | 9 Mar 2018 |
| Building Plan Approval (IOD)File: Plan 2.pdf | 9 Mar 2018 |
| Building Plan Approval (IOD)File: Plan 3.pdf | 9 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: comencemet letter.pdf | 9 Mar 2018 |
| OtherFile: Deed of Lease Assignment.pdf | 9 Mar 2018 |
| OtherFile: Irrevocable Genral Power of Attorney-min.pdf | 9 Mar 2018 |
| OtherFile: JV Agreement.pdf | 9 Mar 2018 |
| PAN CardFile: pan card.pdf | 8 Mar 2018 |
| Declaration in FORM BFile: Form B-min.pdf | 8 Mar 2018 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHIV HILLS | WAGHOLI PUNE | 24 | Completed | Apr 2016 | Late, Jul 2016 |
| SHIV GARDEN | WAGHOLI PUNE | 24 | Completed | Apr 2016 | Late, Nov 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 12 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 70 filed documents as one ZIP, foldered, with a manifest
Keep SHIV PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near RADHESHWARI HOUSING CO-OPERATIVE SOCIETY13,700+ in Pune
Filed coordinates, straight-line distance. 138 registered projects within 2 km.
Yashwin Enchante Phase 2
Vilas Javdekar Infinitee Developers Pvt. L
Godrej Greens
DREAM WORLD LANDMARKS LLP
Yashwin Enchante Phase 1
Vilas Javdekar Infinitee Developers Pvt. L
Kohinoor Kaleido
Intofinity Promoters Private Limited
VIJAY VIHAR
COL. RPS RAWAT
FLAMANTE BY VTP LUXE PHASE 1
INTEGRATED BUSINESS ECOSYSTEM PRIVATE LIMI
Builder: TRIMURTI DEVELOPERS
TRIMURTI DEVELOPERS has 13 registrations on MahaRERA, including SHAKUNTALA PARK and SHRI HARI ROW-BUNGLOWS. Its filings disclose 13 earlier MahaRERA projects: declares 7 of 12 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SHIV PARK is delayed beyond 29 Sep 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHIV PARK?
The registered promoter entity is TRIMURTI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHIV PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHIV PARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHIV PARK?
The professionals named in the filing: Architect: GIRISH KARANDE; Engineer: Mr G A BHILARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHIV PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback