Home / Browse projects / Aurangabad, Maharashtra / SHITAL NAGAR

Registered No litigation declared Residential / Group Housing project

SHITAL NAGAR

By SANJAY SHYAMLAL VYAS

RG-MH-03683 · RERA P51500048680 · Last updated on MahaRERA portal: 20 Jan 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
29 of 44Construction stages doneacross 4 buildings; furthest along: Slabs of Super Structure, 50%
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

SHITAL NAGAR is a Residential / Group Housing project by SANJAY SHYAMLAL VYAS in Aurangabad, Maharashtra, registered with MahaRERA as P51500048680 on 12 Jan 2023. Possession is promised by 31 Dec 2028.

At a glance

Project

  • NameSHITAL NAGAR
  • TypeResidential / Group Housing
  • Location
    • Padegoan
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500048680
  • ReraGenie IDRG-MH-03683

Builder

  • NameSANJAY SHYAMLAL VYAS
  • Entity typeIndividual
  • Other registrations4 more →
  • Completed2 of 5
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJan 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Jan 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings4 building records
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building Plan ANA40000
Building Type BNA20000
Building Type CNA20000
Building Type DNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

Building Plan A82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building Type B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building Type C41%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building Type D65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed45

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots45
Open Space45
BuildingOpen SpaceTotal
Building Plan A3232
Building Type B33
Building Type C33
Building Type D77

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,100 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Hiralal Sonaji BramhakarAurangabad (M Corp.)Aurangabad
Ahilyabai Hiralal BramhakarAurangabad (M Corp.)Aurangabad

Approvals and building plan

Permissible FSI1702.62
Proposed, not sanctioned1,703 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJalna Road Aurangabad

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSIDDIQUI M HARES
EngineerSIDDIQUI MOHD MUJTABA
Chartered AccountantA C SETHI & Associates
Chartered AccountantAbhishek K Kulkarni
PartnerRole in project
SANJAY SHYAMLAL VYAS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jul 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHITAL NAGAR 010724 C.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHITAL NAGAR 011024 C.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHITAL NAGAR 010125 C.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHITAL NAGAR Q4 310324.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHITAL NAGAR Q1 300624.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHITAL NAGAR Q2 011024.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHITAL NAGAR Q3 311224.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHITAL NAGAR Q1 300624.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHITAL NAGAR Q2 011024.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHITAL NAGAR Q3 311224.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 05-01-2024.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 3112.pdf18 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A 05-01-2024.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: disclose 3112.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 17-01-24.pdf18 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf23 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer 05102023.pdf20 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineering Certificate 2A.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23 (1).pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 March 23.pdf2 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 June 23.pdf2 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 23.pdf30 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 23.pdf30 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A MARCH 23.pdf30 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A JUNE 23.pdf30 Sep 2023
Disclosure of sold/ booked inventoryFile: Disclousre Shital Nagar 30 March 23.pdf30 Sep 2023
Disclosure of sold/ booked inventoryFile: Disclousre Shital Nagar 30 June 23.pdf30 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA Certificate (2).pdf30 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 23.pdf30 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: RERA NEW.pdf2 Jan 2023
Declaration in FORM BFile: RERA FORM B SV.pdf30 Dec 2022
Details of encumbrances concerned to FinanceFile: Declaration of No Enuncumbrance.pdf1 Dec 2022
Details of encumbrances concerned to LegalFile: Declaration of No Enuncumbrance.pdf1 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA Certificate.pdf1 Dec 2022
Proforma of Agreement for saleFile: ATS RERA - Shital Nagar.pdf1 Dec 2022
Proforma of Allotment letterFile: Allotment Letter.pdf1 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Seperate Bank Account.pdf1 Dec 2022
Deviation Report with respect to Allotment letterFile: No Deviation Letter for Allotment Letter.pdf1 Dec 2022
Deviation Report with respect to model copy of AgreementFile: No Deviation Letter for Agreement to Sale.pdf1 Dec 2022
Copy of the legal title reportFile: Full Search Report_compressed.pdf6 Aug 2022
Copy of the legal title reportFile: Format A Search Report.pdf16 Jul 2022
Layout approvalFile: Layout_compressed.pdf7 Jul 2022
Building plan approvalFile: 1 Building Plan A compressed.pdf7 Jul 2022
Building plan approvalFile: Building Plan B and C compressed.pdf7 Jul 2022
Building plan approvalFile: Row Houses D_compressed.pdf7 Jul 2022
Copy of Layout Approval (in case of layout)File: Layout_compressed.pdf7 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan A compressed.pdf7 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan B and C compressed.pdf7 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: Row Houses D_compressed.pdf7 Jul 2022
Declaration about Commencement CertificateFile: N Declaration For Commencement Certificate_compressed.pdf7 Jul 2022
Building plan approvalFile: 1 NA ORDER.pdf5 Jul 2022
Details of encumbrances concerned to FinanceFile: 1 CERSAI details.pdf5 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: 1 NA ORDER.pdf5 Jul 2022
CERSAI detailsFile: 1 CERSAI details.pdf5 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Commence Certificate.pdf1 Jul 2022
PAN CardFile: 1 PAN Card.pdf18 Jun 2022

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep SHITAL NAGAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Padegoan1,400+ in Aurangabad

2 kmSHITAL NAGARCompleted 6Lapsed / revoked 7Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: SANJAY SHYAMLAL VYAS

SANJAY SHYAMLAL VYAS has 5 registrations on MahaRERA, including NAMAN VIHAR and LAXMI TOWER -1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if SHITAL NAGAR is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHITAL NAGAR?

The registered promoter entity is SANJAY SHYAMLAL VYAS, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHITAL NAGAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHITAL NAGAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHITAL NAGAR?

The professionals named in the filing: Architect: SIDDIQUI M HARES; Engineer: SIDDIQUI MOHD MUJTABA; Chartered Accountant: A C SETHI & Associates; Chartered Accountant: Abhishek K Kulkarni. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHITAL NAGAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHITAL NAGAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHITAL NAGAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.