Home / Browse projects / Thane, Maharashtra / SHETH CNERGY PH 1 - UPTO 11TH FLOOR

Registered Litigation declared Commercial project

SHETH CNERGY PH 1 - UPTO 11TH FLOOR

By Sheth Developers Private Limited

RG-MH-15789 · RERA P51700023047 · Last updated on MahaRERA portal: 5 May 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 4 complaints at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken
  • Rs 85.00 crore secured on the land, in favour of VIVRITI CAPITAL LIMITED

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 48 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 41%
24 of 173Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 133 documents Report an error

SHETH CNERGY PH 1 - UPTO 11TH FLOOR is a Commercial project by Sheth Developers Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700023047 on 18 Nov 2019. Possession is promised by 28 Dec 2027. The completion date has moved by 48 months from the original filing. 149 of the 173 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameSHETH CNERGY PH 1 - UPTO 11TH FLOOR
  • TypeCommercial
  • Location
    • EASTERN EXPRESS HIGHWAY
    • PANCH PAKHADI
    • Thane (M Corp.)
    • Thane
    • 400601
  • Pincode400601
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700023047
  • ReraGenie IDRG-MH-15789

Builder

  • NameSheth Developers Private Limited
  • Entity typeCompany
  • CINU45200MH1993PTC070335
  • Managing DirectorAshwin Sheth
  • Other registrations9 more →
  • Completed3 of 10
  • Declared earlier projects11 →

Key dates

this monthRegisteredNov 2019First promiseDec 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Nov 2019
  • Promised completion28 Dec 2027
  • Revised completionRevised to 28 Dec 2027 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed133 files

Current status

86%149 of 173 units booked
67.4%Work done, per cost certificate

Figures as on 5 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHETH CNERGYNA770173173

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 41%.

SHETH CNERGY: 41% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure41%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed353

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots353
Closed/Covered353

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area6,416 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofVIVRITI CAPITAL LIMITED
Secured amountRs 85.00 crore
CERSAI search filedYes
Declared on10 Feb 2026

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI12504.0
Proposed, not sanctioned7,894 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMUNIR SUVARAT CHHAYA BLDG SAHAR ROAD KOLDONGARI ANDHERI EAST MUMBAI 69
Estimated costRs 60.45 cr
Cost incurredRs 40.76 cr
Work done67.43%
BuildingWingEstimatedIncurred
SHETH CNERGYNARs 54.87 crRs 40.76 cr
-NARs 5.58 cr-

Certifying professionals and partners11

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBipin Nannaware
ArchitectTEN FOLDS ARCHITECTS AND CONSULTANTS
EngineerMuhammad Shoeb Chouhan
EngineerUmesh N Tripathi
EngineerSmarty Lachhwani
EngineerAnas Shaikh
EngineerMr.Sandeep Magam
Chartered AccountantM B AGRAWAL & CO.
Chartered AccountantHaresh Bhanushali
Chartered AccountantHaresh Bhanushali and Associates
Chartered AccountantMr. Haresh Bhanushali
PartnerRole in project
Sheth Developers Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA27092401835Dec 2023 → Dec 2024

Reason as filed by the promoterThe applicant vide Development Agreement dated 01.10.2003 executed between Voltas Limited and the applicant, acquired rights to develop a land admeasuring aggregating to 1,15,018 sq. mtrs. The Applicant state out of the bigger property the land bearing Survey No. 35/4A admeasuring 434 sq. mtrs., land bearing Survey No. 35/8 admeasuring 5236.17 sq. mtrs., and land bearing survey no. 35/9/A admeasuring 746.30 sq. mtrs., was affected by Fire Bridget Station and MTRS reservation as per the sanctioned Development Plan for the City of Thane. Thane Municipal Corporation permitted the applicant to dev

EXT51700026018Dec 2023 → Dec 2027

Reason as filed by the promoterThe applicant vide Development Agreement dated 01.10.2003 executed between Voltas Limited and the applicant, registered at the office of sub-registrar Thane at Serial No. TNN1/06589/2003 on 03.10.2003 acquired rights to develop a land admeasuring aggregating to 1,15,018 sq. mtrs. The Applicant state out of the bigger property the land bearing Survey No. 35/4A admeasuring 434 sq. mtrs., land bearing Survey No. 35/8 admeasuring 5236.17 sq. mtrs., and land bearing survey no. 35/9/A admeasuring 746.30 sq. mtrs., (Hereinafter referred to as “The entire property”) was affected by Fire Bridget Statio

Litigation declared1

CaseCourtStatus
CP/320/2024/2024Bombay High CourtOngoing

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12500459SUNIL BABAN SHINDESheth Developers Private Limited11/02/2025
CC12500650Sanjay ThakurSheth Developers Private Limited24/02/2025
CC12500652Sanjay ThakurSheth Developers Private Limited24/02/2025
CC12503592sunil patilSheth Developers Private Limited08/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 28 Dec 2027

Documents filed133

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: CNERGY Thane Phase-2 Architects Certificate FORM -1.pdf5 May 2026
Withdrawal Update Form 2File: SHETH CNERGY PH 1.pdf5 May 2026
Withdrawal Update Form 3File: Form - 3_Cnergy Thane_Mar 26.pdf5 May 2026
Withdrawal Update Form 1File: FORM 1 CNERGY THANE PHASE 1.pdf28 Jan 2026
Withdrawal Update Form 2File: SHETH CNERGY PH-1.pdf28 Jan 2026
Withdrawal Update Form 3File: Form-3_Cnergy Thane_Dec 25_Signed.pdf28 Jan 2026
Form 5 (FY 2024-2025)File: Form - 5_Cnergy Thane_2024-25-Signed.pdf25 Nov 2025
Withdrawal Update Form 1File: FORM-1 - Sheth Cnergy ph 1.pdf21 Nov 2025
Withdrawal Update Form 2File: FORM 2 - SHETH CNERGY PH 1.pdf21 Nov 2025
Withdrawal Update Form 3File: Signed Form-3 Cnergy_Thane_Sept_2025.pdf21 Nov 2025
Form 2A (FY 2024-2025)File: FORM-2A - CENRGY PH -1.pdf5 Nov 2025
Withdrawal Update Form 1File: Form 1 - Cnergy Thane PH 1.pdf29 Sep 2025
Withdrawal Update Form 2File: Form - 2 Cnergy Thane.pdf29 Sep 2025
Withdrawal Update Form 3File: Form - 3 Cnergy Thane.pdf29 Sep 2025
Cnergy Thane29 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Sheth Cengry Phase-I.pdf29 Apr 2025
FORM 2 - Sheth Cnergy29 Apr 2025
Disclosure of sold/ booked inventoryFile: SHETH CNERGY-THANE 1.pdf29 Apr 2025
Disclosure of sold/ booked inventoryFile: CNERGY-THANE.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Cnergy Thane.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3- Sheth Cnergy Phase-I.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 - Sheth Cnergy-Thane.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CNERGY-PH 1--FORM -1-Architect Certificate.pdf29 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 Cynergy Thane.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Cnergy Thane.pdf29 Oct 2024
Disclosure of sold/ booked inventoryFile: CNERGY THANE.pdf29 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 - SHETH CNERGY-THANE.pdf8 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 - SHETH CNERGY THANE.pdf8 Oct 2024
Form 5 (FY 2023-2024)File: FORM-5 - SHETH CNERGY THANE.pdf30 Sep 2024
Disclosure of sold/ booked inventoryFile: CNERGY-THANE.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Cnergy Thane.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 - SHETH CNERGY.pdf26 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 -SHETH CNERGY PHASE-I.pdf26 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: CC Cnergy Thane 4 AND 5 FLOOR.pdf19 Jul 2024
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate Cnergy Thane.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: CNERGY THANE.pdf6 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 4.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Cnergy Thane.pdf23 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 - Sheth Cnergy.pdf22 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 - Cnergy Thane.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: CNERGY THANE (1).pdf31 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form- 1 Cnergy Thane.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 - Cnergy Thane.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 - Cnergy Thane.pdf16 Jan 2024
Building plan approvalFile: IOA.pdf26 Dec 2023
Layout approvalFile: 1.pdf26 Dec 2023
Layout approvalFile: 2.pdf26 Dec 2023
Layout approvalFile: 3.pdf26 Dec 2023
Copy of Layout Approval (in case of layout)File: 1.pdf26 Dec 2023
Copy of Layout Approval (in case of layout)File: 2.pdf26 Dec 2023
Copy of Layout Approval (in case of layout)File: 3.pdf26 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: IOA.pdf26 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: Revised Cc.pdf14 Dec 2023
Declaration about Commencement CertificateFile: CC Declaration.pdf14 Dec 2023
Declaration in FORM BFile: Form B.pdf14 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1) 1st quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2) 2nd quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3) 3rd quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4) 4th quater.pdf7 Dec 2023
Disclosure of sold/ booked inventoryFile: CNERGY THANE (1).pdf27 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form - 1 Cnergy Phase 1 ( Thane ).pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Cnergy Thane.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 - Cnergy Thane.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 - SHETH CNERGY-THANE.pdf8 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 CNERGY THANE.pdf19 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 CNERGY THANE.pdf19 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CYNERGY - Thane.pdf17 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CYNERGY - Thane.pdf17 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Cnergy Thane - Jan 23 to Mar 23.pdf25 Apr 2023
Disclosure of sold/ booked inventoryFile: Sheth Cnergy - Thane.pdf25 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Cnergy Thane - Jan 23 to Mar 23.pdf25 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1-Cynergy-Ph1-Jan'23-Mar'23.pdf12 Apr 2023
Disclosure of sold/ booked inventoryFile: Sheth Cnergy Thane.pdf2 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2 CNERGY THANE.pdf18 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3 CNERGY THANE.pdf18 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sheth Cnergy Thane.pdf12 Jan 2023
Declaration about Commencement CertificateFile: Sheth Cnergy Form D 10-2-20.pdf28 Nov 2022

Promoter's earlier projects10

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise7 delivered late1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SHETH BLUE IVYP51800001407DINDOSHI MALAD, Mumbai Suburban66Jul 2017OngoingNov 2027Registered original: Jun 2023Not due yet
SIGMAZANDU PHARMACTICAL GOKHALE ROAD SOUTH DADAR W MUMBAI - 25260-CompletedJul 2014Late, Dec 2014
VIVIANA MALLViviana Mall Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601240-CompletedMay 2013May 2013
Vasant LawnsVasant Lawns Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601465-CompletedMar 2012Late, Nov 2013
VASANT MARVELWESTRN EXPRESS HIGHWAY BORIWALI EAST MUMBAI - 66641-CompletedOct 2011Late, Jul 2012
CNERGYAPPASAHEB MARATHE MARG PRABHADEVI MUMBAI 2533-CompletedSep 2011Sep 2011
BEAUMONDEAPPASAHEB MARATHE MARG PRABHADEVI MUMBAI 25196-CompletedJul 2011Late, Jan 2012
VASANT GALAXYJUNCTION OF MG ROAD AND LINK ROAD BANGUR NAGAR GOREGAON WEST MUMBAI803-CompletedOct 2010Late, Mar 2011
VASANT VALLEYMALAD EAST MUMBAI 96127-CompletedJun 2010Late, Dec 2010
VASANT GARDENSWAPNA NAGARI OFF LBS MARG MULUND WEST MUMBAI 801,825-CompletedMar 2007Late, Dec 2007

How this compares with Thane

86%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 48 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHETH CNERGY PH 1 - UPTO 11TH FLOOR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PANCH PAKHADI7,600+ in Thane

2 kmSHETH CNERGY PH 1 - UPTOCompleted 160Lapsed / revoked 71Other 170Dot size: filed unitsN

Filed coordinates, straight-line distance. 401 registered projects within 2 km.

Builder: Sheth Developers Private Limited

Sheth Developers Private Limited has 10 registrations on MahaRERA, including VASANT FIONA and CLARION. Its filings disclose 11 earlier MahaRERA projects: declares 2 of 9 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SHETH CNERGY PH 1 - UPTO 11TH FLOOR is delayed beyond 28 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHETH CNERGY PH 1 - UPTO 11TH FLOOR?

The registered promoter entity is Sheth Developers Private Limited, a company as per the filing. Its CIN U45200MH1993PTC070335 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHETH CNERGY PH 1 - UPTO 11TH FLOOR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHETH CNERGY PH 1 - UPTO 11TH FLOOR?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHETH CNERGY PH 1 - UPTO 11TH FLOOR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHETH CNERGY PH 1 - UPTO 11TH FLOOR?

The professionals named in the filing: Architect: Bipin Nannaware; Architect: TEN FOLDS ARCHITECTS AND CONSULTANTS; Engineer: Muhammad Shoeb Chouhan; Engineer: Umesh N Tripathi; Engineer: Smarty Lachhwani; Engineer: Anas Shaikh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHETH CNERGY PH 1 - UPTO 11TH FLOOR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHETH CNERGY PH 1 - UPTO 11TH FLOOR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHETH CNERGY PH 1 - UPTO 11TH FLOOR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.