Registered No litigation declared Residential / Group Housing project

SHETH AVALON - PHASE 2

By Sheth Developers Private Limited

RG-MH-93787 · RERA P51700015517 · Last updated on MahaRERA portal: 7 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken
  • Rs 275.00 crore secured on the land, in favour of TATA CAPITAL HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 24 months from the original
16 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 95%
85 of 241Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 146 documents Report an error

SHETH AVALON - PHASE 2 is a Residential / Group Housing project by Sheth Developers Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700015517 on 7 Mar 2018. Possession is promised by 30 Dec 2027. The completion date has moved by 24 months from the original filing. 156 of the 241 units on this registration are recorded sold or booked, and 16 of 33 construction stages are filed complete.

At a glance

Project

  • NameSHETH AVALON - PHASE 2
  • TypeResidential / Group Housing
  • Location
    • W E HIGHWAY POKKHARAN RD NO 2
    • MAJIWADA
    • Thane (M Corp.)
    • Thane
    • 400601
  • Pincode400601
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700015517
  • ReraGenie IDRG-MH-93787

Builder

  • NameSheth Developers Private Limited
  • Entity typeCompany
  • CINU45200MH1993PTC070335
  • Managing DirectorAshwin Sheth
  • Other registrations9 more →
  • Completed3 of 10
  • Declared earlier projects11 →

Key dates

this monthRegisteredMar 2018First promiseDec 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Mar 2018
  • Promised completion30 Dec 2027
  • Revised completionRevised to 30 Dec 2027 (originally 30 Dec 2025)
  • Buildings3 building records
  • Documents filed146 files

Current status

65%156 of 241 units booked
75.0%Work done, per cost certificate

Figures as on 7 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER ANA504488593
TOWER BNA494488492
TOWER CNA332856056

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 95%.

TOWER A56%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises37%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TOWER B56%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises37%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TOWER C89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 7 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes35%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed506

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots506
Closed/Covered506
BuildingClosed/CoveredTotal
TOWER A206206
TOWER B200200
TOWER C100100

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area6,147 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofTATA CAPITAL HOUSING FINANCE LIMITED
Secured amountRs 275.00 crore
Declared on17 Sep 2025

Approvals and building plan

Sanctioning authorityTHANE MUNICIPAL CORPORATION
Permissible FSI45905.78
Proposed, not sanctioned6,214 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK LIMITED, CONWOOD HOUSE, FILM CITY ROAD, GOREGAON, MUMBAI 400063
Estimated costRs 270.00 cr
Cost incurredRs 202.55 cr
Work done75.02%
BuildingWingEstimatedIncurred
TOWER ANARs 89.11 crRs 66.96 cr
TOWER BNARs 87.86 crRs 70.52 cr
TOWER CNARs 75.74 crRs 61.82 cr
-NARs 17.28 crRs 3.25 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBipin Nannaware
EngineerSMARTY LACHHWANI
EngineerPankaj N Bhagat
EngineerMuhammad Shoeb Chouhan
Chartered AccountantHaresh Bhanushali
Chartered AccountantM B AGRAWAL & CO.
PartnerRole in project
Sheth Developers Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30092517987Dec 2025 → Dec 2027

Reason as filed by the promoterAs per order of the Hon'ble Chairman (MahaRERA) Dated 12/12/2025 we request you kindly to grant us extension till 30/12/2027

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Feb 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Feb 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Aug 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2027

Documents filed146

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 146 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: CC Revalidation Note Sheet_26871_signed.pdf7 Aug 2026
Commencement certificateFile: CERTIFICATE (1).pdf7 Aug 2026
Commencement certificateFile: Declaration About Commencemnt Certificate (Format-D) Avalon.pdf7 Aug 2026
Withdrawal Update Form 1File: SHETH AVALON PH 2.pdf7 Aug 2026
Withdrawal Update Form 2File: SHETH AVALON PH 2.pdf7 Aug 2026
Withdrawal Update Form 3File: Form 3_Avalon A to C_June 26.pdf7 Aug 2026
Withdrawal Update Form 1File: Avalon Phase-2 Architects Certificate FORM -1.pdf4 May 2026
Withdrawal Update Form 2File: SHETH AVALON-PH 2.pdf4 May 2026
Withdrawal Update Form 3File: Form - 3_Avalon A to C_Mar 26.pdf4 May 2026
Withdrawal Update Form 1File: FORM 1 AVALON PHASE 2.pdf2 Feb 2026
Withdrawal Update Form 2File: SHETH AVALON PH-2.pdf2 Feb 2026
Withdrawal Update Form 3File: Form-3_Avalon A to C_Dec 25_Signed.pdf2 Feb 2026
Form 5 (FY 2024-2025)File: Form 5.pdf7 Nov 2025
Withdrawal Update Form 1File: form1 sheth avalon ph 2.pdf6 Nov 2025
Withdrawal Update Form 2File: SHETH AVALON PHASE 2.pdf6 Nov 2025
Withdrawal Update Form 3File: Signed Form-3 Avalon-A to C_Sept_2025.pdf6 Nov 2025
Form 2A (FY 2024-2025)File: FORM-2A - Sheth Avalon Phase 2.pdf5 Nov 2025
Withdrawal Update Form 1File: Form 1 - Avalon Phase 2.pdf30 Sep 2025
Withdrawal Update Form 2File: SHETH AVALON - FORM 2.pdf30 Sep 2025
Withdrawal Update Form 3File: Form - 3 Avalon A to C.pdf30 Sep 2025
Avalon PH 229 Apr 2025
Certificates of CA (Form 3)File: FORM 3 -Sheth Avalon.pdf29 Apr 2025
FORM 2 - Sheth Avalon A,B,C29 Apr 2025
Disclosure of sold/ booked inventoryFile: AVALON-A TO C 1.pdf29 Apr 2025
Disclosure of sold/ booked inventoryFile: AVALON.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: AVALON.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: AVALON.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Avalon PH 2.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Avalon PH 2.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Avalon PH 2.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2- Avalon.pdf16 Jan 2025
Certificates of CA (Form 3)File: FORM-3- Sheth Avalon Phase-II.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2- Avalon.pdf16 Jan 2025
Certificates of CA (Form 3)File: FORM-3- Sheth Avalon Phase-II.pdf16 Jan 2025
Certificates of CA (Form 3)File: FORM-3- Sheth Avalon Phase-II.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2- Avalon.pdf16 Jan 2025
Declaration about Commencement CertificateFile: Declaration of CC.pdf7 Jan 2025
Declaration about Commencement CertificateFile: Declaration of CC.pdf7 Jan 2025
Declaration about Commencement CertificateFile: Declaration of CC.pdf7 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AVALON--FORM -1-Architect Certificate.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Avalon Phase II.pdf29 Oct 2024
Certificates of CA (Form 3)File: Form - 3 Avalon Phase II.pdf29 Oct 2024
Disclosure of sold/ booked inventoryFile: AVALON (A - C).pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AVALON--FORM -1-Architect Certificate.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Avalon Phase II.pdf29 Oct 2024
Certificates of CA (Form 3)File: Form - 3 Avalon Phase II.pdf29 Oct 2024
Disclosure of sold/ booked inventoryFile: AVALON (A - C).pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AVALON--FORM -1-Architect Certificate.pdf29 Oct 2024
Certificates of CA (Form 3)File: Form - 3 Avalon Phase II.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Avalon Phase II.pdf29 Oct 2024
Disclosure of sold/ booked inventoryFile: AVALON (A - C).pdf29 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 - SHETH AVALON -PHASE II.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 - SHETH AVALON -PHASE II.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 - SHETH AVALON -PHASE II.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: AVALON Ph 2.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Avalon Ph 2.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 - AVALON-A,B,C.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM -3 -SHETH AVALON PHASE-II.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 4.pdf3 May 2024
Disclosure of sold/ booked inventoryFile: AVALON.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Sheth Avalon PH 2.pdf23 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 - Avalon A B C.pdf22 Apr 2024
Certificates of CA (Form 3)File: FORM-3 - Sheth Avalon Phase II.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: AVALON.pdf2 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form- 1 Avalon Ph 2.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 - Avalon A To C.pdf16 Jan 2024
Certificates of CA (Form 3)File: Form - 3 - Avalon A To C.pdf16 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1) 1st quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2) 2nd quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3) 3rd quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4) 4th quater.pdf7 Dec 2023
Disclosure of sold/ booked inventoryFile: AVALON PHASE-2 ATO C.pdf27 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - AVALON.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 - Avalon - II.pdf18 Oct 2023
Certificates of CA (Form 3)File: Form - 3 - Avalon - II.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 - SHETH AVALON - PHASE-II.pdf8 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 -AVALON.pdf19 Jul 2023

Promoter's earlier projects10

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise7 delivered late1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SHETH BLUE IVYP51800001407DINDOSHI MALAD, Mumbai Suburban66Jul 2017OngoingNov 2027Registered original: Jun 2023Not due yet
SIGMAZANDU PHARMACTICAL GOKHALE ROAD SOUTH DADAR W MUMBAI - 25260-CompletedJul 2014Late, Dec 2014
VIVIANA MALLViviana Mall Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601240-CompletedMay 2013May 2013
Vasant LawnsVasant Lawns Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601465-CompletedMar 2012Late, Nov 2013
VASANT MARVELWESTRN EXPRESS HIGHWAY BORIWALI EAST MUMBAI - 66641-CompletedOct 2011Late, Jul 2012
CNERGYAPPASAHEB MARATHE MARG PRABHADEVI MUMBAI 2533-CompletedSep 2011Sep 2011
BEAUMONDEAPPASAHEB MARATHE MARG PRABHADEVI MUMBAI 25196-CompletedJul 2011Late, Jan 2012
VASANT GALAXYJUNCTION OF MG ROAD AND LINK ROAD BANGUR NAGAR GOREGAON WEST MUMBAI803-CompletedOct 2010Late, Mar 2011
VASANT VALLEYMALAD EAST MUMBAI 96127-CompletedJun 2010Late, Dec 2010
VASANT GARDENSWAPNA NAGARI OFF LBS MARG MULUND WEST MUMBAI 801,825-CompletedMar 2007Late, Dec 2007

How this compares with Thane

65%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHETH AVALON - PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAJIWADA7,600+ in Thane

2 kmSHETH AVALON - PHASE 2Completed 161Lapsed / revoked 72Other 183Dot size: filed unitsN

Filed coordinates, straight-line distance. 416 registered projects within 2 km.

Builder: Sheth Developers Private Limited

Sheth Developers Private Limited has 10 registrations on MahaRERA, including VASANT FIONA and CLARION. Its filings disclose 11 earlier MahaRERA projects: declares 2 of 9 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SHETH AVALON - PHASE 2 is delayed beyond 30 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHETH AVALON - PHASE 2?

The registered promoter entity is Sheth Developers Private Limited, a company as per the filing. Its CIN U45200MH1993PTC070335 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHETH AVALON - PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHETH AVALON - PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHETH AVALON - PHASE 2?

The professionals named in the filing: Architect: Bipin Nannaware; Engineer: SMARTY LACHHWANI; Engineer: Pankaj N Bhagat; Engineer: Muhammad Shoeb Chouhan; Chartered Accountant: Haresh Bhanushali; Chartered Accountant: M B AGRAWAL & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHETH AVALON - PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHETH AVALON - PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHETH AVALON - PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.