Home / Browse projects / Thane, Maharashtra / Sheetal Utsav

Registered No litigation declared Mixed project

Sheetal Utsav

By DGS Township Pvt Ltd

RG-MH-42419 · RERA PM1330002500978 · Last updated on MahaRERA portal: 9 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken
  • Allotment letter deviates from the model form

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Apr 2031Possession promisedmoved 4 months from the original
34 of 104Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 19 documents Report an error

Sheetal Utsav is a Mixed project by DGS Township Pvt Ltd in Thane, Maharashtra, registered with MahaRERA as PM1330002500978 on 26 Sep 2025. Possession is promised by 30 Apr 2031. The completion date has moved by 4 months from the original filing. 70 of the 104 units on this registration are recorded sold or booked.

At a glance

Project

  • NameSheetal Utsav
  • TypeMixed
  • Location
    • Survey No 168 (old) Survey No 39/1/A PT (New)
    • Mira-Bhayandar
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PM1330002500978
  • ReraGenie IDRG-MH-42419

Builder

  • NameDGS Township Pvt Ltd
  • Entity typeCompany
  • CINU74120MH2014PTC254452
  • GSTIN27AAECD9891R1ZJ
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsSURAJDEV DUDHNATH SHUKLA, Ishwardev Dudhnath Shukla, INDRADEV DUDHNATH SHUKLA, ROHIT SURAJDEV SHUKLA
  • Other registrations3 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredSep 2025First promiseDec 2030Revised toApr 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Sep 2025
  • Promised completion30 Apr 2031
  • Revised completionRevised to 30 Apr 2031 (originally 31 Dec 2030)
  • Buildings1 building record
  • Documents filed19 files

Current status

67%70 of 104 units booked
12.7%Work done, per cost certificate

Figures as on 9 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sheetal UtsavNA999014104

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Sheetal Utsav:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 9 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed178

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots178
Stilt / Ground58
Podiums / Upper Parking Floor120

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,477 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Sep 2025
LandownerVillageDistrict
Amogh CHS Ltd-Thane

Approvals and building plan

Sanctioning authorityMira Bhayandar Municipal Corporation
Permissible FSI12059.26
Proposed, not sanctioned5,205 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchN.G.N. VAIDYA MARG, MUMBAI - 400023
Estimated costRs 64.00 cr
Cost incurredRs 8.13 cr
Work done12.71%
BuildingWingEstimatedIncurred
Sheetal UtsavNARs 32.00 crRs 4.07 cr
-NARs 32.00 crRs 4.07 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnish & Associates
EngineerSaroj Vishvakarma
EngineerAkash Pandey
Chartered AccountantSDBA & Co.
PartnerRole in project
DGS Township Pvt Ltd-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PM1330002500978/WarDec 2030 → Apr 2031

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Sep 2025
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2031

Documents filed19

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A.pdf9 Sep 2026
Withdrawal Update Form 1File: FORM 1.pdf26 Aug 2026
Withdrawal Update Form 2File: FORM 2 - Utsav June 26.pdf26 Aug 2026
Withdrawal Update Form 3File: Sheetal Utsav Form 3 JUNE_compressed.pdf26 Aug 2026
Withdrawal Update Form 1File: FORM 1.pdf17 Aug 2026
Withdrawal Update Form 2File: FORM 2 - Utsav Phase 2 (1).pdf17 Aug 2026
Withdrawal Update Form 3File: Sheetal Utsav Form 3 JUNE_compressed.pdf17 Aug 2026
Withdrawal Update Form 1File: Form-1.pdf7 May 2026
Withdrawal Update Form 2File: Utsav FORM 2 - March 26.pdf7 May 2026
Withdrawal Update Form 3File: USTAV FORM3_MARCH 2026_compressed.pdf7 May 2026
Withdrawal Update Form 1File: Form 1-sep.pdf2 May 2026
Withdrawal Update Form 2File: Form-2.pdf2 May 2026
Withdrawal Update Form 3File: DGS Ustav From 3.pdf2 May 2026
Withdrawal Update Form 1File: Form 1 Utsav Dec 25 (1).pdf30 Apr 2026
Withdrawal Update Form 2File: Form 2 Utsav Dec 25.pdf30 Apr 2026
Withdrawal Update Form 3File: AMOG_USTA_FORM-3_DEC 2025_compressed.pdf30 Apr 2026
Declaration and undertaking (Annexure A)File: Annexure A.pdf19 Sep 2025
Layout approvalFile: latest Plan - converted.pdf18 Sep 2025
Building plan approvalFile: latest Plan - converted.pdf18 Sep 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Sheetal SahyogP51800054809Kurar Malad (E), Mumbai Suburban211Feb 2024OngoingJun 2027Not due yet

How this compares with Thane

67%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 4 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sheetal Utsav on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mira-Bhayandar7,600+ in Thane

2 kmSheetal UtsavCompleted 101Lapsed / revoked 72Other 95Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: DGS Township Pvt Ltd

DGS TOWNSHIP PVT LTD has 4 registrations on MahaRERA, including SHEETAL TAPOVAN and SHEETAL ANUPAM. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Sheetal Utsav is delayed beyond 30 Apr 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sheetal Utsav?

The registered promoter entity is DGS Township Pvt Ltd, a company as per the filing. Its CIN U74120MH2014PTC254452 and GSTIN 27AAECD9891R1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sheetal Utsav?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sheetal Utsav?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sheetal Utsav?

The professionals named in the filing: Architect: Anish & Associates; Engineer: Saroj Vishvakarma; Engineer: Akash Pandey; Chartered Accountant: SDBA & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sheetal Utsav?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sheetal Utsav. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sheetal Utsav to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.